CPSBIDFM-1 DEPARTMENT OF TRANSPORTATION PAGE 1 CONSTRUCTION SERVICES/PROCUREMENT DIVISION TRENTON, NEW JERSEY TABULATION OF BIDS AND UNIT PRICES RT. 206 FROM COLBY FARM RD. TO 450 METERS NORTH OF MAIN ST. (C.R. 513) CONTRACT NO. 087950512 GRADING, PAVING, AND STRUCTURES. FEDERAL PROJECT NO. HPP-NHS-0035(174) TWPS. OF CHESTER, BORO. OF CHESTER, MORRIS COUNTY D.P. NO. 08147 BIDS RECEIVED JANUARY 29, 2009 CONTRACT AWARD DATE MARCH 18, 2009 BIDDERS TOTAL PRICE BID 1 . DAIDONE ELECTRIC, INC. $ 9,456,000.00 200 RAYMOND BOULEVARD NEWARK NJ07105 2 . TILCON NEW YORK INC $ 9,988,000.00 625 MT HOPE ROAD WHARTON NJ07885 3 . APONTE CONSTR CO INC $ 10,486,933.35 P O BOX 925 FLEMINGTON NJ08822 4 . NEW PRINCE CONCRETE CONSTRUCTION CO $ 10,997,159.54 215 ELLEEN TERRACE HACKENSACK NJ07601 5 . FERREIRA CONSTRUCTION CO INC $ 11,455,040.00 31 TANNERY ROAD BRANCHBURG NJ08876 6 . SMITH-SONDY ASPHALT CONSTRUCTION CO $ 11,682,976.50 150 ANDERSON AVENUE WALLINGTON NJ07057 7 . CARBRO CONSTRUCTORS CORP $ 11,707,681.97 605 OMNI DRIVE HILLSBOROUGH NJ08844 8 . INTERCOUNTY PAVING ASSOC LLC $ 11,714,476.75 859 WILLOW GROVE STREET HACKETTSTOWN NJ07840 9 . STAR OF THE SEA CONCRETE CORP $ 11,882,505.25 448 MARLBORO ROADD OLD BRIDGE NJ08857 10 . STACEY CONTR INC $ 13,023,271.90 642 BROAD STREET CLIFTON NJ07013 11 . TARHEEL ENTERPRISES INC $ 13,030,686.49 2000 HIGHWAY 35 MORGAN NJ08879 12 . CONTI ENTERPRISES INC $ 13,333,331.00 ONE CRAGWOOD ROAD SOUTH PLAINFIELD NJ07080 ITEM DESCRIPTION UNIT CONTRACT LOW BIDDER 2ND LOW BIDDER NO. QUANTITY UNIT PRICE DOLLAR AMT. UNIT PRICE DOLLAR AMT. 1 PERFORMANCE BOND AND PAYMENT BOND LS 1 70,000.00 70,000.00 35,000.00 35,000.00 2 FINAL CLEANUP LS 1 26,750.00 26,750.00 1,000.00 1,000.00 3 CONSTRUCTION LAYOUT LS 1 63,171.00 63,171.00 35,000.00 35,000.00 4 FIELD OFFICE TYPE D SET-UP U 1 30,000.00 30,000.00 20,000.00 20,000.00 5 FIELD OFFICE TYPE D MAINTENANCE MO 22 1,000.00 22,000.00 1,700.00 37,400.00 6 TELEPHONE SERVICE LS 1 6,000.00 6,000.00 6,000.00 6,000.00 7 FUEL PRICE ADJUSTMENT LS 1 21,800.00 21,800.00 21,800.00 21,800.00 8 TRAINEES HRS 2,500 1.00 2,500.00 1.00 2,500.00 9 OWNER'S AND CONTRACTOR'S PROTECTIVE LS 1 32,153.00 32,153.00 250.00 250.00 LIABILITY INSURANCE 10 POLLUTION LIABILITY INSURANCE LS 1 10,000.00 10,000.00 250.00 250.00 11 PROGRESS SCHEDULE LS 1 1.00 1.00 5,000.00 5,000.00 12 MOBILIZATION LS 1 785,972.80 785,972.80 329,999.72 329,999.72 13 NO ITEM U 0 .00 0.00 .00 0.00 14 NO ITEM U 0 .00 0.00 .00 0.00 15 CLEARING SITE LS 1 78,953.00 78,953.00 150,000.00 150,000.00 16 SEALING OF ABANDONED WELLS U 8 1,000.00 8,000.00 2,500.00 20,000.00 17 STRIPPING HA 2 16,312.00 32,624.00 10,800.00 21,600.00 18 ROADWAY EXCAVATION, UNCLASSIFIED CM 12,036 38.00 457,368.00 30.00 361,080.00 19 ROADWAY EXCAVATION, REGULATED WASTE CM 5,781 21.00 121,401.00 25.00 144,525.00 20 REMOVAL OF HOT MIX ASPHALT OVERLAY SM 1,467 16.00 23,472.00 7.65 11,222.55 21 REMOVAL OF CONCRETE BASE COURSE AND SM 70 85.00 5,950.00 75.00 5,250.00 CONCRETE SURFACE COURSES 22 SAWCUTTING LM 3,343 12.00 40,116.00 7.50 25,072.50 23 MILLING, 50 MM DEPTH SM 5,450 5.90 32,155.00 7.65 41,692.50 24 MILLING, VARIABLE DEPTH SM 500 8.00 4,000.00 7.65 3,825.00 25 OFF-SITE MANAGEMENT OF REGULATED WASTE MGR 7,900 45.00 355,500.00 46.00 363,400.00 26 SAMPLING AND ANALYSIS FOR DISPOSAL AND/OR REC U 79 1,500.00 118,500.00 1,250.00 98,750.00 YCLING - REGULATED WASTE 27 POROUS FILL CM 1,614 63.00 101,682.00 52.00 83,928.00 28 EARTH EXCAVATION FOR TEST PITS CM 30 99.00 2,970.00 98.00 2,940.00 29 ROCK EXCAVATION, SUBSURFACE STRUCTURES CM 940 96.00 90,240.00 179.00 168,260.00 30 SUBBASE CM 2,480 45.00 111,600.00 47.00 116,560.00 31 HEAVY DUTY SILT FENCE LM 720 27.00 19,440.00 15.00 10,800.00 32 DEWATERING BASINS U 1 114.00 114.00 2,500.00 2,500.00 33 HAYBALES U 37 6.00 222.00 5.00 185.00 34 ROADWAY EXCAVATION, TEMPORARY EROSION CONTROL CM 1,000 13.00 13,000.00 1.00 1,000.00 35 CONSTRUCTION DRIVEWAY MGR 120 27.00 3,240.00 25.00 3,000.00 36 CONCRETE WASHOUT FACILITY LS 1 17,100.00 17,100.00 2,500.00 2,500.00 37 OIL ONLY EMERGENCY SPILL KIT U 1 1,450.00 1,450.00 400.00 400.00 38 INLET SEDIMENT BAGS, 610 MM BY 1220 MM U 110 60.00 6,600.00 75.00 8,250.00 39 INLET SEDIMENT BAGS, 1220 MM BY 1220 MM U 19 57.00 1,083.00 75.00 1,425.00 40 TEMPORARY SEDIMENT RISER U 2 1,685.00 3,370.00 1,000.00 2,000.00 41 OIL-WATER SEPARATOR U 1 10,000.00 10,000.00 5,000.00 5,000.00 42 NO ITEM U 0 .00 0.00 .00 0.00 43 NO ITEM U 0 .00 0.00 .00 0.00 44 DENSE GRADED AGGREGATE BASE COURSE, SM 3,019 7.40 22,340.60 9.00 27,171.00 100 MM THICK 45 DENSE GRADED AGGREGATE BASE COURSE, SM 1,325 8.30 10,997.50 11.00 14,575.00 150 MM THICK 46 DENSE GRADED AGGREGATE BASE COURSE, SM 6,815 9.20 62,698.00 13.00 88,595.00 200 MM THICK 47 CONCRETE BASE COURSE, 300 MM THICK SM 713 48.00 34,224.00 72.75 51,870.75 48 NO ITEM U 0 .00 0.00 .00 0.00 49 NO ITEM U 0 .00 0.00 .00 0.00 50 BITUMINOUS CONCRETE PATCH MGR 100 108.00 10,800.00 100.00 10,000.00 51 TACK COAT L 9,200 1.60 14,720.00 .01 92.00 52 PRIME COAT L 10,200 .30 3,060.00 .01 102.00 53 ASPHALT PRICE ADJUSTMENT LS 1 96,700.00 96,700.00 96,700.00 96,700.00 54 CORE SAMPLES, HOT MIX ASPHALT U 50 137.00 6,850.00 100.00 5,000.00 55 SUPERPAVE HOT MIX ASPHALT 12.5H76 SURFACE MGR 4,656 93.00 433,008.00 99.90 465,134.40 COURSE 56 SUPERPAVE HOT MIX ASPHALT 19H64 INTERMEDIATE MGR 6,746 90.00 607,140.00 89.00 600,394.00 COURSE 57 SUPERPAVE HOT MIX ASPHALT 25M64 BASE COURSE MGR 2,344 90.00 210,960.00 88.80 208,147.20 58 NO ITEM U 0 .00 0.00 .00 0.00 59 NO ITEM U 0 .00 0.00 .00 0.00 60 FREESTANDING LANDSCAPE WALL, LOCATION 1 SM 25 375.00 9,375.00 610.00 15,250.00 61 FREESTANDING LANDSCAPE WALL, LOCATION 2 SM 18 363.00 6,534.00 591.70 10,650.60 62 SUBBASE OUTLET DRAIN LM 170 19.00 3,230.00 78.13 13,282.10 63 150 MM CORRUGATED STEEL UNDERDRAIN PIPE LM 46 47.00 2,162.00 135.00 6,210.00 64 300 MM DUCTILE IRON CULVERT PIPE LM 9 215.00 1,935.00 250.43 2,253.87 65 150 MM DUCTILE IRON WATER PIPE, CLASS 50 LM 14 1,006.00 14,084.00 940.00 13,160.00 66 200 MM DUCTILE IRON WATER PIPE, CLASS 50 LM 284 329.00 93,436.00 307.75 87,401.00 67 375 MM REINFORCED CONCRETE CULVERT PIPE LM 875 117.00 102,375.00 162.00 141,750.00 68 450 MM REINFORCED CONCRETE CULVERT PIPE LM 192 134.00 25,728.00 164.00 31,488.00 69 525 MM REINFORCED CONCRETE CULVERT PIPE LM 137 152.00 20,824.00 205.00 28,085.00 70 600 MM REINFORCED CONCRETE CULVERT PIPE LM 264 175.00 46,200.00 280.00 73,920.00 71 750 MM REINFORCED CONCRETE CULVERT PIPE LM 20 250.00 5,000.00 410.00 8,200.00 72 375 MM CORRUGATED METAL CULVERT PIPE LM 0 .00 0.00 0.00 73 450 MM CORRUGATED METAL CULVERT PIPE LM 0 .00 0.00 0.00 74 525 MM CORRUGATED METAL CULVERT PIPE LM 0 .00 0.00 0.00 75 600 MM CORRUGATED METAL CULVERT PIPE LM 0 .00 0.00 0.00 76 675 MM CORRUGATED METAL CULVERT PIPE LM 0 .00 0.00 0.00 77 750 MM CORRUGATED METAL CULVERT PIPE LM 0 .00 0.00 0.00 78 900 MM CORRUGATED METAL CULVERT PIPE LM 0 .00 0.00 0.00 79 375 MM REINFORCED CONCRETE CULVERT PIPE LM 21 117.00 2,457.00 189.00 3,969.00 80 450 MM REINFORCED CONCRETE CULVERT PIPE LM 52 135.00 7,020.00 206.00 10,712.00 81 525 MM REINFORCED CONCRETE CULVERT PIPE LM 7 158.00 1,106.00 218.00 1,526.00 82 600 MM REINFORCED CONCRETE CULVERT PIPE LM 29 177.00 5,133.00 261.00 7,569.00 83 750 MM REINFORCED CONCRETE CULVERT PIPE LM 172 245.00 42,140.00 351.00 60,372.00 84 825 MM REINFORCED CONCRETE CULVERT PIPE LM 21 309.00 6,489.00 407.00 8,547.00 85 900 MM REINFORCED CONCRETE CULVERT PIPE LM 82 333.00 27,306.00 294.00 24,108.00 86 1 050 MM REINFORCED CONCRETE CULVERT PIPE LM 46 463.00 21,298.00 442.00 20,332.00 87 730 BY 1 150 MM REINFORCED CONCRETE LM 22 479.00 10,538.00 422.00 9,284.00 ELLIPTICAL CULVERT PIPE, CLASS HE-III 88 795 BY 1 250 MM REINFORCED CONCRETE LM 54 600.00 32,400.00 590.00 31,860.00 ELLIPTICAL CULVERT PIPE, CLASS HE-III 89 975 BY 1 535 MM REINFORCED CONCRETE LM 18 749.00 13,482.00 803.00 14,454.00 ELLIPTICAL CULVERT PIPE, CLASS HE-III 90 1 095 BY 1 730 MM REINFORCED CONCRETE LM 30 866.00 25,980.00 931.00 27,930.00 ELLIPTICAL CULVERT PIPE, CLASS HE-III 91 VIDEO INSPECTION OF PIPE LM 2,200 3.30 7,260.00 10.50 23,100.00 92 375 MM HIGH DENSITY POLYETHYLENE PIPE LM 18 87.00 1,566.00 195.00 3,510.00 93 450 MM REINFORCED CONCRETE END SECTIONS U 1 1,813.00 1,813.00 507.00 507.00 94 750 MM REINFORCED CONCRETE END SECTIONS U 1 2,215.00 2,215.00 1,223.00 1,223.00 95 900 MM REINFORCED CONCRETE END SECTIONS U 1 2,536.00 2,536.00 1,543.00 1,543.00 96 1 095 BY 1 730 MM REINFORCED CONCRETE END U 1 4,729.00 4,729.00 3,797.00 3,797.00 SECTIONS 97 INLETS, TYPE A U 1 1,347.00 1,347.00 1,550.00 1,550.00 98 INLETS, TYPE B U 52 1,880.00 97,760.00 2,100.00 109,200.00 99 INLETS, TYPE E U 8 2,414.00 19,312.00 2,180.00 17,440.00 100 INLETS, TYPE B-2 U 3 3,617.00 10,851.00 4,185.00 12,555.00 101 INLETS CONVERTED TO MANHOLES U 1 1,273.00 1,273.00 1,740.00 1,740.00 102 MANHOLES U 3 1,561.00 4,683.00 2,150.00 6,450.00 103 MANHOLES, 1.5 M DIAMETER U 2 3,022.00 6,044.00 4,180.00 8,360.00 104 MANHOLES, 1.8 M DIAMETER U 1 4,281.00 4,281.00 4,350.00 4,350.00 105 RECONSTRUCTED MANHOLES, USING EXISTING U 3 3,055.00 9,165.00 875.00 2,625.00 CASTING 106 RESET CASTINGS U 7 144.00 1,008.00 225.00 1,575.00 107 INLETS, TYPE DOUBLE B U 21 3,361.00 70,581.00 3,885.00 81,585.00 108 INLETS, TYPE DOUBLE E U 2 3,978.00 7,956.00 4,350.00 8,700.00 109 INLETS, TYPE DOUBLE B-2 U 1 9,944.00 9,944.00 7,166.00 7,166.00 110 SPECIAL STRUCTURE 1 U 3 6,276.00 18,828.00 4,774.00 14,322.00 111 SPECIAL STRUCTURE 2 U 1 9,333.00 9,333.00 4,900.00 4,900.00 112 SPECIAL STRUCTURE 3 U 1 11,764.00 11,764.00 6,925.00 6,925.00 113 SPECIAL STRUCTURE 4 U 1 2,862.00 2,862.00 9,980.00 9,980.00 114 SPECIAL STRUCTURE 5 U 3 1,934.00 5,802.00 3,010.00 9,030.00 115 OUTLET STRUCTURE 1 U 1 9,662.00 9,662.00 13,500.00 13,500.00 116 OUTLET STRUCTURE 2 U 1 9,621.00 9,621.00 15,750.00 15,750.00 117 CONCRETE SLOPE GUTTERS, 100 MM THICK SM 192 50.00 9,600.00 60.00 11,520.00 118 225 BY 400 MM CONCRETE VERTICAL CURB LM 2,391 41.00 98,031.00 47.50 113,572.50 119 225 BY 450 MM CONCRETE VERTICAL CURB LM 411 46.00 18,906.00 50.00 20,550.00 120 225 MM BY VARIABLE HEIGHT CONCRETE VERTICAL LM 267 52.00 13,884.00 73.00 19,491.00 CURB, DOWELLED 121 225 BY 200 MM CONCRETE VERTICAL CURB, LM 443 38.00 16,834.00 73.00 32,339.00 DOWELLED 122 225 BY 525 MM CONCRETE VERTICAL CURB LM 1,405 54.00 75,870.00 55.00 77,275.00 123 CONCRETE SIDEWALK, 100 MM THICK SM 223 48.00 10,704.00 46.00 10,258.00 124 HOT MIX ASPHALT DRIVEWAY, 150 MM THICK SM 5,651 44.00 248,644.00 43.75 247,231.25 125 DETECTABLE WARNING SURFACES SM 69 271.00 18,699.00 400.00 27,600.00 126 CONCRETE SIDEWALK, 100MM THICK, REINFORCED SM 1,639 50.00 81,950.00 50.00 81,950.00 127 BRICK PAVER PAVEMENT WITH CONCRETE BASE SM 1,195 147.00 175,665.00 135.00 161,325.00 128 BRICK PAVERS SM 259 86.00 22,274.00 135.00 34,965.00 129 DETECTABLE WARNING PAVERS WITH CONCRETE BASE SM 9 237.00 2,133.00 195.00 1,755.00 130 CONCRETE ISLAND, 100 MM THICK SM 997 61.00 60,817.00 46.00 45,862.00 131 MONUMENTS U 20 375.00 7,500.00 350.00 7,000.00 132 GABIONS CM 292 194.00 56,648.00 345.00 100,740.00 133 MISCELLANEOUS CONCRETE CM 12 150.00 1,800.00 400.00 4,800.00 134 MISCELLANEOUS CONCRETE CLASS S CM 366 204.00 74,664.00 200.00 73,200.00 135 TEMPORARY CHAIN-LINK FENCE, 1.5 M HIGH LM 225 35.00 7,875.00 55.00 12,375.00 136 SNOW FENCE, PLASTIC LM 118 9.80 1,156.40 20.00 2,360.00 137 RESET FENCE LM 127 70.00 8,890.00 65.00 8,255.00 138 RIPRAP STONE SLOPE PROTECTION, 600 MM THICK SM 9 58.00 522.00 80.00 720.00 (D50=300 MM) 139 RIPRAP STONE SLOPE PROTECTION, 800 MM THICK SM 23 56.00 1,288.00 105.00 2,415.00 (D50=400 MM) 140 RIPRAP STONE SLOPE PROTECTION, 300MM THICK (D SM 3 63.00 189.00 82.00 246.00 50=150MM) 141 BREAKAWAY BARRICADES U 50 29.00 1,450.00 100.00 5,000.00 142 DRUMS U 100 15.00 1,500.00 100.00 10,000.00 143 TRAFFIC CONES U 100 3.50 350.00 50.00 5,000.00 144 CONSTRUCTION IDENTIFICATION SIGNS, U 2 840.00 1,680.00 1,000.00 2,000.00 1 200 BY 2 400 MM 145 VARIABLE MESSAGE SIGNS U 2 1,000.00 2,000.00 20,000.00 40,000.00 146 CONSTRUCTION SIGNS SM 98 168.00 16,464.00 50.00 4,900.00 147 ILLUMINATED FLASHING ARROWS, U 2 1,000.00 2,000.00 3,000.00 6,000.00 1 200 BY 2 400 MM 148 TRAFFIC CONTROL TRUCKS WITH MOUNTED U 2 1,000.00 2,000.00 15,000.00 30,000.00 CRASH CUSHIONS 149 REMOVABLE BLACK LINE MASKING TAPE LM 1,000 8.00 8,000.00 7.60 7,600.00 150 TEMPORARY SIDEWALK SM 100 26.00 2,600.00 53.00 5,300.00 151 TRAFFIC DIRECTORS, FLAGGERS HRS 500 57.00 28,500.00 65.00 32,500.00 152 REMOVABLE WET WEATHER PAVEMENT MARKING TAPE LM 5,013 6.20 31,080.60 5.72 28,674.36 153 TEMPORARY DRIVEWAY SM 100 26.00 2,600.00 69.00 6,900.00 154 TEMPORARY DRAINAGE LS 1 1.00 1.00 10,000.00 10,000.00 155 TRAFFIC STRIPES LM 5,013 .90 4,511.70 .85 4,261.05 156 TRAFFIC STRIPES, LONG LIFE, EPOXY RESIN LM 5,013 1.30 6,516.90 1.19 5,965.47 157 TRAFFIC MARKINGS, LINES, LONG LIFE, LM 2,142 2.00 4,284.00 1.90 4,069.80 THERMOPLASTIC 158 TRAFFIC MARKINGS, SYMBOLS, LONG LIFE, SM 64 45.00 2,880.00 42.75 2,736.00 THERMOPLASTIC 159 REMOVAL OF TRAFFIC STRIPES AND MARKINGS LM 5,013 1.00 5,013.00 .90 4,511.70 160 SIGNS SM 52 428.00 22,256.00 378.00 19,656.00 161 GUIDE SIGNS, TYPE GA, STEEL "U" POST SUPPORTS SM 13 649.00 8,437.00 370.00 4,810.00 162 RESET WATER VALVE BOXES U 4 214.00 856.00 50.00 200.00 163 RELOCATE FIRE HYDRANT ASSEMBLIES U 4 3,139.00 12,556.00 3,139.35 12,557.40 164 WATER SERVICE CONNECTIONS U 2 2,397.00 4,794.00 2,397.05 4,794.10 165 150 MM GATE VALVES AND BOXES U 5 949.00 4,745.00 949.45 4,747.25 166 200 MM GATE VALVES AND BOXES U 8 1,321.00 10,568.00 1,320.55 10,564.40 167 6 BY 100 MM PVC TELEPHONE CONDUIT, CONCRETE LM 9 150.00 1,350.00 270.00 2,430.00 ENCASED 168 ELECTRICAL UTILITY RELOCATION, JCP&L LS 1 216,000.00 216,000.00 209,520.00 209,520.00 169 WATER AS-BUILT PLAN LS 1 1,269.00 1,269.00 1,268.00 1,268.00 170 GAS AS-BUILT PLAN LS 1 1,600.00 1,600.00 1,600.00 1,600.00 171 GAS PIPE EXCAVATION, UNCLASSIFIED CM 430 54.00 23,220.00 53.62 23,056.60 172 GAS LINESTOP AND TIE-IN, EXCAVATION UNCLASSIF CM 199 510.00 101,490.00 509.57 101,404.43 IED 173 50 MM PLASTIC GAS MAIN (2") LM 83 49.00 4,067.00 49.16 4,080.28 174 150 MM PLASTIC GAS MAIN (6") LM 2 510.00 1,020.00 509.96 1,019.92 175 200 MM PLASTIC GAS MAIN (8") LM 355 76.00 26,980.00 75.94 26,958.70 176 12.7 MM - 38 MM PLASTIC GAS SERVICE TRANSFER U 4 925.00 3,700.00 924.50 3,698.00 177 51 MM - 76 MM PLASTIC GAS SERVICE TRANSFER U 5 925.00 4,625.00 924.50 4,622.50 178 50 MM FABRICATE TIE-IN PIECE U 3 493.00 1,479.00 493.04 1,479.12 179 150 MM FABRICATE TIE-IN PIECE U 1 740.00 740.00 739.56 739.56 180 200 MM FABRICATE TIE-IN PIECE U 3 1,245.00 3,735.00 1,244.79 3,734.37 181 150 MM THRUST RESTRAINT AND BELL JOINT ENCAPS U 2 523.00 1,046.00 523.06 1,046.12 ULATION 182 200 MM THRUST RESTRAINT AND BELL JOINT ENCAPS U 6 697.00 4,182.00 697.42 4,184.52 ULATION 183 GAS, EXCAVATION FOR TEST PITS CM 20 536.00 10,720.00 536.24 10,724.80 184 GAS, PIPE BEDDING CM 162 40.00 6,480.00 40.33 6,533.46 185 GAS, BACKFILL CM 25 39.00 975.00 38.52 963.00 186 50 MM - 200 MM PIPE LINE STOP TIE-IN ASSISTAN CH 100 362.00 36,200.00 361.63 36,163.00 CE (3"-8") 187 12.7 MM - 38 MM PLASTIC GAS SERVICE DIRECT BU U 3 3,575.00 10,725.00 3,574.89 10,724.67 RIAL UNDER 30M 188 51 MM- 76 MM PLASTIC GAS SERVICE DIRECT BURIA U 3 3,575.00 10,725.00 3,574.89 10,724.67 L UNDER 30M 189 12.7 MM- 38 MM PLASTIC GAS SERVICE DIRECT BUR LM 100 107.00 10,700.00 107.26 10,726.00 IAL OVER 30M 190 51 MM - 76 MM PLASTIC GAS SERVICE DIRECT LM 100 107.00 10,700.00 107.26 10,726.00 BURIAL OVER 30M 191 GAS, PROTECTIVE STEEL PLATE, 600 MM X 1200 MM SM 10 89.00 890.00 89.38 893.80 192 NO ITEM U 0 .00 0.00 .00 0.00 193 53 MM RIGID METALLIC CONDUIT, TYPE CUG LM 290 60.00 17,400.00 52.70 15,283.00 194 78 MM RIGID METALLIC CONDUIT, TYPE CUG LM 784 92.00 72,128.00 68.20 53,468.80 195 103 MM RIGID METALLIC CONDUIT, TYPE CUG LM 50 135.00 6,750.00 86.80 4,340.00 196 78 MM RIGID METALLIC CONDUIT, TYPE CUR LM 127 138.00 17,526.00 105.40 13,385.80 197 78 MM RIGID NONMETALLIC CONDUIT LM 297 46.00 13,662.00 80.60 23,938.20 198 GROUND WIRE, NO. 8 AWG LM 1,681 6.80 11,430.80 6.05 10,170.05 199 MULTIPLE LIGHTING WIRE, NO. 2 AWG LM 3,025 9.60 29,040.00 12.25 37,056.25 200 MULTIPLE LIGHTING WIRE, NO. 8 AWG LM 1,680 7.20 12,096.00 10.08 16,934.40 201 SERVICE WIRE, NO. 6 AWG LM 40 11.00 440.00 6.98 279.20 202 FOUNDATIONS, TYPE SFT U 3 1,037.00 3,111.00 1,385.00 4,155.00 203 FOUNDATIONS, TYPE P-MC U 1 2,124.00 2,124.00 2,350.00 2,350.00 204 FOUNDATIONS, TYPE SPF U 1 797.00 797.00 1,050.00 1,050.00 205 FOUNDATIONS, TYPE STF U 3 3,112.00 9,336.00 3,850.00 11,550.00 206 FOUNDATIONS, TYPE SFK U 1 1,106.00 1,106.00 1,150.00 1,150.00 207 FOUNDATIONS, TYPE 2M-MC U 1 2,378.00 2,378.00 3,150.00 3,150.00 208 JUNCTION BOX FOUNDATIONS U 25 1,459.00 36,475.00 1,625.00 40,625.00 209 450 BY 900 MM JUNCTION BOXES U 22 1,272.00 27,984.00 1,525.00 33,550.00 210 CONTROLLER ASSEMBLIES, 8 PHASE U 1 16,793.00 16,793.00 20,500.00 20,500.00 211 PEDESTAL ASSEMBLIES, TYPE PW-1 U 1 1,495.00 1,495.00 1,550.00 1,550.00 212 PEDESTAL ASSEMBLIES, TYPE J-2-W U 2 2,094.00 4,188.00 1,800.00 3,600.00 213 PEDESTRIAN SIGNAL ASSEMBLIES, TYPE W-1 U 11 1,083.00 11,913.00 1,075.00 11,825.00 214 PUSH BUTTON ASSEMBLIES U 4 238.00 952.00 150.00 600.00 215 TRAFFIC SIGNAL ASSEMBLIES, TYPE 6.1MA-1 U 1 2,637.00 2,637.00 2,045.00 2,045.00 216 TRAFFIC SIGNAL ASSEMBLIES, TYPE 10.7S-2 U 1 7,109.00 7,109.00 5,050.00 5,050.00 217 TRAFFIC SIGNAL ASSEMBLIES, TYPE 12.2S-2 U 1 7,593.00 7,593.00 5,375.00 5,375.00 218 TRAFFIC SIGNAL ASSEMBLIES, TYPE 7.6MK-1 U 1 3,575.00 3,575.00 2,750.00 2,750.00 219 TRAFFIC SIGNAL ASSEMBLIES, TYPE C-1 U 5 1,195.00 5,975.00 1,200.00 6,000.00 220 TRAFFIC SIGNAL ASSEMBLIES, TYPE MM-1 U 5 1,201.00 6,005.00 1,225.00 6,125.00 221 TRAFFIC SIGNAL CABLE, 2 CONDUCTOR LM 393 3.70 1,454.10 4.87 1,913.91 222 TRAFFIC SIGNAL CABLE, 5 CONDUCTOR LM 1,465 5.70 8,350.50 5.89 8,628.85 223 TRAFFIC SIGNAL CABLE, 10 CONDUCTOR LM 905 8.60 7,783.00 9.61 8,697.05 224 TRAFFIC SIGNAL STANDARDS, TYPE C U 2 2,311.00 4,622.00 1,725.00 3,450.00 225 TRAFFIC SIGNAL STANDARDS, TYPE S U 1 4,550.00 4,550.00 6,350.00 6,350.00 226 TRAFFIC SIGNAL STANDARDS, TYPE K U 1 2,683.00 2,683.00 2,550.00 2,550.00 227 TRAFFIC SIGNAL STANDARDS, TYPE KE U 1 797.00 797.00 950.00 950.00 228 TRAFFIC CONTROLLER ASSEMBLY TURN ON U 1 2,144.00 2,144.00 1,950.00 1,950.00 229 TEMPORARY TRAFFIC SIGNAL SYSTEM, LS 1 55,680.00 55,680.00 27,500.00 27,500.00 LOCATION NUMBER 1 230 INTERIM TRAFFIC SIGNAL SYSTEM, LOCATION LS 1 4,812.00 4,812.00 3,500.00 3,500.00 NUMBER 2 231 METER CABINETS, TYPE 2M-MC U 1 10,083.00 10,083.00 5,990.00 5,990.00 232 TRAFFIC SIGNAL STANDARD, TYPE SC U 2 6,794.00 13,588.00 7,350.00 14,700.00 233 RED SIGNAL AHEAD SIGN ASSEMBLY LS 1 14,440.00 14,440.00 9,000.00 9,000.00 234 METER CABINET, TYPE TL (15) U 1 2,387.00 2,387.00 2,970.00 2,970.00 235 IMAGE DETECTION SYSTEM, LOCATION 1 LS 1 20,489.00 20,489.00 29,500.00 29,500.00 236 IMAGE DETECTION SYSTEM, LOCATION 2 LS 1 20,489.00 20,489.00 29,900.00 29,900.00 237 LIGHTING ASSEMBLIES, TYPE L-MG-X U 5 1,793.00 8,965.00 1,735.00 8,675.00 238 LIGHTING STANDARD ASSEMBLIES, TYPE L-7.9-MG-X U 26 3,130.00 81,380.00 3,000.00 78,000.00 239 NO ITEM U 0 .00 0.00 .00 0.00 240 TOPSOILING, 100 MM THICK SM 11,652 1.40 16,312.80 1.25 14,565.00 241 BORROW TOPSOIL CM 250 30.00 7,500.00 27.50 6,875.00 242 FERTILIZING AND SEEDING, TYPE A-3 SM 11,652 .50 5,826.00 .45 5,243.40 243 FERTILIZING AND SEEDING, TYPE F SM 1,130 .40 452.00 .40 452.00 244 TOPSOIL STABILIZATION MATTING SM 607 3.70 2,245.90 3.35 2,033.45 245 SYNTHETIC POND LINER SM 3,265 10.00 32,650.00 12.00 39,180.00 246 STRAW MULCHING SM 12,175 .50 6,087.50 .45 5,478.75 247 WOOD MULCHING SM 6,000 3.90 23,400.00 3.50 21,000.00 248 WOOD MULCHING, 50 MM THICK SM 600 3.20 1,920.00 3.00 1,800.00 249 MOWING HA 3 1,605.00 4,815.00 1,000.00 3,000.00 250 HEMEROCALLIS 'HAPPY RETURNS', #SP5 CONTAINER, U 129 16.00 2,064.00 11.40 1,470.60 1 TO 2 FAN DIVISION, HEAVY ROOT SYSTEM 251 JUNIPERUS CHINENSIS SARGENTII, CANS, U 26 32.00 832.00 19.00 494.00 0.4 TO 0.5 M SPREAD 252 TAXUS CUSPIDATA "DENSIFORMIS", B&B, U 539 32.00 17,248.00 26.60 14,337.40 0.4 TO 0.5 M SPREAD 253 NARCISSUS, BULBS U 256 1.10 281.60 .95 243.20 254 VIBURNUM RHYTIDOPHYLLOIDES "ALLEGHANY", B&B, U 66 43.00 2,838.00 38.00 2,508.00 3' TO 4' HIGH 255 WATERING CM 500 30.00 15,000.00 30.00 15,000.00 256 ACER CAMPESTRE, B&B, 76-90 MM CALIPER, 3.1-3. U 66 412.00 27,192.00 325.00 21,450.00 6 M HIGH 257 CRATAEGUS CRUSGALLI 'CRUZAM', B&B, 76-90 MM C U 21 321.00 6,741.00 285.00 5,985.00 ALIPER, 3.1-3.6 M HIGH 258 ITEA VIRGINICA 'HENRY'S GARNET',#3 CONTAINER U 216 40.00 8,640.00 33.25 7,182.00 259 LEUCOTHOE FONTANESIANA, #3 CONTAINER U 80 41.00 3,280.00 33.25 2,660.00 260 PENNISETUM ALOPECUROIDES 'HAMELN', #3 CONTAIN U 19 32.00 608.00 28.50 541.50 ER 261 ROSA RUGOSA, #3 CONTAINER U 52 35.00 1,820.00 28.50 1,482.00 262 SPIREA JAPONICA 'GOLDMOUND',#3 CONTAINER U 36 41.00 1,476.00 36.75 1,323.00 263 TAXUS CUSPIDATA 'NANA', #3 CONTAINER U 92 43.00 3,956.00 33.25 3,059.00 264 ACER RUBRUM "OCTOBER GLORY", B&B, 76 TO 90 MM U 30 321.00 9,630.00 270.00 8,100.00 CALIPER, 3.1 TO 3.6 M HIGH 265 GLEDITSIA TRIACANTHOS INERMIS "SHADEMASTER", U 4 321.00 1,284.00 270.00 1,080.00 B&B, 76-90MM CALIPER, 3.1 TO 3.6 M HIGH 266 JUNIPERUS HORIZONTALIS "BAR HARBOR", #3 CONTA U 340 37.00 12,580.00 27.00 9,180.00 INER 267 QUERCUS PALUSTRIS, B&B, 76-90 MM CALIPER, 3. U 34 321.00 10,914.00 275.00 9,350.00 5 TO 4.25 M HIGH 268 ZELKOVA SERRATA "GREEN VASE", B&B, 76-90 MM C U 5 401.00 2,005.00 275.00 1,375.00 ALIPER, 3.1 TO 3.6 M HIGH 269 PINUS STROBUS "FASTIGIATA", B&B, 3.65 TO 4.25 U 16 615.00 9,840.00 515.00 8,240.00 M HIGH 270 PIERIS JAPONICA "MOUNTAIN FIRE", B&B, 0.9 TO U 335 54.00 18,090.00 47.50 15,912.50 1.2 M HIGH 271 NONVEGETATIVE SURFACE, HOT MIX ASPHALT SM 17 128.00 2,176.00 137.75 2,341.75 272 STONE VENEER SM 93 192.00 17,856.00 727.50 67,657.50 273 TIMBER GUIDE RAIL LM 29 240.00 6,960.00 162.50 4,712.50 274 CONCRETE STAIRS WITH PAVER TREADS AND RISERS LS 1 10,700.00 10,700.00 8,700.00 8,700.00 275 DECORATIVE SEAT WALL, TYPE 1 LM 43 917.00 39,431.00 1,400.00 60,200.00 276 NO ITEM U 0 .00 0.00 .00 0.00 277 CAST STONE CAP LM 53 181.00 9,593.00 655.00 34,715.00 278 STAINLESS STEEL HAND RAILS LM 3 892.00 2,676.00 725.00 2,175.00 279 CAST STONE PANELS U 3 544.00 1,632.00 5,350.00 16,050.00 280 CAST STONE SIGN LS 1 2,943.00 2,943.00 9,700.00 9,700.00 281 DECORATIVE SEAT WALL, TYPE 2 LM 10 1,575.00 15,750.00 1,700.00 17,000.00 282 DECORATIVE PIER, TYPE 1 U 6 1,717.00 10,302.00 4,365.00 26,190.00 283 DECORATIVE PIER, TYPE 2 U 2 3,603.00 7,206.00 5,820.00 11,640.00 284 CAST STONE PIER CAP, 152 MM THICK U 6 423.00 2,538.00 6,300.00 37,800.00 285 CAST STONE PIER CAP, 203 MM THICK U 2 532.00 1,064.00 2,135.00 4,270.00 286 1.2 M HIGH POWDER - COATED ALUMINUM FENCE LM 12 167.00 2,004.00 175.00 2,100.00 287 NO ITEM U 0 .00 0.00 .00 0.00 288 NO ITEM U 0 .00 0.00 .00 0.00 RETAINING WALL NO. 1 289 FOUNDATION EXCAVATION CM 2,530 66.00 166,980.00 55.00 139,150.00 290 CONCRETE IN STRUCTURES, FOOTINGS CM 410 252.00 103,320.00 375.00 153,750.00 291 CONCRETE IN STRUCTURES, RETAINING WALLS CM 660 384.00 253,440.00 625.00 412,500.00 292 REINFORCEMENT STEEL IN STRUCTURES, EPOXY KG 34,863 6.10 212,664.30 3.65 127,249.95 COATED 293 TEMPORARY SHEETING SM 1,180 568.00 670,240.00 575.00 678,500.00 294 200 MM CORRUGATED STEEL UNDERDRAIN PIPE LM 232 66.00 15,312.00 125.00 29,000.00 295 STONE VENEER SM 820 205.00 168,100.00 675.00 553,500.00 296 CAST STONE CAP LM 220 193.00 42,460.00 650.00 143,000.00 297 1.2 M HIGH POWDER-COATED ALUMINUM FENCE LM 220 169.00 37,180.00 150.00 33,000.00 SUMMARY OF AMOUNTS ROAD ITEMS $ 7,786,303.70 $ 7,718,350.05 BRIDGE ITEMS $ 1,669,696.30 $ 2,269,649.95 SUB-TOTAL AMOUNTS FOR BRIDGE WORK RETAINING WALL NO. 1 $ 1,669,696.30 $ 2,269,649.95 AGREE AGREE (HEADER) LOW BID =$ 9,456,000.00 (HEADER) 2ND LOW BID =$ 9,988,000.00 COMPUTED LOW BID =$ 9,456,000.00 COMPUTED 2ND LOW BID =$ 9,988,000.00 COMPUTED LOW BID =$ 9,456,000.00 COMPUTED 2ND LOW BID =$ 9,988,000.00