Update (March 2013):
All roadways and ramps are fully
operational. The remaining work
consists of completion of work
items added to the project, replacement
of components controlling traffic
cameras and dynamic messaging
signs of the Intelligent Transportation
System (ITS) damaged by Superstorm
Sandy. All of this work is scheduled
to be substantially complete
by August 2013.
| Stage
1 A: June
2009 - March 2010 - Completed |
- Construct Duffield/St. Paul's
Avenues intersection
- Construct pre-loading at
west end of project between
Charlotte and Duffield
Avenues
- Begin construction of mainline
Viaduct over St. Paul's
Avenue and Loop
Ramp D
- Begin construction of Route
1&9T Flyover
Ramp
- Begin construction of the
Tonnele Avenue bridges
over NJ TRANSIT and Conrail
railroad tracks
Description
of Ramps:
Loop
Ramp D - Will
pass
over the Tonnele
Circle, pass under
Ramp I and the
mainline Route
1&9T
before tying into
Route 1&9T southbound
Route
1&9T Flyover Ramp - Will
extend from Route 1&9T
northbound passing over
Tonnele Avenue, NJ TRANSIT
and Conrail railroad
tracks and ends in the
area of Spruce Street |
| Stage
1 B: March 2010
- October 2011 -
Completed |
- Construct Ramp
A bridge
- Continue construction of mainline
Viaduct over St. Paul's Avenue
and Loop
Ramp D
- Continue construction of Route
1&9T Flyover
Ramp
- Construct the crossover
ramp,
Ramp B and Ramp
G
- Construct and complete the Route
1&9T bridge over Charlotte
Avenue
- Construct Ramp H
- Continue construction of the
Tonnele Avenue bridges over
NJ TRANSIT and Conrail railroad
tracks
Description of
Ramps:
Ramp
A - Will connect Route
1&9T northbound and St. Paul's
and James Avenues to Route 7 westbound
Loop
Ramp D - Will pass over
the Tonnele Circle, pass under
Ramp I and the mainline Route
1&9T before tying into Route
1&9T southbound
Route
1&9T Flyover
Ramp - Will
extend from Route
1&9T
northbound passing
over Tonnele Avenue,
NJ TRANSIT and
Conrail railroad
tracks and ends
in the area of
Spruce Street
Crossover
Ramp - Will extend
eastward from Ramp A
to the split of Ramp
B and the mainline Route
1&9T
near Charlotte
Avenue
Ramp
B - Will exit
the mainline west of
Charlotte Avenue and
pass over Charlotte Avenue
and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Ramp
G - Will
connect Route 1&9T southbound
with Charlotte Avenue
immediately north of
the Route 1&9T/Newark
Avenue intersection
Ramp
H - Route 1&9T
southbound ramp that
will connect the Tonnele
Avenue bridge over NJ
TRANSIT to the mainline
Viaduct over St. Paul's
Avenue |
| Stage
1 C: July
2010 - February 2011-
Completed |
- Shift Charlotte Avenue southbound
traffic to the Charlotte
Avenue southbound ramp
- Open Ramp A for Route 7 westbound
traffic from St. Paul's Avenue
only
- Construct the Route 1&9T mainline
over Charlotte Avenue
- Connect Ramp
G from Route
1&9T mainline over Charlotte
Avenue to the Charlotte Avenue
southbound ramp
- Continue superstructure construction
of bridges Ramp
B, Ramp C and Route 1&9T mainline Viaduct
- Construct Ramp
H, between
Tonnele Avenue and the Route
1&9T southbound Viaduct
- Construct the western remainder
of the Tonnele Avenue bridges
over NJ TRANSIT and Conrail
railroad tracks
- Modify the interim traffic
signal system at Tonnele
Circle
- Construct the piers of the
Route 1&9T Flyover Ramp adjacent
to the proposed westerly
curbline of Tonnele Avenue
Description
of Ramps:
Ramp
A - Will connect Route
1&9T northbound and St.
Paul's and James Avenues to
Route 7 westbound
Ramp G - Will
connect Route 1&9T southbound
with Charlotte Avenue immediately
north of the Route 1&9T/Newark
Avenue intersection
Ramp B - Will
exit the mainline west of Charlotte
Avenue and pass over Charlotte
Avenue and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Ramp C - Will
extend from Charlotte Avenue
to the mainline Viaduct, this
ramp will replace the connection
to the existing Viaduct by
collecting the traffic from
Route 1&9T northbound and
from Route 7 eastbound
Ramp H - Route
1&9T southbound ramp that
will connect the Tonnele Avenue
bridge over NJ TRANSIT to the
mainline Viaduct over St. Paul's
Avenue
Route 1&9T
Flyover Ramp - Will extend
from Route 1&9T northbound
passing over Tonnele Avenue,
NJ TRANSIT and Conrail railroad
tracks and ends in the area of
Spruce Street |
| Stage
1 D: February
2011 - July 2011 -
Completed |
- Continue construction
of the northbound and southbound
Viaducts and the Ramp
C and Ramp
B Viaducts
- Complete construction
of the Route 1&9T mainline
bridge over Charlotte
Avenue
- Divert southbound Tonnele
Avenue traffic from its
Stage 1C location to the
Stage 1D location along
the west curbline
- Construct the proposed
median barrier of Tonnele
Avenue and proposed Route
1&9T Flyover Ramp piers
- Shift Route 1&9T southbound
and Route 7 traffic to
the new Route 1&9T southbound
Description
of Ramps:
Ramp
C - Will extend
from Charlotte Avenue
to the mainline Viaduct,
this ramp will replace
the connection to the
existing Viaduct by collecting
the traffic from Route
1&9T northbound and
from Route 7 eastbound
Ramp
B - Will exit
the mainline west of
Charlotte Avenue and
pass over Charlotte Avenue
and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Route
1&9T Flyover Ramp
- Will extend
from Route 1&9T northbound
passing over Tonnele
Avenue, NJ TRANSIT and
Conrail railroad tracks
and ends in the area
of Spruce Street
|
| Stage
2 A: April
2010 - October 2011 -
Completed |
- Complete construction
of Ramp
C between Ramp
B bridge and the Tonnele
Circle
- Complete construction
of mainline Viaduct over
St. Paul's Avenue and Loop
Ramp D
- Complete construction
of Route
1&9T Flyover
Ramp
- Complete construction
of the Tonnele Avenue bridges
over NJ TRANSIT and Conrail railroad
tracks
Description
of Ramps:
Ramp
C - Will extend from
Charlotte Avenue to the mainline
Viaduct, this ramp will
replace the connection to
the existing Viaduct by collecting
the traffic from Route 1&9T
northbound and from Route
7 eastbound
Ramp
B - Will exit the
mainline west of Charlotte
Avenue and pass over Charlotte
Avenue and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Loop
Ramp D - Will pass
over the Tonnele Circle,
pass under Ramp I and the
mainline Route 1&9T before
tying into Route 1&9T southbound
Route 1&9T
Flyover Ramp - Will extend
from Route 1&9T northbound
passing over Tonnele Avenue,
NJ TRANSIT and Conrail railroad
tracks and ends in the area of
Spruce Street |
| Stage
2 B: October
2011 - March 2012 -
Completed |
- Shift Route 1&9T southbound
and Route 7 traffic to the
new Route 1&9T southbound
- Shift Route 1&9T northbound
and Route 7 traffic to the
new mainline Viaduct and
the Route
1&9T Flyover Ramp
- Close the St. Paul's Avenue
Viaduct westbound to traffic
- Begin construction of the
reconfigured Tonnele Circle
Description
of Ramps:
Route 1&9T Flyover
Ramp - Will extend from Route
1&9T
northbound passing over Tonnele Avenue,
NJ TRANSIT and Conrail railroad tracks
and ends in the area of Spruce Street |
| Stage
3 A: March
2012 - October 2012 -
Completed |
- Close existing access from the
Tonnele Circle to the Pulaski
Skyway
- Begin construction of Ramp
I bridge over Ramp
D
- Begin construction of Ramp
D bridge over the Tonnele Circle
- Complete construction of Ramp
B bridge over Charlotte
Avenue and Ramp C
- Complete construction of Ramp
C construction at Charlotte
Avenue
- Complete demolition of existing
Viaduct
- Construct connection of Ramp
B Viaduct to the Ramps
B/C approach to
Tonnele Avenue
Description of
Ramps:
Ramp
I - Will cross over Loop
Ramp D and the combined Ramp
B/C before tying into the existing
Pulaski Skyway westbound lanes,
this ramp will replace the existing
ramp
Ramp D - Will pass over
the Tonnele Circle, pass under Ramp I
and the mainline Route 1&9T before
tying into Route 1&9T southbound
Ramp
B - Will exit
the mainline west of
Charlotte Avenue and
pass over Charlotte Avenue
and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Ramp
C - Will extend
from Charlotte Avenue
to the mainline Viaduct,
this ramp will replace
the connection to the
existing Viaduct by collecting
the traffic from Route 1&9T
northbound and from Route
7 eastbound |
| Stage
3 B: July
2012 - October 2012 -
Completed |
- Construct Ramp
E between St.
Paul's Avenue and Ramp
D
- Complete construction of Ramp
I bridge over Ramp
D
- Open access from southbound
Tonnele Avenue to the Pulaski
Skyway
- Complete construction of Ramp
D bridge over the Tonnele
Circle
Description of
Ramps:
Ramp
E - Will extend northward
from St. Paul's Avenue to Ramp
D, providing access to mainline
Route 1&9T
Ramp D - Will pass over the Tonnele
Circle, pass under Ramp I and the mainline
Route 1&9T before tying into Route
1&9T southbound
Ramp I - Will
cross over Loop Ramp D and the combined
Ramp B/C before tying into the existing
Pulaski Skyway westbound lanes, this
ramp will replace the existing ramp |
| Stage
3 C: November
2012 - January 2013 -
Completed |
- Complete construction of the
reconfigured Tonnele Circle
- Open access from the Tonnele