|
Community
Relations Site
Highlights
New Jersey Natural Gas (NJNG) Long Branch Plant Site
Update
Long Branch, Monmouth County
February 2006
PDF
Version of the Update [pdf 114 Kb]
Community
Relations Site Listing's Entry
Site
Highlights Entry
This report is provided in response to a request by the Concerned
Citizens Coalition of Long Branch (CCC) for monthly updates on work
conducted and planned at four areas associated with the former Long
Branch Manufactured Gas Plant (MGP).* These areas are:
- the former MGP (including the former Conrail properties, the
eastern off-site property, and the former Jerry Morgan Park)
- the off-site portion of Troutmans Creek that flows north of
the MGP
- residential areas where the community has expressed concern
about potential soil contamination (Long Branch Avenue, Seaview
Avenue, Grant Court and Ellis Avenue)
- the former Seaview Manor housing complex
All work is consistent with NJDEP's Technical Requirements for
Site Remediation, which were developed to ensure remedial actions
protect human health and the environment.
* For historical information about activities that NJDEP
and NJNG have conducted at these areas, please refer to the monthly
updates NJDEP has provided to CCC since January 2005. |
1) Long Branch Plant
Red Brick Building
NJNG continues to evaluate trichloroethene (TCE) and perchloroethylene
(PCE) contamination in the soil beneath the concrete pad where the red
brick building was located, as well as potential ground water impacts.
NJNG submitted a Remedial Investigation Report (RIR) that summarizes the
findings of its investigation of the soil and ground water in February
2006. NJDEP is evaluating the RIR and preparing comments. NJNG has proposed
deferring submission of the Remedial Action Work Plan (RAWP) for this
area until after NJDEP approved the RIR. NJDEP is drafting a response
to this proposal, which will be sent in early March 2006.
The remedy would essentially consist of removing the remaining concrete
slabs, underground storage tanks (if any exist) and contaminated soil,
followed by capping the area consistent with the rest of the site. If
ground water impacts are found, they will be addressed as part of the
site-wide ground water remedial action.
Soil Gas Investigation
NJNG is conducting a soil gas investigation to evaluate potential vapor
intrusion at the Talco and Atlantic Plumbing Supply Company (APSC) buildings.
NJNG recently finished sampling near the Talco property and submitted
an RIR summarizing the findings of the soil gas investigation for this
area in February 2006. NJDEP is currently reviewing the RIR and expects
to issue comments in the spring of 2006. A court order issued as a result
of the litigation between NJNG and APSC states that NJNG cannot have access
to the APSC property until APSC vacates it, which should occur in September
2006. Investigative efforts at APSC will commence after this date.
Ground Water Investigation
In December 2005 NJNG’s contractor began field activities to delineate
the dense non-aqueous phase liquid (DNAPL) and conduct ground water treatment
studies, pursuant to its Remedial Investigation Work Plan/Ground Water
Pilot Test Work Plan. NJNG recently proposed submitting the RIR for this
work by the March 6, 2006 due date and deferring submission of the RAWP
until after NJDEP approves the RIR. NJDEP is drafting a response to this
proposal, which will be sent in early March 2006.
On-Site Portion of Troutmans Creek
Remediation of the southern on-site portion of the Troutmans Creek is
pending since this work cannot be implemented until NJNG is allowed access
to the APSC property. As noted above, these efforts will start after September
2006.
2) Troutmans Creek
NJDEP required NJNG to submit an Interim Remedial Action Work Plan (IRAWP)
in February 2006 detailing its proposals to implement the following:
- complete remediation of the corrugated metal pipe culvert in accordance
with NJDEP’s conditional approval letter dated 11/3/04;
- remove all contaminated sediments from the concrete box culvert beneath
Seaview Avenue continuing north within the creek channel to the southern
end of the Joline Avenue bridge (at a minimum);
- remove the free/residual product from the creek and the creek banks.
NJNG proposed submitting a draft RAWP instead of the IRAWP on February
20, 2006; however, NJDEP did not receive either a draft RAWP or IRAWP
by this date. NJDEP is drafting a letter informing NJNG that they are
out of compliance.
NJNG is also expected to submit an Ecological Risk Assessment (ERA),
including, but not limited to, conducting a benthic community survey,
sediment toxicity testing and collecting sediment samples for analysis
of site-related contaminants. The ERA is necessary to complete the Remedial
Investigation and satisfy NJDEP’s “Technical Requirements
for Site Remediation.” NJNG has proposed submitting a draft ERA
Work Plan by March 23, 2006. NJDEP finds the proposal acceptable and will
send a letter agreeing to this schedule in early March 2006.
3) Off-Site Residential Areas
NJDEP collected soil samples from the right-of-ways along Long Branch
Avenue, Seaview Avenue and Ellis Avenue and from Grant Court in May 2005
and analyzed the samples for volatile organic compounds, semi-volatile
organic compounds, total petroleum hydrocarbons and metals. NJDEP is completing
an RIR summarizing its findings and plans to submit copies to CCC members
in March 2006.
The results of the off-site soil investigation revealed that two shallow
samples collected from beneath the pavement on Ellis Avenue contained
semi-volatile organic compounds and a metal at levels exceeding NJDEP’s
soil cleanup criteria. It also revealed that two deep soil samples (collected
more than six feet below grade) at Grant Court contained semi-volatile
organic compounds and metals above NJDEP’s soil cleanup criteria.
In addition, one surface soil sample near a dumpster in the Grant Court
housing development contained arsenic above NJDEP’s soil cleanup
criteria. The Long Branch Housing Authority (LBHA) placed gravel over
the area near the dumpster and installed a temporary fence around it.
Additional sampling will be required to complete the delineation at these
areas.
4) Seaview Manor
NJDEP finished reviewing the Remedial Action Report (RAR) that NJNG
submitted for Block 400, Lot 7 in December 2005 and issued a letter requesting
that NJNG furnish additional information and documentation within 90 days.
NJNG subsequently determined that the excavation for the unrestricted
use remedial action was not implemented as approved. In January 2006 NJNG
re-mobilized its contractors to finish excavating the contaminated soil
at Block 400, Lot 7, and document their compliance with NJDEP’s
“Technical Requirements for Site Remediation” via submission
of a revised RAR. The revised RAR was received in late January 2006 and
the RAR for the remaining parcels (except the culvert) was received in
February 2006. NJDEP is reviewing the documents and expects to issue comments
in the spring of 2006.
Culvert Status
NJNG removed two feet of soil from the culvert area and capped it during
the remedial action for Block 400, Lots 6 and 7. The removal of the culvert
and any underlying contamination will occur in the spring and summer of
2006.
|