|
Community
Relations Site
Highlights
New Jersey Natural Gas (NJNG) Long Branch Plant Site
Update
Long Branch, Monmouth County
August 2006
PDF
Version of the Update [pdf 123 Kb]
Community
Relations Site Listing's Entry
Site
Highlights Entry
This report is provided in response to a request by the Concerned
Citizens Coalition of Long Branch (CCC) for monthly updates from
the Site Remediation and Waste Management Program (SRWM) on work
conducted and planned at four areas associated with the former Long
Branch Manufactured Gas Plant (MGP). These areas are:
- the former MGP (including the former Conrail properties, eastern
off-site property, and former Jerry Morgan Park)
- the off-site portion of Troutmans Creek that flows north of
the MGP
- residential areas where the community has expressed concern
about potential soil contamination (Long Branch Avenue, Seaview
Avenue, Grant Court and Ellis Avenue)
- the former Seaview Manor housing complex
All work is consistent with NJDEP’s Technical Requirements
for Site Remediation, which were developed to ensure remedial actions
protect human health and the environment.
For historical information about activities that NJDEP and NJNG
have conducted at these areas, please refer to the monthly updates
NJDEP has provided to CCC since January 2005. The updates are available
at www.nj.gov/dep/srp/community/highlights.htm.
For more information, see NJDEP’s Environmental Justice web
page at http://www.nj.gov/dep/ej.
|
1) Long Branch Plant
Red Brick Building
In July 2006 NJDEP issued comments on NJNG’s Remedial Investigation
Report (RIR) and Addendum Letter for this area, which were submitted in
January 2006 and April 2006, respectively. Based on its review of these
documents, NJDEP has determined that additional soil sampling must be
conducted to verify that the volatile organic compounds (PCE and TCE)
and polycyclic aromatic hydrocarbons in the soil have been fully delineated.
NJDEP gave NJNG two options for accomplishing this task: mobilize for
another phase of delineation sampling or submit a Remedial Action Work
Plan (RAWP) that includes post-remediation sampling. NJNG has elected
to submit an RAWP with post-remediation sampling. NJDEP expects to receive
the RAWP in the fall of 2006.
Atlantic Plumbing and Supply Company (ASPC)
NJDEP approved an RAWP to conduct an unrestricted use remedial action
for the APSC property in April 2005. However, implementation of the RAWP
was delayed while NJNG negotiated with the owners of APSC to obtain access
to the property. The court order issued as a result of litigation between
NJNG and APSC states NJNG can have access to the property when APSC vacates
it in September 2006.
In May 2006, NJNG submitted a revised RAWP that consolidates the plans
for the APSC property, the on-site portion of Troutmans Creek and the
remainder of the former MGP site into a single RAWP. This approach enables
NJNG to bid these remedial actions as a single scope of work without affecting
the September 2006 start date. NJDEP has reviewed the revised RAWP and
plans to issue written comments in September 2006.
On-Site Portion of Troutmans Creek
Remediation of the southern on-site portion of the Troutmans Creek had
been delayed since this work could not be implemented until NJNG is allowed
access to the APSC property. Now that negotiations between NJNG and APSC
are over, these efforts are scheduled to start in September 2006, as noted
above. NJNG plans to complete the remediation by March 2007.
Soil Gas Investigation
NJNG submitted an RIR summarizing the findings of the soil gas investigation
for the Talco property in February 2006. NJDEP issued a letter approving
the RIR in May 2006. Pursuant to the Revised RAWP dated May 2006, NJNG
plans to demolish the APSC building, eliminating the need to evaluate
vapor intrusion for the current structure. NJNG must still evaluate all
of the former MGP as specified by NJDEP’s Vapor Intrusion Guidance
on future use of undeveloped parcels.
Ground Water Investigation
NJNG submitted a Draft RIR/Draft Ground Water Pilot Testing Report (GWPTR),
a Draft Remedial Action Selection Report (RASR) and a Draft Phase II Ground
Water Monitoring Report (GWMR) in March 2006. The Draft RIR details efforts
to define the extent of the on-site dense non-aqueous phase liquid (DNAPL)
and the Draft GWPTR summarizes the results of the ground water treatment
studies. The Draft RASR presents the remedies NJNG plans to select to
remediate the DNAPL and dissolved ground water contamination. NJDEP reviewed
these documents and issued a conditional approval letter for the Phase
II Ground Water Monitoring Report and a comment letter for the remaining
documents in July 2006. The approval and comment letters required NJNG
to conduct the following tasks:
- Continue the pilot test study to obtain data to support the remedy
selection and report the data in the quarterly ACO progress report
- Complete delineation of the DNAPL plume
- Complete delineation of the dissolved contaminant plume
NJNG is required to submit an RIWP to address items 2 and 3 in November
2006
2) Off-Site Portion of Troutmans Creek
NJNG submitted a Draft Ecological Risk Assessment (ERA) Work Plan in
March 2006 that outlined proposals for tasks that include, but are not
limited to conducting a benthic community survey, sediment toxicity testing,
and sediment sampling for analysis of site-related contaminants. NJDEP
issued a conditional approval for the ERA Work Plan in May 2006. NJNG
conducted the first sampling event in June 2006 and will perform the second
one in September 2006.
NJNG submitted a Draft RAWP for Troutmans Creek in March 2006. NJDEP
reviewed the Draft RAWP and CCC’s comments on this document and
issued a comment letter on August 3, 2006. NJDEP advised NJNG in the comment
letter that it must first complete the ERA and delineate soil and product
contamination in the creek before submitting a revised RAWP for this area.
The revised RAWP for the off-site portion of Troutmans Creek is due in
April 2007.
3) Off-Site Residential Areas
NJDEP issued an RIR in February 2006 that summarized its findings of
the soil sampling it conducted on Long Branch Avenue, Seaview Avenue,
Ellis Avenue and Grant Court. The results of the soil investigation revealed
that two shallow samples collected from beneath the pavement on Ellis
Avenue contained semi-volatile organic compounds and a metal at levels
exceeding NJDEP’s soil cleanup criteria. It also revealed that two
deep soil samples (collected more than six feet below grade) at Grant
Court contained semi-volatile organic compounds and metals above NJDEP’s
soil cleanup criteria. In addition, one surface soil sample near a dumpster
in the Grant Court housing development contained arsenic above NJDEP’s
soil cleanup criteria.
The Long Branch Housing Authority (LBHA) placed gravel over the area
near the dumpster and installed a temporary fence around it. LBHA received
NJDEP approval for its sampling plan to complete the soil delineation
for Grant Court and conducted the sampling in April 2006. LBHA submitted
an RIR and RIR Addendum to NJDEP in May 2006 and June 2006, respectively.
NJDEP issued its approval of these documents in August of 2006. The approval
letter confirmed that the contamination in this area was adequately delineated
and requested that LBHA submit a RAWP to address the contamination. NJDEP
expects to receive the RAWP in late summer or early fall of 2006.
4) Seaview Manor
NJNG submitted a Revised RAR for Block 400, Lot 7 in January 2006 and
SRWM reviewed numerous aspects of the Revised RAR during February and
March 2006. Based on its review, SRWM has worked closely with the Land
Use Regulation Program to resolve issues related to the CAFRA permit for
the new Seaview Manor. These efforts have allowed the contractor to resume
construction of the housing units. NJDEP issued a conditional approval
of the Revised RAR in April 2006.
NJNG submitted an RAR for the remainder of the LBHA properties and adjacent
properties in February 2006. NJDEP reviewed the RAR and CCC’s comments
on the submittal and issued a comment letter on August 18, 2006. NJDEP
is requiring NJNG to submit a RIWP with proposals to delineate newly identified
soil contamination at Block 400, Lot 6, an RAR Addendum to address several
deficiencies in the RAR, as well as several revised deed notices. The
RIWP Addendum is due in late 2006 and NJDEP is recommending that NJNG
integrate the RAR Addendum for this area into the RAR Addendum for the
culvert area, which is due in January 2007.
Culvert Status
NJNG removed two feet of soil from the culvert area and capped it during
the remedial action for Block 400, Lots 6 and 7. The removal of the culvert
and any underlying contamination will be implemented in late September
or early October 2006.
Related Information
LBHA Activities
LBHA submitted a Remedial Investigation Report (RIR) in May 2006 that
summarizes the soil and ground water sampling it conducted in the vicinity
of the two underground storage tanks (USTs) formerly located on Block
400, Lot 7. NJDEP reviewed this report and issued a comment letter on
August 1, 2006 that required LBHA to conduct a vapor intrusion evaluation
for this area. NJDEP expects to receive a report on the vapor intrusion
evaluation in late September or early October 2006.
LBHA also submitted a RAWP for Block 400 Lot 7 in February 2006 that
details plans for installation the storm water and sanitary sewer lines.
NJDEP issued a conditional approval of the RAWP in May 2006. This work
was completed in August of 2006, along with decontamination of the sheet
piling installed within Troutmans Creek. NJDEP expects to receive an RAR
documenting all of these activities in October 2006.
|