| Renewal of DPCC/DCR Plans is required
every 3 years from the last "approval" or "conditional
approval" of DPCC/DCR plans (7:1E-4.9(a)). One copy
must be sent to NJ DEP 180 days prior to expiration
of those plans.
New major facilities must submit
a DPCC/DCR plan at least 180 days prior to the anticipated
operational date (NJAC 7:1E-4.5(d)). Plans must
be approved and implemented prior to operating the
facility. A written notice must be submitted 60
days before the start of any new construction/installation,
substantial modification or replacement of any above-ground
storage tank, above-ground enclosed storage space,
leak detection, or other monitoring or safety system except for certain construction/modifications
contained in an upgrading schedule of an approved
DPCC plan (7:1E-4.8(a)).
Any changes to facility design,
operation or maintenance that could materially affect
facility potential to discharge a Hazardous Substance
must be reported to the Department by way of an
amendment to the DPCC/DCR plan within 30 days. Changes
not subject to certification and approval requirements
of amendments must be reported to the Department
within 30 days.
Please note that a facility may
be subject to a Spill Compensation and Control tax
even if it is not required to prepare plans for
DPCC/DCR. |