|
Community
Relations Site
Highlights
New Jersey Natural Gas (NJNG) Long Branch Plant Site
Update
Long Branch, Monmouth County
November 2006
PDF
Version of the Update [pdf 130 Kb]
Community
Relations Site Listing's Entry
Site
Highlights Entry
This report is provided in response to a request by the Concerned
Citizens Coalition of Long Branch (CCC) for monthly updates from
the Site Remediation and Waste Management Program (SRWM) on work
conducted and planned at four areas associated with the former Long
Branch Manufactured Gas Plant (MGP). These areas are:
- the former MGP (including the former Conrail properties, eastern
off-site property, and former Jerry Morgan Park)
- the off-site portion of Troutmans Creek that flows north of
the MGP
- residential areas where the community has expressed concern
about potential soil contamination (Long Branch Avenue, Seaview
Avenue, Grant Court and Ellis Avenue)
- the former Seaview Manor housing complex
All work is consistent with NJDEP’s Technical Requirements
for Site Remediation, which were developed to ensure remedial actions
protect human health and the environment.
For historical information about activities that NJDEP and NJNG
have conducted at these areas, please refer to the monthly updates
NJDEP has provided to CCC since January 2005. The updates are available
at http://www.nj.gov/dep/srp/community/highlights.htm.
For more information, see NJDEP’s Environmental Justice web
page at http://www.nj.gov/dep/ej.
|
1) Long Branch Plant
Red Brick Building
Based on its review of NJNG’s Remedial Investigation Report (RIR)
and Addendum Letter for this area, NJDEP has determined that additional
soil sampling must be conducted to verify that the volatile organic compounds
(PCE and TCE) and polycyclic aromatic hydrocarbons in the soil have been
fully delineated. To address this requirement, NJNG submitted a Draft
Revised Remedial Action Work Plan (RAWP) that includes post-remediation
sampling on November 22, 2006. NJDEP is reviewing the document and expects
to issue comments in January 2007.
APSC, On-Site Portion of Troutmans Creek and remainder of
MGP
NJNG took possession of the APSC property in September 2006 and has finished
demolishing the building. NJDEP received a revised RAWP Addendum outlining
NJNG’s plans to remediate these areas on October 31, 2006. NJDEP
reviewed the document and issued an approval letter on November 28, 2006.
NJNG is expected to submit a Draft Revised Remedial Action Report (RAR)
summarizing the remedial work conducted in this area on January 14, 2008.
Soil Gas Investigation
NJNG’s February 2006 RIR on the soil gas investigation concluded
vapor intrusion was not a concern for the Talco property and NJDEP has
accepted this conclusion. NJNG has demolished the building at the APSC
property, thereby eliminating the need to evaluate vapor intrusion for
the structure. NJNG must still evaluate all of the former MGP as specified
by NJDEP’s Vapor Intrusion Guidance on future use of undeveloped
parcels.
Ground Water Investigation
NJDEP received a Draft Remedial Investigation Work Plan (RIWP) on October
26, 2006 containing proposals in response to the NJDEP’s comment
letters dated July 21, 2006, July 28, 2006, and August 18, 2006. In summary,
the proposals address requirements to further delineate both dissolved
ground water contamination and dense non-aqueous phase liquid (DNAPL).
The RIWP also contains proposals to conduct post-remediation soil sampling
on Block 400 Lot 6 and additional soil investigation within the Seaview
Avenue right of way. NJNG is also continuing the pilot test study to obtain
data to support remedy selection and reports the data to NJDEP in quarterly
ACO progress reports. NJDEP plans to complete its review by late December
2006.
2) Off-Site Portion of Troutmans Creek
NJNG has completed the fieldwork described in the Draft Ecological Risk
Assessment (ERA) Work Plan dated March 2006. NJNG will submit a Draft
RIR (ERA) summarizing its findings on January 18, 2007.
NJDEP has reviewed NJNG’s Draft RAWP for Troutmans Creek dated
March 2006 and issued a comment letter in August 2006. NJDEP advised NJNG
that it must first complete the ERA and delineate soil and product contamination
in the creek (see next paragraph) before submitting a revised RAWP for
this area. The revised RAWP for the off-site portion of Troutmans Creek
was due in April 2007, but now NJNG will submit this RAWP on March 13,
2007.
In September 2006, NJDEP issued a conditional approval letter for NJNG’S
RIWP outlining plans to delineate free and residual product and soil contamination
on the banks of Troutmans Creek. NJNG initiated the fieldwork described
in the RIWP on October 30, 2006 and will submit an RIR summarizing its
findings to NJDEP on March 13, 2007.
3) Off-Site Residential Areas
NJDEP issued an RIR in February 2006 that summarized the findings of
the soil sampling it conducted on Long Branch Avenue, Seaview Avenue,
Ellis Avenue and Grant Court. The investigation revealed that two shallow
soil samples collected from beneath the pavement on Ellis Avenue contained
semi-volatile organic compounds and a metal at levels exceeding NJDEP’s
soil cleanup criteria. It also revealed that two deep soil samples (collected
more than six feet below grade) at Grant Court contained semi-volatile
organic compounds and metals above NJDEP’s soil cleanup criteria.
In addition, one surface soil sample near a dumpster in the Grant Court
housing development contained arsenic above NJDEP’s soil cleanup
criteria.
The Long Branch Housing Authority (LBHA) placed gravel over the area
near the dumpster and installed a temporary fence around it. LBHA subsequently
conducted a remedial investigation to delineate the extent of contamination
on Grant Court. NJDEP issued an approval letter for LBHA’s RIR and
RIR Addendum for the deep soil contamination at Grant Court in August
2006. The approval letter confirmed that LBHA adequately delineated the
soil contamination in this area and requested LBHA submit an RAWP for
Grant Court. NJDEP received the RAWP on October 11, 2006 and plans to
complete its review in December 2006.
NJDEP will investigate the extent of the soil contamination beneath the
pavement at Ellis Avenue. The timing of NJDEP’s investigation is
still being discussed, but will likely be scheduled for late spring/early
summer 2007.
4) Seaview Manor
NJDEP issued three separate no further action (NFA) letters for Block
400 Lot 7, all of which were dated October 31, 2006. One was for the unrestricted
use remedial action NJNG conducted for areas A and B, another was for
the restricted use remedial action NJNG conducted on the southeastern
corner of this parcel, and the last was for the restricted use remedial
action performed for LBHA’s two former underground storage tanks.
NJNG reviewed NJNG’s February 2006 RAR for the remainder of the
LBHA properties and adjacent properties and issued a comment letter in
August 2006. NJDEP required NJNG to submit an RIWP Addendum with proposals
to satisfy the post-remediation sampling requirements for Block 400, Lot
6 and further investigate potential soil contamination beneath Seaview
Avenue. The RIWP Addendum was integrated into the RIWP described under
the ground water investigation section of this update and was received
by NJDEP on October 26, 2006. NJDEP plans to complete its review of the
RIWP Addendum in December 2006.
Culvert Status
NJNG initiated a remedial action to remove the culvert and underlying
contamination in late in October 2006. Substantial completion of the remedial
action has been achieved with activities such as contractor demobilization,
restoration and reporting currently underway or pending. NJNG plans to
submit the RAR Addendum for the culvert area to NJDEP on April 9, 2007.
Related Information
LBHA Activities
Installation of the storm water and sanitary sewer lines was completed
in August 2006, along with decontamination of the sheet piling installed
within Troutmans Creek. The RAR documenting all of these activities was
due in November 2006, but NJDEP granted LBHA’s request to extend
the due date and the RAR will now be submitted on December 15, 2006.
|