Planned Advertisements


6-Month Look Ahead


IMPORTANT
Read our disclaimer before downloading or attempting
to use any of the files from this site
.


  

Transportation System Management (TSM)

Project/Work Description


UPC #176110

Rt. 1, Forrestal Rd to Wynwood Dr./Whispering Woods Blvd, ITS

This is a TSM limited scope project for installing ITS devices – Dynamic Message Signs (DMS), Camera Surveillance System (CSS), Fiber Optic Cables and their integration to DOT network for communication to Central Control System on Rt. 1. 

Proposed Advertised Month July, 2018

Project Details

Middlesex County/Plainsboro Twp, South Brunswick Twp

MP 12.93-16.96

Estimate Range  $1,000,000 - $5,000,000


UPC #176080

Traffic Surveillance Camera Communication Conversion

This is a TSM limited scope project for converting legacy cameras statewide from serial communication to Ethernet communication and the phase out of the antiquated American Dynamics Video Switches and associated hardware.

Proposed Advertised Month August, 2018

Project Details

Statewide

Estimate Range  $5,000,000 - $10,000,000

  

Maritime Resources

Project/Work Description


DP #18472

Maintenance Dredging of the Metedeconk Channel Complex

Navigational dredging with placement in open water.

Proposed Advertised Month July, 2018

Project Details

Ocean County

Estimate Range  $10,000,000 - $20,000,000

 

Capital Program Management (CPM)

Project/Work Description


UPC #153100

Rt 47, Bridge over Rt 295

The center pier and both abutments will be raised approximately 2 feet to achieve a minimum 16'-6'' clearance (minimum vertical underclearance is 16'-6'' over freeways as per AASHTO).

The PPA consists of replacing the existing concrete deck, parapets and superstructure in stages.

* The abutment bridge seats, backwalls and pier cap will be modified as necessary to accept the new continuous steel beams and the new vertical clearance.

* The deck will be made composite with the superstructure and the bearings will be replaced and designed seismically retrofitted to withsand a seismic event.

Proposed Advertised Month June, 2018

Project Details

Gloucester County/Westville Boro

MP 74.0-74.0

Estimate Range  $5,000,000 - $10,000,000


UPC #183290

Rt 18 SB, Rt 138 to Deal Rd

Limited Scope Pavement Preservation

Pavement preservation is needed on Route 18 using fog seal, chip seal and slurry seal resurfacing. The Pavement Recommendation does not include bridge deck, approach slab, or any structures. No guide rail or ADA improvments are included in the project scope. The actual limit for pavement treatment shall be adjusted with respect to pavement change in the field.

Proposed Advertised Month June, 2018

Project Details

Monmouth County/Wall Twp, Neptune Twp, Ocean Twp

MP 5-14-11.37

Estimate Range  $1,000,000 - $5,000,000


UPC #183380

Rt 78, Washington Valley Rd to Plainfield Ave (CR 663)

Limited Scope Pavement Preservation

Pavement preservation is needed on Route 78 using HPTO and slurry seal resurfacing. The Pavement Recommendation does not include bridge deck, approach slab, or any structures. No guide rail or ADA improvments are included in the project scope. The actual limit for pavement treatment shall be adjusted with respect to pavement change in the field.

Proposed Advertised Month June, 2018

Project Details

Somerset County/Various Municipalities

MP 30.87-42.77

Estimate Range  $10,000,000 - $20,000,000


UPC #183430

Rt 287, CR 533 (Main St) to Rt 78 Ramp

Limited Scope Pavement Preservation

Pavement preservation is needed on Route 287 using HPTO and slurry seal resurfacing. The Pavement Recommendation does not include bridge deck, approach slab, or any structures. No guide rail or ADA improvments are included in the project scope. The actual limit for pavement treatment shall be adjusted with respect to pavement change in the field.

Proposed Advertised Month June, 2018

Project Details

Somerset County/Bridgewater Twp, Bedminster Twp

MP 13.0-21.0

Estimate Range  $10,000,000 - $20,000,000


UPC #183400

Rt 22 WB, Ramp from Rt 78 EB to CR 523 (Oldwick Rd)

Limited Scope Pavement Preservation

Pavement preservation is needed on Route 22 using chip seal and slurry seal resurfacing. The Pavement Recommendation does not include bridge deck, approach slab, or any structures. No guide rail or ADA improvments are included in the project scope. The actual limit for pavement treatment shall be adjusted with respect to pavement change in the field.

Proposed Advertised Month June, 2018

Project Details

Hunterdon County/Clinton Boro, Lebanon Boro, Readington Twp

MP 19.25-25.61

Estimate Range  $5,000,000 - $10,000,000


UPC #143560

Rt 22, Commons Way to Route 287

Concrete Pavement Repair and a 1" HPTO Overlay on the Westbound. 1" HPTO treatment for the Eastbound direction.

Proposed Advertised Month July, 2018

Project Details

Somerset County/Bridgewater Twp

MP 34.3-36.87

Estimate Range  $5,000,000 - $10,000,000


UPC #114090

Rt 22 EB, Rt 78 to Rt 28 (CR 614, Easton Turnpike)

This is a limited scope project that will resurface and rehabilitate 12.4 miles of pavement on US Route 22 Eastbound in Hunterdon County (Clinton Township, Lebanon Borough and Readington Township) and in Somerset County (Branchburg Township and Bridgewater Township).

The overall project limits are from the I-78 Interchange (MP 19.25) in Clinton Township, Hunterdon County to west of Country Club Road (MP 32.53) in Bridgewater Township, Somerset County. Work will be done between MP 19.25 to MP 31.41, ramp work only between MP 32.05 and MP 32.20 and work resumes between MP 32.44 to MP 32.53.

Structures located within the project limits are: 1005-150, 1005-151, 1005-152, 1005-153, 1005-154, 1005-155, 1005-156, 1005-157, 1005-158, 1005-159, 1005-160, 1005-161, 1005-162, 1801-150, 1801-152, 1801-153, 1801-155.

Proposed Advertised Month August, 2018

Project Details

Hunterdon County/Clinton Twp, Lebanon Boro, Readington Twp

MP 19.25-31.41

Estimate Range  $5,000,000 - $10,000,000


UPC #124110

Rt 40 NJ Turnpike to E Quillytown Rd

Limited Scope Pavement Resurfacing Project.

Proposed Advertised Month August, 2018

Project Details

Salem County/Carneys Point Twp

MP 1.7-5.7

Estimate Range  $1,000,000 - $5,000,000


UPC #133480

Sign Structure Replacement Contract 2013-2

This is a Limited Scope Sign Structures Replacement project. The scope of work will include removal of existing sign structures and replacement with new sign structures that meet all current standards. It is requested to create a new project to advance to final design utilizing in-house design units with design funding from the Sign Structure Rehabilitation line item.

In-house Project. There are 27 signstructures in the project.

Proposed Advertised Month August, 2018

Project Details

TBD/Various Municipalities

Estimate Range  $5,000,000 - $10,000,000


UPC #183340

Rt 202, Alexauken Creek Rd to Rt 179/CR 514/Old York Rd

Limited Scope Pavement Preservation

Pavement preservation is needed on Route 202 using asphalt rubber chip seal and slurry seal resurfacing. The Pavement Recommendation does not include bridge deck, approach slab, or any structures. No guide rail or ADA improvments are included in the project scope. The actual limit for pavement treatment shall be adjusted with respect to pavement change in the field.

Proposed Advertised Month August, 2018

Project Details

Hunterdon County/Lambertville City, West Amwell Twp, East Amwell Twp

MP 0.53-6.95

Estimate Range  $1,000,000 - $5,000,000


UPC #043080

Rt 40 Woodstown Intersection Improvements

The project will include Route 40/Route 45 intersection improvements which includes safety and operational improvements; resurfacing of Route 45 and reconstruction of the existing pavement along Route 40 from M.P. 10.46 to M.P. 10.87 along with upgrading all rodway appurtenances and sidewalks improvements to ADA compatible.

Proposed Advertised Month August, 2018

Project Details

Salem County/Woodstown Boro

MP 10.46-10.87

Estimate Range  $1,000,000 - $5,000,000


UPC #114230

Rt 49, Sarah Run Dr to Garrison Lane, Pavement

Limited Scope Pavement Resurfacing

1. MP 18.78-25.08, MP 25.72-26.40, MP 31.40-37.23 Travel lanes including shoulder : Mill 3" in depth and Pave with 1.5" Hot Mix Asphalt 9.5M76 Surface Course and 1.5" Hot Mix Asphalt 9.5M76 Intermediate Course. NOTE: Outer shoulder>6ft Mill 2" and Pave 2" Hot Mix Asphalt 12.5M64 Surface Course

2. MP 38.55-40.1 Travel lanes including shoulder (+1" raise in profile): Mill 2" in depth and Pave with 1.5" Hot Mix Asphalt 9.5M76 Surface Course and 1.5" Hot Mix Asphalt 9.5M76 Intermediate Course.

3. MP 25.08-25.72, 26.4-27 and 37.23-38.55: recently paved; carry out minor repair work if needed.

Proposed Advertised Month August, 2018

Project Details

Cumberland County/Stow Creek Twp, Shiloh Boro, Hopewell Twp

MP 18.78-40.01

Estimate Range  $5,000,000 - $10,000,000


UPC #168030

Sign Structure Replacement Contract 2015-2

This project will replace various overhead sign structures on Route 195 and Route 9.

Proposed Advertised Month August, 2018

Project Details

Mercer, Monmouth & Middlesex Counties/Various Municipalities

MP Rt 195: 4.71-34.01; Rt 9: 106.8-133.15

Estimate Range  $5,000,000 - $10,000,000


UPC #124120

Rt 95M, Rt 175 to Railroad Bridge

Limited Scope Pavement Resurfacing Project I-95 both directions MP 1.37 - 3.4; generally consists of 3 lanes and wide outside shoulder in both directions. Project Limits has changed to cover MP 1.37-3.40.

Proposed Advertised Month August, 2018

Project Details

Mercer County/Ewing Twp, Hopewell Twp

MP 1.37-3.4

Estimate Range  $5,000,000 - $10,000,000


UPC #144390

Rt 23, Bridges over NYS&W RR

23 Bridges over NYS&W RR (Structures # 1605-173 & 1605-164) Deck Replacement.

Proposed Advertised Month August, 2018

Project Details

Passaic County/West Milford Twp

MP 24.18-24.58

Estimate Range  $5,000,000 - $10,000,000


UPC #183250

Rt 206, Bridge over Branch of Stony Brook

Replacement with a one span three sided culvert and possibly pre-cast versus cast in place. The project does not include any widening of the roadway but incidental work for the approaches is anticipated. Utility relocation is not anticipated. It is also not anticipated that right-of-way will be required to construct the project.

Proposed Advertised Month August, 2018

Project Details

Mercer County/Princeton Twp

MP 56.77

Estimate Range  $1,000,000 - $5,000,000


UPC #143780

Rt 295, Rt 195/29 to Rt 1

Limited Scope Resurfacing project.

Proposed Advertised Month September, 2018

Project Details

Mercer County/Hamilton Twp & Lawrence Twp

MP 60.4-67.5

Estimate Range  $10,000,000 - $20,000,000


UPC #143770

Rt 195 WB, Rt 295 to CR 524/539 (Old York Rd)

Limited Scope Resurfacing project.

Proposed Advertised Month September, 2018

Project Details

Mercer & Monmouth Counties/Hamilton Twp, Robbinsville Twp & Upper Freehold Twp

MP 0-9.25

Estimate Range  $5,000,000 - $10,000,000


UPC #143720

Rt 57, Rt 22 to Rt 31

Limited Scope Pavement Resurfacing Project

Proposed Advertised Month September, 2018

Project Details

Warren County/Lopatcong Twp, Franklin Twp, Washington Boro

MP 0-3.1 & 3.9-11.06

Estimate Range  $1,000,000 - $5,000,000


UPC #183320

Rt 287, South St (CR 601) to Littleton Rd (CR 630)

Pavement Preservation.  This project has been identified as having a high benefit/cost ratio for pavement preservation.

Proposed Advertised Month September, 2018

Project Details

Morris County/Hanover Twp, Morristown Town, Morris Twp

MP 35.67-42.19

Estimate Range  $10,000,000 - $20,000,000


UPC #183360

Rt 24, Rt 287 to Rt 78

Pavement Preservation. Apply a 0.75" ULTRA THIN FRICTION COURSE to the pavement of the mainline and shoulders of Rt. 24.

Proposed Advertised Month September, 2018

Project Details

Morris, Union & Essex Counties/Hillside Twp

MP 0.0-10.42

Estimate Range  $5,000,000 - $10,000,000


UPC #183330

Rt 287, CR S91 (W. Oakland Ave) to CR 84 (Franklin Ave)

Pavement Preservation. This project has been identified as having a high benefit/cost ratio for pavement preservation.

Proposed Advertised Month September, 2018

Project Details

Bergen County/Oakland Boro, Franklin Lakes Boro

MP 58.13-60.62

Estimate Range  $5,000,000 - $10,000,000


UPC #124010

Rt 31 Bull Run Rd to Branch of Stoney Brook

This project is a limited scope pavement resurfacing project.

Proposed Advertised Month September, 2018

Project Details

Mercer & Hunterdon Counties/Hopewell Twp, Pennington Boro, East Amwell Twp

MP 4.7-14.3

Estimate Range  $5,000,000 - $10,000,000


UPC #093200

Rt 173 Bridge over Pohatcong Creek

Bridge replacement and scour countermeasures for Structure # 2103-152. Superstructure rating=3, SR=41.7. It is recommended for replacement.

Proposed Advertised Month September, 2018

Project Details

Warren County/Greenwich Twp,

MP 1.5-1.6

Estimate Range  $1,000,000 - $5,000,000


UPC #153360

Sign Structure Replacement Contract 2016-4

This project is part of statewide sign structure replacement program. There are five structures on Route 55, five structures on I-295 and five structures on Rt 676. The project is a limited scope project and will also add one new sign structure on Rt 676.

Proposed Advertised Month October, 2018

Project Details

Various Counties/Various Municipalities

Estimate Range  $5,000,000 - $10,000,000


UPC #154050

Rt 287 NB, Rt 202/206 to South St (CR 601)

This is a limited scope resurfacing project, extending from Route 287 MP 23.00 to MP 35.56.

Proposed Advertised Month October, 2018

Project Details

Somerset & Morris Counties/Bedminister Twp, Bernard Twp & Morris Twp

MP 23.0-35.57

Estimate Range  $10,000,000 - $20,000,000


UPC #144410

Rt 80, Bridges over Rockaway River

This is a federally funded Limited Scope project that will replace Rt 80 EB& WB Bridge Superstructure over Rockaway River.

Proposed Advertised Month October, 2018

Project Details

Morris County/Jefferson Twp,

MP 32.57

Estimate Range  $5,000,000 - $10,000,000


UPC #143280

Rt 322 Business, Bridge over Raccoon Creek

This project will replace the entire superstructure for the Structure # 0807152, Rt 322 Business Bridge over Raccoon Creek, MP 0.45, in Harrison Township, Gloucester County

Formerly known as Rt 45 Bridge over Raccoon Creek
Due to re-designation of Rt 322 Business, the project is now re-named as Rt 322 Business, Bridge over Raccoon Creek, MP 0.45 of Rt 322 Business. The structure number, town, county remain unchanged. The Straight Line Diagrams may not have the correct and up to date information.

Proposed Advertised Month November, 2018

Project Details

Gloucester County/Harrison Twp

MP 0.45-0.45

Estimate Range  $1,000,000 - $5,000,000


UPC #114210

Rt 40 Wilson Ave to Route 77

Limited Scope pavement resurfacing, safety, and ADA improvements.

Proposed Advertised Month November, 2018

Project Details

Salem County/Woodstown Boro, Pilesgrove Twp, Upper Pittsgrove Twp

MP 10.87-16.4

Estimate Range  $1,000,000 - $5,000,000


UPC #143310

Paterson Plank Rd (CR 681), Bridge over Rt 3 at MP 9.12

This is a Superstructure replacement project, Structure # 0907152.

Proposed Advertised Month November, 2018

Project Details

Hudson County/Secaucus Town

MP 5.31-5.31

Estimate Range  $1,000,000 - $5,000,000


UPC #048023

Rt 322/CR 551 Kings Highway

Under the proposed project, left-turn slots have been proposed on Route 322 and Kings Highway approaches. In addition, signal retiming has also been proposed. These improvements will address the safety and operational concerns.

Proposed Advertised Month November, 2018

Project Details

Gloucester County/Woolwich Twp

MP 6.72-7.25

Estimate Range  $1,000,000 - $5,000,000


UPC #123580

Rt 1 over Forrestal Rd

This is a Limited Scope superstructure replacement project.

Proposed Advertised Month November, 2018

Project Details

Middlesex County/Plainsboro Twp

MP 12.93

Estimate Range  $1,000,000 - $5,000,000


UPC #058004

Rt 22 Bloy Street to Liberty Avenue

This is a bridge replacement project. The Bloy Street Bridge bridge over Rt. 22 will be replaced. Improvements will be made to the accel and decel lanes on Rt. 22.

Proposed Advertised Month November, 2018

Project Details

Union County/Hillside Twp

MP 56.9-57.3

Estimate Range  $5,000,000 - $10,000,000

 

Operations

Project/Work Description

 

DP #18470

Job Order Contracting (JOC) State Channel Maintenance Dredging and Associated Facilities Contruction and Maintenance 2018

Proposed Advertised Month June, 2018

Project Details

Dredging Projects less than 35,000 cubic yards

Hudson, Middlesex, Monmouth, Ocean, Burlington, Atlantic, Cape May, Cumberland & Gloucester Counties/Various locations

Estimate Range $1,000,000 - $5,000,000


DP #18468

Maintenance Resurfacing Contract No. 521

Proposed Advertised Month June, 2018

Project Details

Statewide/Various locations

Estimate Range $5,000,000 - $10,000,000


DP #17459

Bridge Preventive Maintenance Contract 2017-1

Proposed Advertised Month June, 2018

Project Details

TBD

Estimate Range $1,000,000 - $5,000,000


DP #18455

Bridge Preventive Maintenance Contract 2018-1

Proposed Advertised Month July, 2018

Project Details

Route 147 MP 0.00 - 4.00/Cape May County, Middle Township

Estimate Range $1,000,000 - $5,000,000


DP #18456

Bridge Preventive Maintenance Contract 2018-2

Proposed Advertised Month July, 2018

Project Details

Route 440 MP 0.00 - 4.00/Middlesex County, Woodbridge Township

Estimate Range $1,000,000 - $5,000,000


DP #17450

Drawbridge Preventive Maintenance Contract 2017-1

Proposed Advertised Month July, 2018

Project Details

Various locations/Various municipalities in North Region/Bergen, Essex, Hudson, Morris, Passaic, Sussex, Union & Warren Counties

Estimate Range $1,000,000 - $5,000,000


DP #18464

Maintenance Job Order Contracting (JOC) Bridge Repairs, North - 2018

Proposed Advertised Month August, 2018

Project Details

Bergen, Essex, Hudson, Morris, Passaic, Sussex, Union & Warren Counties/Various municipalities in North Region

Estimate Range $1,000,000 - $5,000,000


DP #18465

Maintenance Job Order Contracting (JOC) Bridge Repairs, Central - 2018

Proposed Advertised Month August, 2018

Project Details

Hunterdon, Mercer, Middlesex, Monmouth, Ocean Somerset, & Warren Counties/Various municipalities in Central Region

Estimate Range $1,000,000 - $5,000,000


DP #18466

Maintenance Job Order Contracting (JOC) Bridge Repairs, South - 2018

Proposed Advertised Month August, 2018

Project Details

Atlantic, Burlington, Camden, Cape May, Cumberland, Gloucester & Salem Counties/Various municipalities in South Region

Estimate Range $1,000,000 - $5,000,000


DP #18467

Bridge Preventive Maintenance Contract 2018-4

Proposed Advertised Month August, 2018

Project Details

TBD

Estimate Range $1,000,000 - $5,000,000


DP #18411

Pavement Preservation Contract, North - 2018

Proposed Advertised Month August, 2018

Project Details

NJ-23 NB MP19.50 - 30.62, NJ-23 SB MP30.62 - 19.80/Morris, Passaic & Sussex Counties/Hardyston Twp., Jefferson Twp., West Milford Twp.

Estimate Range $1,000,000 - $5,000,000


DP #18412

Pavement Preservation Contract, South - 2018

Proposed Advertised Month August, 2018

Project Details

I-295 NB MP4.46 - 14.00
I-295 SB MP 11.22 - 4.46/Gloucester & Salem Counties/Carneys Point Twp., Logan Twp., Oldmans Twp.

Estimate Range $1,000,000 - $5,000,000


DP #18457

Bridge Preventive Maintenance Contract 2018-3

Proposed Advertised Month August, 2018

Project Details

TBD/Union County

Estimate Range $1,000,000 - $5,000,000


DP #18454

Orphan Bridge Preventive Maintenance Contract 2018-1

Proposed Advertised Month August, 2018

Project Details

Union County/Various locations

Estimate Range $1,000,000 - $5,000,000


DP #18463

Drainage Restoration Contract, Statewide- 2018

Proposed Advertised Month August, 2018

Project Details

Statewide/TBD

Estimate Range $1,000,000 - $5,000,000


DP #18458

Maintenance Bridge Painting Contract 2018-1

Proposed Advertised Month September, 2018

Project Details

TBD

Estimate Range $1,000,000 - $5,000,000


DP #18459

Maintenance Bridge Painting Contract 2018-2

Proposed Advertised Month September, 2018

Project Details

TBD

Estimate Range $1,000,000 - $5,000,000


DP #18460

Maintenance Bridge Painting Contract 2018-3

Proposed Advertised Month September, 2018

Project Details

TBD

Estimate Range $1,000,000 - $5,000,000


DP #17452

Maintenance Bridge Scour
Countermeasures 2017 Federal

Proposed Advertised Month October, 2018

Project Details

TBD

Estimate Range $5,000,000 - $10,000,000

 
 
Go to NJDOT home page Contact Us | Privacy Notice | Legal Statement | Accessibility Statement  Go to State of New Jersey home page
  department: home | about | NJ commuter | in the works | business | engineering | freight, air & water | capital | community | data | links | index
  statewide: NJ Home | about NJ | business | government | state services A to Z | departments

  Copyright © State of New Jersey, 2002-2018
  Department of Transportation
  P.O. Box 600
  Trenton, NJ 08625-0600
OPRA - open public records act

  Last Updated:  June 13, 2018