Project Details: Contract 2 - Route 139


pulaski skyway graphic Work under Contract 2 involves deck replacements and other work on the Conrail and Hoboken Viaducts. Work under this contract is anticipated to be completed by early 2016.

Making the Pulaski Skyway stronger and better.

Starting in December 2013, work under Contract 2 required the New Jersey Department of Transportation (NJDOT) to implement a movable barrier system that provides motorists on Route 139 Lower Roadway with two travel lanes in the peak direction, meaning eastbound motorists are provided two travel lanes in the morning and westbound motorists are provided two travel lanes in the evening. When Contract 3 began and the Pulaski Skyway northbound travel lanes were closed, the Route 139 Lower Roadway provides motorists with one travel lane eastbound and two travel lanes westbound.

Construction Staging

Pre-Phase 1 (Completed)
  • Remove Lower Roadway median barrier and replace with movable barrier
Phase 1 (Completed)
  • Construct detour road, Lower Roadway drainage and retaining walls
Phases 2, 3 and 4
  • Deck and column replacement on the Conrail and Hoboken Viaducts, steel replacement and repair, lighting and intersection improvements

Intersection closures on the eastbound side of Route 139 will be necessary during these phases. The tentative timeframe and additional detour information is below:

Phase 2 (Ongoing)
Fall 2014 to Spring 2015

Part 1- Fall 2014 to Winter 2014/2015
Temporary road open to traffic. All cross streets on the upper roadway remain open. Upper roadway traffic (headed east toward New York) between Central Avenue and Palisade Avenue is detoured to the tempoary roadway constructed adjacent to the upper eastbound roadway.

Detour route:
Right turn from Route 139 eastbound onto Central Avenue, turn left onto Hoboken Avenue, proceed onto the temporary roadway.

Part 2- Winter 2014/2015 to Spring 2015
Temporary road open to traffic. Intersection closure: Palisade Avenue and Oakland Avenue.

Detour route: Traffic traveling on the upper roadway will exit upper Route 139 via right turn at Summit Avenue then turn left onto Hoboken Avenue and proceed to the temporary roadway constructed adjacent to upper Route 139 between Oakland Avenue and Palisade Avenue.

Phase 3
Spring 2015 to Fall 2016

Temporary road open to traffic. Intersection closure: Baldwin Avenue and Central Avenue

Detour route:
Traffic traveling on the upper roadway will exit upper Route 139 via right turn at Summit Avenue then turn left onto Hoboken Avenue and proceed to the temporary roadway constructed adjacent to upper Route 139 between Oakland Avenue and Palisade Avenue.

Phase 4
Fall 2016 to Fall 2017

Intersection closure: Summit Avenue/Bevan Street

Detour route (from north of Route 139):
Traffic destined for eastbound upper Route 139 will travel south on JFK Boulevard, turn left onto Newark Avenue and continue to the temporary roadway constructed adjacent to upper Route 139 between Oakland Avenue and Palisade Avenue.

Phase 5
  • Lower Roadway barrier replacement, final pavement
Phase 6
  • Upper Roadway final pavement

The Hoboken and Conrail Viaducts are sections of Route 139. Route 139 features Upper and Lower roadways, extending from the eastern end of the Pulaski Skyway to the Holland Tunnel. It provides eastbound motorists with access to Hudson County and New York City destinations, and provides westbound motorists with access to the Pulaski Skyway, Newark and points west.

The Hoboken Avenue Viaduct (Upper Roadway) is a four lane east-west divided arterial in Jersey City which carries traffic from the Pulaski Skyway to the Holland Tunnel. The Lower Roadway, located beneath the Hoboken Avenue Viaduct, also serves as a link between the Jersey City and New York.

route 139 lower roadway photo

Route 139 Lower Roadway

The Conrail Viaduct is a four lane, 12 span structure. It is located between the Hoboken Avenue Viaduct and the Pulaski Skyway and crosses over abandoned Conrail railroad tracks.

The Viaducts were constructed in 1927 as part of the limited-access approach road to the Holland Tunnel. Repairs will eliminate structural deficiencies and strengthen them against seismic activity. Improvements include:

  • Replace the deck, supporting beams and columns supporting the eastbound side of the Hoboken Viaduct and resurface the westbound roadway.
  • Replace the deck on the Conrail Viaduct and strengthen the supporting trusses.
  • Operational improvements at several intersections on the Upper Roadway.

project limits graphic

 
Go to NJDOT home page Contact Us | Privacy Notice | Legal Statement | Accessibility Statement  Go to State of New Jersey home page
  department: home | about | NJ commuter | in the works | business | engineering | freight, air & water | capital | community | data | links | index
  statewide: NJ Home | about NJ | business | government | state services A to Z | departments

  Copyright © State of New Jersey, 2002-2014
  Department of Transportation
  P.O. Box 600
  Trenton, NJ 08625-0600
OPRA - open public records act

  Last Updated:  October 7, 2014