Question 1: Would you please consider allowing 11” x 17” pages for the schedule, the organizational chart, and the 2 extra pages?
Answer 1: Yes, the schedule, the organizational chart, and the two extra pages for pictures, cross sections etc. can be on 11” x 17” size. Please note that NO ADDITIONAL NARRATIVE BEYOND THE (6) PAGE LIMIT WILL BE EVALUATED and those pages will be 8 ½” x 11” size. Also note that since the submission is a pdf only, a hard copy of the submission may or may not be printed out by the Technical Evaluation Committee when reviewing.
Question 2: Can a BS in Transportation Engineering & Management with an MS in Transportation Engineering and NJPE meet the requirement for Roadway Design Task Leader?
Answer 2: No. While for a Project Manager a bachelor’s degree with a PE is acceptable, for a roadway design engineer the requirement is specified with a BSCE and a PE.
Question 3: For the Traffic Engineering Team Leader, can a NJPE with a PhD in Transportation Engineering fulfill the PTOE requirement?
Answer 3: No.
Question 4: Can a Bachelor of Technology in Transportation with a NJ PE License fulfill the BS in Engineering requirement for Utility Team Leader?
Answer 4: No.
|