New Jersey Administrative Code
Printable Version
(168 kB / pdf )

| N.J.A.C. 5:30-5.1 to
5.5. |
Encumbrance Accounting and Certifications
of Availability of Funds |
|
5:30-5.1 |
General authority |
|
5:30-5.2 |
Encumbrance systems |
|
5:30-5.3 |
General requirements |
|
5:30-5.4 |
Procedure |
|
5:30-5.5 |
Methods of accounting for and certifying
available funds for special situations |
| |
| N.J.A.C.
5:30-11.1 to 11.10 |
Change Orders and Open-End Contracts |
|
5:30-11.1 |
Application, compliance and penalties |
|
5:30-11.2 |
Definitions |
|
5:30-11.3 |
General requirements for all change
orders |
|
5:30-11.4 |
Procedures for minor field (site)
modifications |
|
5:30-11.5 |
General procedures for change orders |
|
5:30-11.6 |
Change orders for professional services
and extraordinary unspecifiable services |
|
5:30-11.7 |
Change orders for materials, supplies
and equipment which are part of construction contract |
|
5:30-11.8 |
Change orders for construction, reconstruction
and major repair contracts |
|
5:30-11.9 |
Procedures for change orders which
exceed 20 percent limitation |
|
5:30-11.10 |
Open-end contracts |
SUBCHAPTER 5. ENCUMBRANCE ACCOUNTING AND CERTIFICATIONS OF AVAILABILITY
OF FUNDS
5:30-5.1 General authority
(a) This subchapter shall apply to all government agencies
subject to the authority of the Local Finance Board pursuant to
the Local Budget Law (N.J.S.A. 40A:4-1 et seq.) or the Local Authorities
Fiscal Control Act (N.J.S.A. 40A:5A-1 et seq.). For the purpose
of this subchapter, such government agencies shall be referred to
as local units.
(b) Every governing body and chief executive officer shall take
reasonable steps as necessary so that all officials and employees
responsible for the administration of public contracts are aware
of and are able to comply with the requirements of the law and these
rules.
5:30-5.2 Encumbrance systems
(a) All local units except those subject to the Local Authorities
Fiscal Control Act (N.J.S.A. 40A:5A-1 et seq.) shall maintain an
encumbrance accounting system for its current fund as follows:
- The system shall be designed at a minimum to record charges
to amounts appropriated for "Other Expenses" in the
same or greater level of detail as "Other Expenses"
are maintained in the adopted budget. This shall be done in such
a way to record charges against amounts appropriated at the time
the charges are authorized so that the funds allocated for such
purposes are reserved and cannot be used for other charges within
that line item. Examples of such authorization actions include
the issuance of a purchase order or the execution of a contract
- If the local unit budget uses a greater detail level through
the use of object accounts, transactions shall be encumbered at
the object level detail.
- Local units shall maintain internal controls that ensure that
all purchases to "Other Expenses" or other non-salary
line items shall be sequentially numbered either through pre-printed
multiple copy purchase orders or a computerized system that produces
appropriate purchasing internal control.
(b) Systems similar to those described in (a) above, appropriately
adapted to meet local needs, shall be used for capital, trust, and
utility funds.
(c) The Director of the Division of Local Government Services shall
make available such technical documents as may be advisable to local
units to provide further guidance on encumbrance systems.
(d) The provisions of this section codify and continue the provisions
of Technical Accounting Directive No. 1, issued in April of 1985
and effective January 1, 1986.
5:30-5.3 General requirements
(a) The chief financial officer of a local unit, appointed
pursuant to N.J.S.A. 40A:9-140.1 et seq. or N.J.S.A. 40A:9-28.1
et seq., shall be responsible for determining the availability of
sufficient funds for all contracts and amendments thereto. The delegation
of this duty by the chief financial officer does not relieve him
or her of this responsibility.
(b) The governing bodies of all other local units shall designate
by resolution or ordinance, as appropriate, an individual to serve
as the certifying finance officer. The certifying finance officer
shall be responsible for determining the availability of sufficient
funds for all contracts and amendments thereto. The delegation of
this duty by the certifying finance officer does not relieve him
or her of this responsibility.
(c) If a purchase or the execution of a contract does not require,
either by State law or any State or local regulation, specific authorization
by formal action of the governing body, then the individual approving
the contract or release of the purchase order shall ascertain from
the chief financial officer or certifying finance officer, as appropriate,
that there are available sufficient uncommitted appropriations to
provide for the payment. The administrative official or employee
shall be so authorized pursuant to N.J.S.A. 40A:11-3.
5:30-5.4 Procedure
(a) The following procedure shall be utilized for the certification
of funds when a contract is to be awarded by the governing body
of the local unit:
- The chief financial officer or certifying finance officer, as
appropriate, charged with the responsibility of maintaining the
financial records of the contracting unit shall certify in writing
to the governing body the availability or lack thereof of adequate
funds for each contract which is pending approval by the governing
body. Said certification shall designate specifically the line
item appropriation(s) of the official budget to which the contract
will be properly charged, ensuring that the same funds shall not
be certified as available for more than one pending contract.
Said officer shall be solely responsible for the accuracy of the
certification.
- No resolution authorizing the entering into of any contract
pursuant to N.J.S.A. 40A:11-1 et seq. or any other law for the
expenditure of public funds to a vendor shall be enacted unless
it shall recite that such a certificate showing availability of
funds has been provided. The resolution shall specify the exact
line item appropriation(s) or ordinance which shall be charged.
- The certification of availability of funds shall be attached
to the original copy of the resolution or ordinance and kept in
the files of the municipal clerk, clerk of the board of chosen
freeholders or secretary to the governing body.
- Before a governing body approves a resolution or ordinance authorizing
the entering into of a contract, the local unit's attorney shall
be satisfied that a certificate of availability of funds has been
provided.
- A local unit's governing body shall not enter into or execute
a contract unless it has been presented with a written certification
from its chief financial officer or certifying finance officer,
as appropriate, stating the availability of sufficient funds for
the contract(s) pending approval by the governing body.
- When a contract is issued as a purchase order or amendment thereto,
the certification of availability of funds shall be executed through
the budgetary accounting encumbrance process.
(b) When a contract is awarded and a resolution of the governing
body is not required, the availability of funds shall be certified
by the chief financial officer or certifying finance officer shall
make an appropriate entry into the local units encumbrance
system pursuant to N.J.A.C. 5:30-5.1 and 5.2 prior to the issuance
of a contract.
5:30-5.5 Methods of accounting
for and certifying available funds for special situations
(a) Temporary budget: When a local unit is operating under
a temporary budget, as provided for in N.J.S.A. 40A:4-19, it may
enter into a contract for a period extending beyond the time period
funded in the temporary budget, subject to the following:
- The full cost of the contract for that fiscal year shall be
certified against the temporary budget, which must contain sufficient
appropriations therefor; or
- If the full cost of that year is not charged against the temporary
budget, at least the pro-rated amount reflecting all liability
to be incurred during the temporary budget period must be charged
and certified, and the contract must contain a clause making its
continuation past such date subject to the appropriation of sufficient
funds. Immediately after the final budget adoption, a certificate
of available funds shall be prepared for the remaining balance
and filed with the original ordinance or resolution.
(b) Open end contracts: When a contract provides for certain goods
or services to be provided upon request, up to an established maximum,
and the local unit is not obligated to order, accept or pay for
said goods or services except when it orders them, then the certification
of available funds shall be as follows:
- The full maximum amount covered by the contract shall be charged
against the budget at the time the contract is awarded, and the
full amount shall be certified; or
- No amount shall be chargeable or certified until such time as
goods or services are ordered or otherwise called for. Prior to
incurring the liability by placing the order, the certification
of available funds shall be made by the chief financial officer
or certifying finance officer, as appropriate, and attached to
the file copy of the purchase order or other such document. It
shall be the responsibility of the official responsible for issuing
the purchase order to notify and seek the certification of availability
of funds from the chief financial officer or certifying finance
officer, as appropriate.
(c) Contracts up to 12 months not coinciding with fiscal year:
When a contract is awarded for a period of up to 12 months not coinciding
with the established fiscal year of the local unit, the following
methods shall be followed for purposes of accounting and providing
the certification of available funds.
- f the contract is for a professional service or is essentially
a single undertaking or project with one basic work project required
(such as, but not limited to, contracts for revaluation, codification,
management studies and feasibility surveys), rather than being
divisible into separate steps or actions which in themselves are
independently acceptable as complete work products, then the full
cost of the contract shall be chargeable to and certified against
the budget or appropriation of the year in which the contract
is awarded. This method may also, at local option, be followed
for contracts described in (c)2 below.
- If the contract is not of the character described in (c)1 above,
and provides for goods or services to be provided at separate
intervals over the contract period, then the amounts for which
liability is to be incurred shall be charged and certified to
the two respective years' appropriations at the times, as appropriate,
of the contract being awarded (with respect to the amount from
the first fiscal year); the adoption of the temporary budget and
the adoption of the final budget (for the remainder of the contract
for the second fiscal year).
(d) Multi-year contract requirements are as follows:
- Contracts entered into pursuant to N.J.S.A. 40A:11-15 for periods
in excess of 12 months shall be charged and certified as follows:
- For construction and related services authorized by N.J.S.A.
40A:11-15(9), to the budget or appropriation in full at the
time of contract award;
- For other contracts, to the respective budgets in accordance
with the time(s) at which the respective work or services
are performed or liability for payment otherwise incurred,
and subject to such requirements of this section as might
apply with respect to temporary budgets, open-end contracts
or contracts not commencing at the beginning of the fiscal
year.
- All multi-year leases and contracts except contracts specifically
exempted pursuant to N.J.S.A. 40A:11-15 shall contain a clause
making them subject to the availability and appropriation annually
of sufficient funds as may be required to meet the extended obligation
or contain an annual cancellation clause.
(e) Advance award of contracts: No contract shall be awarded in
one fiscal year if the date on which it properly takes effect falls
in the next fiscal year unless the contract includes a provision
making it subject to the availability and appropriation of sufficient
funds in the year in which it takes effect.
(f) Payment from proceeds shall be as follows:
- Under the circumstances when a contractual liability may be
lawfully incurred and a payment may lawfully be made without an
appropriation, such as for professional services for liquidation
or foreclosure of tax title liens as provided by N.J.S.A. 40:50-6,
the certification of available funds should recite that fact and
cite the statute.
- Contracts for services to be paid from savings generated by
or from State or Federal aid funds not yet received and appropriated
are not permitted unless an appropriation is made prior to the
time the expenditure of funds is authorized.
SUBCHAPTER 11. CHANGE ORDERS AND OPEN-END CONTRACTS
5:30-11.1 Application,
compliance and penalties
(a) Unless specifically stated to the contrary, the rules
in this subchapter apply to all local government agencies that are
encompassed by the definition of contracting unit in N.J.S.A. 40A:11-2(1)
by whatever name called, and referred to in this subchapter as contracting
units.
(b) Every governing body and chief executive officer shall take
all steps necessary so that all officials and employees shall be
aware of and comply with the requirements of these rules.
5:30-11.2 Definitions
The following words and terms, as used in this subchapter,
shall have the following meaning, unless the context clearly indicates
otherwise.
"Change order" means a properly prepared document authorized
by the governing body which directs and authorizes a vendor providing
goods or performing services to a contracting unit pursuant to a
contract awarded by governing body resolution to change the quantity
or character of goods provided or services performed from that originally
specified or estimated and to correspondingly change the payment
due therefore.
"Chief executive officer" means the elected or appointed
individual with the highest level of administrative authority of
the contracting unit. In the case of a municipality, this may refer
to the mayor as appropriate to the form of government; in the case
of a county, the director of a board of chosen freeholders, county
executive, or county manager as appropriate to the form of government;
in the case of an authority, the chair of the authority; and, in
the case of a fire district, the president or other presiding officer
of the board of fire commissioners.
"Open-end contracts" means those contracts for which
price bids were solicited on a unit basis because exact quantities
needed were not known at the time bids were sought. Such contracts,
when advertised and awarded, must include a minimum and a maximum
number of units that can be ordered for each item under the contract.
Zero is an acceptable minimum. Orders placed under such open-end
contracts shall not be considered as change orders for purposes
of this section, but shall be subject to the requirements specified
in N.J.A.C. 5:30-11.10. Examples include, but are not limited to,
blacktopping and office supplies such as stationery.
5:30-11.3 General requirements
for all change orders
(a) No changes in quantities, work performed, services rendered,
materials, supplies or equipment delivered or provided shall be
authorized, permitted or accepted except by the procedures established
herein. All change orders unless otherwise stated in this subchapter
shall be subject to the following:
- Each change order shall be in writing and shall be numbered
consecutively (beginning with number one) and attached to the
original purchase order or contract for each project.
- Change orders which result in payment reduction below the originally
contracted price may be made by locally established procedure,
provided that any change orders increasing cost on the same contract
shall include reference to such reductions.
- Quantities of items or work shall not be changed in such a manner
as to nullify the effect of the competitive determination of lowest
responsible bidder which was made at the time of contract award,
if at said time the changes could have been reasonably foreseen.
- Responsibility required by these rules to be exercised specifically
by the governing body, including authorization of change orders,
shall not be delegated except for minor field (site) modifications
pursuant to N.J.A.C. 5:30-11.4.
- Change orders may be executed by the representative appointed
by the governing body but the responsibility for the authorization
of change orders shall not be delegated by the governing body
except for minor field (site) modifications pursuant to N.J.A.C.
5:30-11.4.
- Change orders shall be used to change the number of units or
items originally advertised and contracted for, provided that:
- Unit prices or a price methodology were sought in the original
specifications and included in the contract;
- The original specification and the contract included a provision
that the unit prices could be so used; and
- If (a)6i and ii above were not contained in the original
specification, a change order shall not be issued.
- Change orders shall not be used to substantially change the
quality or character of the items or work to be provided, inasmuch
as such would have been a determining factor in the original bidding.
- Change orders shall not serve the purpose of escalation clauses
and, therefore, shall not be utilized to effectuate upward price
adjustments.
- Total number of change orders executed for a particular contract
shall not cause the originally awarded contract price to be exceeded
by more than 20 percent unless otherwise authorized by these rules.
- If proposed change orders do exceed the 20 percent limitation
of (a)9 above, no work shall be performed or purchases made until
the procedures of N.J.A.C. 5:30-11.9 have been completed. If the
governing body determines issuance of the change order is not
justifiable, a new contract shall be executed in accordance with
the Local Public Contracts Law.
- Before authorizing any change orders resulting in additional
expenditures, the availability of funds shall be certified in
writing by the chief financial officer or certifying finance officer,
as appropriate.
- The 20 percent limitation of (a)9 above shall not apply to emergency
situations as defined within N.J.S.A. 40A:11-6.
- Change order authorizations shall not be withheld until the
completion of the entire project.
5:30-11.4 Procedures for
minor field (site) modifications
The governing body shall be required to authorize all change
orders, except that minor field (site) modifications (for example,
additional fill stone needed, modifications of footings, additional
rock blasting) may be authorized, provided that they do not affect
the overall scope of work of the contract, by the designated representative
of the governing body. These change orders shall result only in
minor price increases to the originally awarded contract price.
5:30-11.5 General procedures
for change orders
(a) The governing body approval process for change orders
shall be as follows:
- The chief executive officer of the contracting unit or his or
her designee shall file with the governing body a request for
the change order, stating the facts involved and indicating that
the proposed change order may be allowed under these rules. If
the request and justification are prepared by other than an official
of the contracting unit, they must be countersigned by the chief
executive officer or his or her designee.
- The governing body shall take such steps as it may find appropriate
to assure that a change is necessary and that the work will be
completed.
- The governing body shall then pass a resolution authorizing
a written amendment to a contract covering the change(s) to be
made. The exact form of this amendatory contract shall be at the
discretion of the contracting unit attorney.
- The resolution described in (a)3 above shall be passed before
execution of the change order. No work shall be performed or purchases
made on the involved phase of the contract until the resolution
is passed.
5:30-11.6 Change orders
for professional services and extraordinary unspecifiable services
(a) This section shall apply only to change orders for professional
and extraordinary, unspecifiable services contracts.
(b) In case of conflict with the general requirements of N.J.A.C.
5:30-11.3, the specific language of this section shall prevail but,
otherwise, the requirements of N.J.A.C. 5:30-11.3 shall be satisfied.
(c) Changes should be within the scope of activities of the original
contract, and not for the purpose of undertaking new or different
work or projects. Changes in payments for activities within the
scope of activities of the contract shall be in accordance with
a schedule of specific charges or rates contained in the contract
and shall be effectuated by a written change order authorized by
the governing body. If such a schedule is not included in the contract,
the contract should be amended to provide for same.
(d) The 20 percent limitation of N.J.A.C. 5:30-11.3(a)9 shall not
apply to professional and consultant contracts.
(e) If the change is not within the scope of activities of the
original contract and the contract was awarded without competitive
bidding being required by law or rule, as is the case for professional
services and certain authorized extraordinary unspecifiable services
in accordance with N.J.S.A. 40A:11-5(1)(a)(i), any change beyond
the original scope of activities shall be made by amendatory contract
approved by the governing body.
5:30-11.7 Change orders
for materials, supplies and equipment which are part of construction
contract
(a) The requirements of this section shall apply only to change
orders for materials, supplies and equipment which are part of construction
contracts.
(b) In case of conflict with the general requirements of N.J.A.C.
5:30-11.3, the specific language of this section shall prevail but,
otherwise, the requirements of N.J.A.C. 5:30-11.3 shall be satisfied.
(c) Change orders for materials, supplies and equipment items which
are part of a contract which is primarily a construction contract
shall be processed in accordance with the rules governing construction
contracts. Contracts awarded on a unit price basis (including, but
not limited to, asphalt overlays, curbing) as an open-end contract
shall be handled under the section dealing with open-end contracts.
However, contracts awarded for the paving, construction or reconstruction
of specifically described streets, parking lots, or sections shall
be treated as construction contracts.
5:30-11.8 Change orders
for construction, reconstruction and major repair contracts
(a) The requirements of this section shall apply only to the
particular type of contract in question.
(b) In case of conflict with the general requirements of N.J.A.C.
5:30-11.3, the specific language of this section shall prevail but,
otherwise, the requirements of N.J.A.C. 5:30-11.3 shall be satisfied.
(c) Change orders for construction, reconstruction and major repair
contracts shall be limited to the following types:
- Unforeseeable problems, which are defined as conditions or circumstances
that could not be foreseen at the time the specifications were
written and the contract awarded; provided that a substantial
amount of the construction would be delayed, which would result
in substantial increases in costs above the original contract
amount or substantial inconvenience to the public if bidding were
to be required; and
- Minor modifications to effect economies, improve service or
resolve minor problems with affected property owners.
(d) Change orders for construction, reconstruction and major repair
contracts shall not be made for the following:
- Changes that materially expand upon the size, nature or scope
of the project as it was originally described in the bid specifications;
or
- Extra work that could reasonably be effectuated by a separately
bid contract without unduly disrupting the basic work or imposing
adverse cost consequences.
5:30-11.9 Procedures for
change orders which exceed 20 percent limitation
(a) General provisions regarding the procedures for change
orders which exceed the 20 percent limitation are as follows:
- The procedures in this section shall only be followed when a
particular change order on any type of contract, except professional
and extraordinary unspecifiable service contracts, will cause
the total amount of change orders executed for the particular
contract to exceed the originally awarded contract price by more
than 20 percent. The purpose of the procedures is to allow for
such a change only in limited instances. Such a change shall not
be permitted when the factual circumstances make it reasonably
possible to execute a new contract for the additional work. Such
a change may be allowed, for example, when an unforeseen circumstance
or differing site condition is combined with a situation which
renders execution of a new contract an unreasonable interference
with the efficient completion of the work.
- Generally such change orders are not justifiable and the ready
issuance of them by contracting units would constitute an abuse
of these rules.
(b) A written certification justifying the performance of the work
or the furnishing of the services which would necessitate issuance
of such a change order shall be filed by the contractor with the
chief executive officer or designee. This certification shall include
an explanation of the factual circumstances which necessitate issuance
of the change order; a statement indicating why these circumstances
could not have been foreseen; a statement indicating why issuance
of the change order would be in the best interests of the contracting
unit and would not constitute an abuse of these rules; and, if the
nature of the change order is technical, the certification shall
include a certified statement from the contractor's appropriate
expert, such as an engineer or architect. This statement shall explain
in detail the factual circumstances which necessitate issuance of
the proposed change order. A rewrite or paraphrase of the rules
in this subchapter is not acceptable.
(c) The governing body approval process for change orders which
exceed the 20 percent limitation is as follows:
- The chief executive officer or his or her designee shall file
a request for the change order with the governing body. This request
shall include a statement indicating why the proposed change may
be allowed under this subchapter. A copy of the certification
required under (b) above must also be attached to the request.
- If the certification required pursuant to (b) above includes
a certified statement from an engineer or other expert as required
by (b) above, the request to the governing body shall also include
a statement from the contracting unit's engineer or an official
or employee with the appropriate expertise. This statement shall
explain in detail the factual circumstances which justify issuance
of the proposed change order. A rewrite or paraphrase of the rules
in this subchapter is not acceptable.
- The governing body shall take appropriate steps to assure that
the change order is proper and allowable under this subchapter.
- The governing body shall then pass a resolution authorizing
a written amendatory contract to be entered into covering the
change(s) to be made. The exact form of this amendatory contract
shall be at the discretion of the contracting unit attorney.
- The resolution described in (c)4 above shall be passed before
execution of the change order.
- The governing body shall cause to be printed once, in an official
newspaper, a brief notice indicating the additional amount to
be expended, the original contract price, the nature of the original
and additional work and why it is necessary to expend the additional
funds. A copy of the advertisement shall also be filed with the
clerk or secretary of the governing body and be available for
inspection by the public.
(d) The clerk or secretary of the governing body of each contracting
unit shall report to the Director on an appendix to the contracting
units annual budget all change orders from the previous fiscal
year which exceeded the 20 percent limitation. This report shall be
made on a form provided by the Director. A summary of the report shall
be included as supplemental material in the annual audit of the contracting
unit.
5:30-11.10 Open-end contracts
(a) The issuance of purchase orders pursuant to an open-end
contract shall be considered to be the carrying out of the contract
and not a change order. The following requirements shall apply:
- Purchase orders under open-end contracts shall not be used for
purposes such as changing the quality or character of items to
be provided, nor to exceed the maximum number(s) of items or units
provided for in the original specifications and contract. Such
changes would constitute a change order.
- Each time a purchase order is placed, the contracting agent
shall ensure that funds are available for the purchase through
either an encumbrance or certification of availability of funds.
- Purchase orders shall be placed by the contracting agent, subject
to such controls or approval requirements as the governing body,
chief executive or other administrative officer may lawfully impose.
|