Use aggregates from a single source and geological classification in any 1 construction item unless otherwise authorized. Use only sources of aggregate that are listed on the QPL.
The ME may allow aggregates from different sources if they are of the same geological classification and have similar specific gravities and aggregate properties.
Use test methods for gradation according to the appropriate provisions of AASHTO T 11 or T 27, unless otherwise noted. Gradations of aggregates in the various tables of this and other Sections are the percentages passing by weight.
The aggregate producer shall submit annually, to the ME for approval, a quality control plan for the aggregate products. The aggregate producer may obtain guidelines for developing the quality control plan from the ME upon request.
Provide an area for each stockpile of adequate size, reasonably uniform in cross-section, well drained, and cleared of foreign materials.
At concrete and HMA mixing plants, stockpile a sufficient quantity of aggregate to provide for a minimum of 1 day’s operations. Place the aggregate stockpiles on a firm, hard surface, such as a compacted aggregate, HMA, or concrete surface. Construct the stockpile by placing the aggregates in layers of not more than 3 feet thick.
Locate the piles so that there is no contamination by foreign material and no intermingling of aggregates from adjacent piles. Do not use steel-tracked equipment on the stockpiles.
Do not store aggregates from different sources, geological classifications, or of different gradings in stockpiles near each other unless a bulkhead is placed between the different materials. If blending aggregates of different gradings and from different sources, proportion through weigh hoppers. The ME may allow loader blending of aggregate stockpiles if included in the approved aggregate producer’s quality control plan. The Department will reject aggregates found segregated or contaminated. If a stockpile is rejected for segregation, the Contractor may reconstruct it for further evaluation. Use methods that prevent segregation when charging aggregates from stockpiles.
Do not use washed aggregates sooner than 24 hours after washing or until the surplus water has drained out and the material has a uniform moisture content.
Do not stockpile RAP higher than 15 feet. Cover or otherwise protect stockpiles of RAP for use in HMA to prevent buildup of moisture.
Obtain coarse aggregate as specified in 901.01. Use coarse aggregate that is broken stone or washed gravel graded as specified Table 901.03-1. Stockpile coarse aggregate as specified in 901.02. The ME will sample coarse aggregate as specified in Table 901.03-2.
| Table 901.03-1 Standard Sizes of Coarse Aggregate | ||||||||||||||||
| Amounts finer than each laboratory sieve, percentage by weight | ||||||||||||||||
| No. | Nominal Size | 4" | 3-1/2" | 3" | 2-1/2" | 2" | 1-1/2" | 1" | 3/4" | 1/2" | 3/8" | No. 4 | No. 8 | No. 16 | No. 50 | No. 100 |
| 1 | 3-1/2" - 1-1/2" | 100 | 90-100 | 25-60 | 0-15 | 0-5 | ||||||||||
| 2 | 2-1/2" - 1-1/2" | 100 | 90-100 | 35-70 | 0-15 | 0-5 | ||||||||||
| 3 | 2" - 1" | 100 | 90-100 | 35-70 | 0-15 | 0-5 | ||||||||||
| 4 | 1-1/2" - 3/4" | 100 | 90-100 | 20-55 | 0-15 | 0-5 | ||||||||||
| 5 | 1" - 1/2" | 100 | 90-100 | 20-55 | 0-10 | 0-5 | ||||||||||
| 57 | 1" - No. 4 | 100 | 95-100 | 25-60 | 0-10 | 0-5 | ||||||||||
| 67 | 3/4"- No. 4 | 100 | 90-100 | 20-55 | 0-10 | 0-5 | ||||||||||
| 7 | 1/2" - No. 4 | 100 | 90-100 | 40-70 | 0-15 | 0-5 | ||||||||||
| 8 | 3/8" - No. 8 | 100 | 85-100 | 10-30 | 0-10 | 0-5 | ||||||||||
| 9 | No. 4 - No. 16 | 100 | 85-100 | 10-40 | 0-10 | 0-5 | ||||||||||
| 10 | No. 4 - No. 200 | 100 | 85-100 | 10-30 | ||||||||||||
| Table 901.03-2 Coarse Aggregate Sampling | ||
| Coarse Aggregate, No. | Sample Size (pounds) | Frequency |
| 1 | 150 | 1000 tons or 830 cubic yards |
| 2 | 100 | 1000 tons or 830 cubic yards |
| 3 | 90 | 1000 tons or 830 cubic yards |
| 4 | 70 | 1000 tons or 830 cubic yards |
| 5 & 57 | 50 | 500 tons or 415 cubic yards |
| 67 | 30 | 500 tons or 415 cubic yards |
| 7 | 20 | 250 tons or 200 cubic yards |
| 8, 9, & 10 (stone sand) | 10 | 250 tons or 200 cubic yards |
Use broken stone that is uniform in texture and quality and that conforms to the requirements specified in Table 901.03.01-1.
| Table 901.03.01-1 Requirements for Broken Stone | ||
| Aggregate Property | Test Method | Maximum Percent |
| Weathered and deleterious stone | NJDOT A-3 | 5 |
| Broken stone other than that classification approved for use | NJDOT A-3 | 5 |
| Flat and elongated pieces for graded material No. 67 and larger length greater than 5 times the thickness or width) |
ASTM D 4791 | 10 |
| Absorption in cold water: | ||
| No. 9 and larger | AASHTO T 85 | 1.8 |
| Stone sand only (No. 10) | AASHTO T 84 | 2.0 |
| Sodium sulfate soundness, loss | AASHTO T 104 | 10 |
| Adherent fines in coarse aggregates: | ||
| HMA | NJDOT A-4 | 1.5 |
| Concrete | NJDOT A-4 | 1.0 |
| Percentage of wear (Los Angeles Abrasion Test): | ||
| HMA surface course | AASHTO T 96 | 40 |
| HMA intermediate or base course | AASHTO T 96 | 45 |
| Concrete surface course and bridge decks | AASHTO T 96 | 40 |
| Concrete, other | AASHTO T 96 | 50 |
| Dense-graded aggregate base course | AASHTO T 96 | 50 |
The geologic classifications are as follows:
Use washed gravel that is either crushed or uncrushed as specified and that conforms to the requirements specified in Table 901.03.02-1.
| Table 901.03.02-1 Requirements for Washed Gravel | ||
| Aggregate Property | Test Method | Maximum Percent |
| Weathered and deleterious gravel | NJDOT A-3 | 5 |
| Sodium sulfate soundness, loss | AASHTO T 104 | 10 |
| Soft particles as determined by scratch hardness test | NJDOT A-5 | 5 |
| Absorption in cold water: | ||
| No. 9 and larger | AASHTO T 85 | 1.8 |
| Stone sand only (No. 10) | AASHTO T 84 | 2.0 |
| Clay lumps, organic material, coal and other foreign or deleterious matter (Percent by weight or volume, whichever is greater) |
AASHTO T 112 | 0.5 |
| Chloride content | AASHTO T 260 | 0.06 |
| Crushed gravel material with at least 1 fractured face (Nicked gravel is not considered crushed) |
ASTM D 5821 | 60 |
| Adherent fines in coarse aggregates: | ||
| HMA | NJDOT A-4 | 1.5 |
| Concrete | NJDOT A-4 | 1.0 |
Quartz gravel is composed of natural pebbles, of which the majority is coarsely crystalline quartz. Ensure that the individual crystals within each pebble are intergrown into a tenacious, nonporous, interlocking texture that fractures as a single unit. Ensure that the percent of wear determined according to the Los Angeles Abrasion Test is as specified for the various uses, except that the percent maximum loss for quartz gravel is 50 percent.
When the sodium sulfate soundness and scratch hardness tests total 10 percent or more, the ME will perform a petrographic analysis to determine the amount of unsound and weathered material.
Obtain blast furnace slag as specified in 901.01. Use as blast furnace slag the air-cooled residue resulting from the production of pig iron. Ensure that the blast furnace slag consists of tough, durable, angular fragments that are uniform in density, absorption, and quality, and are free from flux stone, dirt, or other objectionable material. Stockpile blast furnace slag as specified in 901.02. Ensure that blast furnace slag conforms to the requirements specified in Table 901.04-1.
| Table 901.04-1 Requirements for Blast Furnace Slag | ||
| Aggregate Property | Test Method | Requirement |
| Weight per cubic foot (loose measure), pounds | AASHTO T 19 | 60 minimum |
| Percentage of wear, Los Angeles Abrasion Test | AASHTO T 96 | 50 maximum |
| Sulfur, percentage by weight | ASTM C 563 | 2 maximum |
Use coarse aggregate for HMA that is broken stone conforming to 901.03.01, except that the Contractor may use carbonate rock for the surface course only in shoulder areas, parking areas, or driveways.
For HMA surface course, use fine aggregate that is manufactured stone sand or natural sand.
Manufacture stone sand from aggregates conforming to 901.03, with not more than 15 percent passing the No. 200 sieve. When the percent passing the No. 200 sieve exceeds 15 percent, blend the stone sand with another approved sand so that the combination contains no more than 15 percent passing the No. 200 sieve, based on stockpile samples theoretically combined. Feed each sand source into the plant through a separate cold feed hopper.
Use natural sand consisting of material composed of predominantly angular particles of quartz or other hard durable minerals conforming to the quality and gradation requirements specified in Table 901.05.02-1 and Table 901.05.02-2, respectively.
| Table 901.05.02-1 Quality Requirements for Fine Aggregate used in HMA | ||
| Aggregate Property | Test Method | Maximum Percent |
| Mica | NJDOT A-2 | 2.0 |
| Absorption, cold water | AASHTO T 84 | 2.0 |
| Sodium sulfate soundness, loss | AASHTO T 104 | 5.0 |
| Clay and clay lumps | AASHTO T 88 | 5.0 |
| Table 901.05.02-2 Gradation Requirements for Fine Aggregate used in HMA |
|
| Sieve Size | Percent Passing |
| 3/8" | 100 |
| No. 4 | 95 - 100 |
| No. 8 | 80 - 100 |
| No. 200 | 0 - 5 |
For HMA surface course, wash and grade the natural sand. Natural sand does not need to be washed if it conforms to the requirements of 901.06.02, except that the allowable percent passing the No. 200 sieve is 0 to 5 percent.
The ME will sample fine aggregate at a frequency of 10 pounds for each 500 tons.
Use mineral filler for HMA that is free from lumps and foreign materials. Produce mineral filler from broken stone conforming to 901.03.01, fly ash conforming to 903.02.03.A, kiln dust from cement manufacture, or baghouse fines from an HMA plant. Produce baghouse fines from a consistent geological source of coarse and fine aggregate.
Ensure that a HMA mixture containing the filler retains 70 percent of its initial strength after an immersion cycle of 14 days when prepared according to AASHTO T 167 and tested according to AASHTO T 165.
Use mineral filler that, when tested according to AASHTO T 37, conforms to the gradation requirements specified in Table 901.05.03-1.
| Table 901.05.03-1 Gradation Requirements for Mineral Filler | |
| Sieve Size | Percent Passing |
| No. 50 | 95 - 100 |
| No. 200 | 70 - 100 |
Process RAP for HMA through screening and crushing operations to ensure that it is 100 percent passing the maximum aggregate size for the mixture.
Use RAP containing asphalt binder that is free from solvents or other contaminating substances. Ensure that the coarse aggregate contained in the RAP conforms to the requirements of 901.03.01 for broken stone and to the requirements of 901.03.02 for gravel. Ensure that the fine aggregate contained in the RAP conforms to the quality requirements in 901.05.02.
Use container glass that is derived from items such as bottles. Use glass that when crushed does not produce thin sliver and flake-like fragments. Ensure that no more than 5 percent of the material is glass derived from thin walled items, such as test tubes and other laboratory glassware, which are not considered to be container glass. Use CRCG that is 100 percent passing a 3/8-inch sieve.
Ensure that the CRCG contains no more than the maximum allowable percent of foreign materials specified in Table 901.05.05-1.
| Table 901.05.05-1 Allowable Percentages of Foreign Materials in CRCG | |
| Foreign Material | Maximum Percent1 |
| Paper | 2.5 |
| Metal | 3.0 |
| Plastic | 0.3 |
| Other | 0.5 |
| 1 | Determine the percent by dividing the weight of a foreign material retained on the No. 4 sieve by the total weight of material retained on the No. 4 sieve. |
Use GBSM that is derived from pre-consumer roofing shingles and is 100 percent passing a 3/4-inch sieve and that conforms to the composition requirements specified in Table 901.05.06-1.
| Table 901.05.06-1 Components of GBSM | |
| Material | Composition by Weight |
| Petroleum asphalt | 30 - 40% |
| Fibers | 10% Maximum |
| Mineral matter | 50 - 65% |
Submit a certificate of compliance, as specified in 106.07, for the GBSM. Submit test methods and results along with the certification.
Add the GBSM to the mixture through a feed system that individually proportions the GBSM and is approved by the ME.
For use as a coarse aggregate, fine aggregate, or both in HMA base course, the Contractor may use a maximum of 20 percent remediated ID-27 petroleum contaminated soil, produced by a NJDEP approved “Class B” recycling center operating pursuant to N.J.A.C 7:26A, provided it conforms to all quality requirements specified in 901.05.01 and 901.05.02.
The ME will test aggregates used in concrete according to AASHTO T 303 for potential expansion due to alkali-silica reactivity. The ME will classify aggregates that produce expansion of 0.1 percent or more after 14 days in solution as potentially reactive. Use potentially reactive aggregate in concrete only in conjunction with remedial agents such as fly ash, slag, or low alkali cement at the minimum addition rates specified in 903.03.01.
Use coarse aggregate that is broken stone or washed gravel conforming to 901.03.01 or 901.03.02, respectively, except do not use carbonate rock for concrete surface courses, bridge approach, or bridge decks. Use coarse aggregate that is the size or sizes shown in Table 903.03.06-1 and Table 903.03.06-2. Wash the coarse aggregate at least 24 hours before use.
For all classes of concrete and mortar, use fine aggregate that is washed and sized through a sand classifier plant and composed of quartz or other hard, durable particles. Ensure that the fine aggregate is subangular to angular in shape and free of soft particles. Derive fine aggregate from either a natural sand deposit resulting from glacial or water action, or produce a manufactured stone sand from the mechanical crushing of quarried rock or gravel that conforms to 901.03. Ensure that the fine aggregate also conforms to 901.01 and 901.02 and the gradation specified in Table 901.06.02-1.
| Table 901.06.02-1 Gradation Requirements for Fine Aggregate used in Concrete, Mortar, and Grout |
|
| Sieve Size | Percent Passing |
| 3/8" | 100 |
| No. 4 | 95 - 100 |
| No. 8 | 80 - 100 |
| No. 16 | 50 - 85 |
| No. 30 | 25 - 65 |
| No. 50 | 10 - 30 |
| No. 100 | 1 - 10 |
| No. 200 | 0.0 - 3.4 |
Ensure that the fine aggregate does not have more than 45 percent passing any sieve and retained on the next sieve and that the fineness modulus according to AASHTO M 6 is from 2.3 to 3.1 for concrete. Ensure that the fine aggregate conforms to the quality requirements specified in Table 901.06.02-2.
| Table 901.06.02-2 Quality Requirements for Fine Aggregate used in Concrete, Mortar, and Grout |
|||
| Aggregate Property |
Test Method |
Minimum Percent |
Maximum Percent |
| Mica | NJDOT A-2 | 2.0 | |
| Absorption, cold water | AASHTO T 84 | 2.0 | |
| Sodium sulfate soundness, loss | AASHTO T 104 | 5.0 | |
| Chloride content | AASHTO T 260 | 0.06 | |
| Lightweight pieces | AASHTO T 113 | 0.25 | |
| 7-Day mortar strength | NJDOT A-1 | 75 | |
The ME will test the fine aggregate for organic impurities and will reject it if it produces a color darker than the standard. Ensure that the mortar-making properties of the fine aggregate for concrete and mortar are not less than 100 percent of those of standard Ottawa sand.
The ME will sample fine aggregate at a frequency of 10 pounds for each 500 tons.
Manufacture lightweight aggregate by expanding or sintering material such as slate or shale by the rotary kiln process. Grade the lightweight aggregate to the size designation requirements for 3/4-inch to No. 4 sieves of Table 1 of ASTM C 330. Ensure that the lightweight aggregate producer has at least 5 years experience and a record of successful production and use of such product. Submit to the ME a certification of compliance as specified in 106.07. Ensure that the lightweight aggregate conforms to ASTM C 330 and the following requirements:
| Table 901.06.03-1 Sampling for Sodium Sulfate Soundness Testing | |
| Sieve Size | Weight |
| 1" to 3/4" | 2.20 pounds |
| 3/4" to 1/2" | 1.65 pounds |
| 1/2" to 3/8" | 1.10 pounds |
| 3/8" to No. 4 | 0.66 pounds |
Use grit for spreading over the epoxy waterproofing that is a subangular, natural, 98 percent silica sand. Ensure that 90 percent of the total sample by weight falls between the No. 4 and No. 30 sieves, with 0 percent passing the No. 30 sieve.
Use riprap stones that consist of a uniformly graded mixture of rock conforming to 901.03.01, such that 50 percent of the mixture by weight is equal to or larger than the designated median stone size (d50). Ensure that the stones are a well-graded mixture composed primarily of the larger stone sizes, but with a sufficient quantity of other sizes to fill the progressively smaller voids between the stones. Ensure that the diameter of the largest stone size is less than 1.5 times d50.
To fill gabion baskets, use crushed stone consisting of trap rock, granite, or gneiss and conforming to the requirements of 901.03.01. To prevent breakdown after placement, use aggregate that is free of cracks due to jointing, faulting, or other causes. Ensure that the aggregate conforms to the size requirements specified in Table 901.09-1.
| Table 901.09-1 Gabion Basket Stone Size Requirements | ||
| Basket Height | Minimum | Maximum |
| Less than 24 inches | 3 inch | 5 inch |
| Greater than or equal to 24 inches | 4 inch | 8 inch |
Use a DGA that is listed on the QPL. For gradation acceptance, the ME will sample DGA according to AASHTO T 2 for each 500 cubic yards. The ME will apply the gradation requirements to the material after it has been placed and compacted on the Project.
Produce virgin DGA from broken stone conforming to 901.03.01, crushed gravel conforming to 901.03.02, or blast furnace slag conforming to 901.04, except that at least 90 percent of all fragments shall contain at least 1 fractured face. Ensure that the DGA conforms to the following requirements and gradation:
| Table 901.10.01-1 Gradation Requirements for DGA | |
| Sieve Size | Percent Passing |
| 1-1/2" | 100 |
| 3/4" | 55 - 90 |
| No. 4 | 25 - 50 |
| No. 50 | 5 - 20 |
| No. 200 | 3 - 10 |
The Contractor may produce DGA from recycled concrete aggregate that conforms to the gradation and plasticity requirements specified in 901.10.01 and to the following:
| Table 901.10.02-1 Composition Requirements for RCA | ||
| Aggregate Property | Minimum Percent |
Maximum Percent |
| Concrete1 | 90 | |
| HMA | 10 | |
| Brick, cinder block, schist, concrete washout, and other friable material | 4 | |
| Reactive material | 0 | |
| Wood | 0.1 | |
| 1 | To meet the minimum requirement for concrete, the Contractor may add broken stone, vitreous china, or crushed gravel. Use broken stone conforming to 901.03.01 or crushed gravel conforming to 901.03.02, except that it need not be washed |
The Contractor may also produce DGA by mixing a maximum of 50 percent RAP conforming to 901.05.04 with previously approved virgin DGA.
Use a method of mixing that will ensure that the blended mixture is homogeneous with regard to particle size and composition. Ensure that the blended mixture meets the following requirements:
| Table 901.10.03-1 Composition Requirements for Virgin DGA and RAP Mixture | |
| Aggregate Property | Percent by Weight Maximum |
| RAP | 50 |
| Concrete | 5 |
| Brick, schist, and other friable material | 4 |
| Reactive material | 0 |
| Wood | 0.1 |
Use soil aggregates that are natural or prepared mixtures consisting predominately of hard, durable particles of stone, gravel, or sand. Mixtures may contain some silt, clay, or stone dust. Ensure that stone conforms to 901.03.01, and that gravel is crushed or uncrushed and conforms to 901.03.02. Use sand that is either natural sand resulting from the weathering process or stone sand produced by grinding or crushing of rock. Ensure that stone sand is manufactured from an aggregate source as specified in 901.03. Provide natural sand consisting of material composed of predominantly angular particles of quartz or other hard, durable minerals.
The Contractor may use soil aggregate produced from RPCSA produced by a NJDEP approved “Class B” recycling center operating pursuant to N.J.A.C 7:26A.
Do not place soil aggregate obtained from subaqueous sources until the ME has determined that its moisture content is not excessive.
Ensure that soil aggregate conforms to the following:
| Table 901.11-1 Standard Soil Aggregate Gradations | |||||||||||||
| Gradation Designations, percentage by weight passing square mesh sieves | |||||||||||||
| 6" | 4" | 2" | 1-1/2" | 1" | 3/4" | 1/2" | No. 4 | No. 8 | No. 16 | No. 50 | No. 100 | No. 200 | |
| I-1 | 100 | 70-100 | 50-95 | 30-60 | 5-25 | 0-7 | |||||||
| I-2 | 100 | 65-100 | 40-75 | 5-30 | 0-7 | ||||||||
| I-3 | 100 | 60-90 | 40-80 | 10-35 | 0-8 | ||||||||
| I-4 | 100 | 60-100 | 40-100 | 25-100 | 20-100 | 15-85 | 8-45 | 5-10 | |||||
| I-5 | 100 | 70-100 | 30-80 | 10-35 | 5-12 | ||||||||
| I-6 | 100 | 80-100 | 45-100 | 30-90 | 0-20 | 0-3 | |||||||
| I-7 | 100 | 80-100 | 35-100 | 25-90 | 5-50 | 0-8 | 0-2 | ||||||
| I-8 | 100 | 95-100 | 45-70 | 5-25 | 0-5 | ||||||||
| I-9 | 100 | 80-100 | 60-100 | 40-100 | 20-70 | 5-35 | 0-20 | 0-8 | |||||
| I-10 | 100 | 80-100 | 60-100 | 40-100 | 20-70 | 5-40 | 0-30 | 0-20 | |||||
| I-11 | 100 | 80-100 | 60-100 | 40-100 | 0-75 | 0-9 | |||||||
| I-12 | 100 | 70-100 | 0-75 | 0-5 | |||||||||
| I-13 | 100 | 30-100 | 0-12 | ||||||||||
| I-14 | See Text. | ||||||||||||
| I-15 | 100 | 80-100 | 30-80 | 0-25 | 0-10 | ||||||||
| Table 901.11-2 Electrochemical Requirements for Designation I-15 | ||
| Property | Test Method | Requirement |
| Resistivity, ohm-cm | AASHTO T 288 | Greater than 3000 |
| pH | AASHTO T 289 | Acceptable Range of 5 - 10 |
| Organic Content | AASHTO T 267 | 1.00% Maximum |
| Chloride | AASHTO T 291 | Less than 100 ppm |
| Sulfates | AASHTO T 290 | Less than 200 ppm |
The ME will sample soil aggregate as specified in Table 901.11-3.
| Table 901.11-3 Soil Aggregate Sampling | |
| Soil Designation | Sampling/ Frequency |
| I-1, I-2, I-3, I-4, I-5, I-6, I-7, I-8, I-9, & I-10 | According to AASHTO T 2 for each 500 cubic yards |
| I-11, I-12, I-13, & I-15 | According to AASHTO T 2 for each 500 cubic yards1 |
| I-14 | According to AASHTO T 2 for each 2000 cubic yards |
| 1 | After initial 10,000 cubic yards have been sampled, the ME will take 1 sample for each 2000 cubic yards, except if any sample fails or is borderline, then the ME will revert to 1 sample for each 500 cubic yards. The ME will continue with the 1 sample for each 500 cubic yards sampling frequency until the ME determines that the gradation requirements are consistently being met |
The ME may sample stockpiles before placement, but the Department will make the final and governing determination of conformance or nonconformance based on sampling and testing of the materials after they have been placed as specified in the Contract. Remove materials that do not conform and replace with conforming materials, or correct the deficiencies of the non-conforming materials. If corrective action has been taken, the ME will take an additional sample, and if necessary, one check sample. If the materials still do not conform after corrective action, the ME will not perform further testing until the Contractor tests and certifies that the rejected material has been corrected. After this certification, the ME will analyze an additional sample, and if this sample does not meet the requirements, the Contractor shall remove and replace the material.
Use the following temperature-volume correction (TVC) factors to convert the volume of bituminous materials, measured at the temperature at the point of use, to the volume at 60 °F:
| TVC = 1.0211326242 − 3.548988118 x 10−4 [T (°F)] + 4.49881 x 10−8 [T (°F)]2 |
| TVC = 1.02413769 − 4.0641418 x 10−4 [T (°F)] + 6.79176 x 10−8 [T (°F)]2 |
| Table 902.01-1 TVC Factors for Emulsified Asphalt Material | ||||||||
| Temp (°F) | Factor | Temp (°F) | Factor | Temp (°F) | Factor | Temp (°F) | Factor | |
| 40 | 1.0050 | 75 | 0.9953 | 110 | 0.9876 | 145 | 0.9792 | |
| 41 | 1.0048 | 76 | 0.9960 | 111 | 0.9874 | 146 | 0.9790 | |
| 42 | 1.0045 | 77 | 0.9958 | 112 | 0.9872 | 147 | 0.9787 | |
| 43 | 1.0043 | 78 | 0.9955 | 113 | 0.9869 | 148 | 0.9785 | |
| 44 | 1.0040 | 79 | 0.9953 | 114 | 0.9867 | 149 | 0.9782 | |
| 45 | 1.0038 | 80 | 0.9950 | 115 | 0.9864 | 150 | 0.9780 | |
| 46 | 1.0035 | 81 | 0.9948 | 116 | 0.9862 | 151 | 0.9778 | |
| 47 | 1.0033 | 82 | 0.9945 | 117 | 0.9860 | 152 | 0.9775 | |
| 48 | 1.0030 | 83 | 0.9943 | 118 | 0.9857 | 153 | 0.9773 | |
| 49 | 1.0028 | 84 | 0.9940 | 119 | 0.9855 | 154 | 0.9770 | |
| 50 | 1.0025 | 85 | 0.9938 | 120 | 0.9852 | 155 | 0.9768 | |
| 51 | 1.0023 | 86 | 0.9935 | 121 | 0.9850 | 156 | 0.9766 | |
| 52 | 1.0020 | 87 | 0.9933 | 122 | 0.9847 | 157 | 0.9763 | |
| 53 | 1.0018 | 88 | 0.9930 | 123 | 0.9845 | 158 | 0.9761 | |
| 54 | 1.0015 | 89 | 0.9928 | 124 | 0.9843 | 159 | 0.9758 | |
| 55 | 1.0013 | 90 | 0.9925 | 125 | 0.9840 | 160 | 0.9756 | |
| 56 | 1.0010 | 91 | 0.9923 | 126 | 0.9838 | 161 | 0.9754 | |
| 57 | 1.0008 | 92 | 0.9920 | 127 | 0.9835 | 162 | 0.9751 | |
| 58 | 1.0005 | 93 | 0.9918 | 128 | 0.9833 | 163 | 0.9749 | |
| 59 | 1.0003 | 94 | 0.9915 | 129 | 0.9830 | 164 | 0.9747 | |
| 60 | 1.0000 | 95 | 0.9913 | 130 | 0.9828 | 165 | 0.9744 | |
| 61 | 0.9998 | 96 | 0.9910 | 131 | 0.9826 | 166 | 0.9742 | |
| 62 | 0.9995 | 97 | 0.9908 | 132 | 0.9823 | 167 | 0.9739 | |
| 63 | 0.9993 | 98 | 0.9905 | 133 | 0.9821 | 168 | 0.9737 | |
| 64 | 0.9990 | 99 | 0.9903 | 134 | 0.9818 | 169 | 0.9735 | |
| 65 | 0.9988 | 100 | 0.9901 | 135 | 0.9816 | 170 | 0.9732 | |
| 66 | 0.9985 | 101 | 0.9899 | 136 | 0.9814 | 171 | 0.9730 | |
| 67 | 0.9983 | 102 | 0.9896 | 137 | 0.9811 | 172 | 0.9728 | |
| 68 | 0.9980 | 103 | 0.9884 | 138 | 0.9809 | 173 | 0.9725 | |
| 69 | 0.9978 | 104 | 0.9891 | 139 | 0.9806 | 174 | 0.9723 | |
| 70 | 0.9975 | 105 | 0.9889 | 140 | 0.9804 | 175 | 0.9721 | |
| 71 | 0.9973 | 106 | 0.9886 | 141 | 0.9802 | 176 | 0.9718 | |
| 72 | 0.9970 | 107 | 0.9884 | 142 | 0.9799 | 177 | 0.9716 | |
| 73 | 0.9968 | 108 | 0.9881 | 143 | 0.9797 | 178 | 0.9713 | |
| 74 | 0.9965 | 109 | 0.9879 | 144 | 0.9794 | 179 | 0.9711 | |
Use asphalt binder that conforms to AASHTO M 320, Table 1. Use Grade 64-22, except the ME may direct that an asphalt of softer grade be used when the mixture contains a high percentage of RAP and except where otherwise specified.
When specified, use PG 76-22 asphalt binder that is a storage-stable, pre-blended, homogeneous, polymer modified asphalt binder using styrene-butadiene or styrene-butadiene-styrene formulations. Ensure that the binder’s rolling thin film oven test (AASHTO T 240) residue has a minimum elastic recovery (ASTM D 6084, Procedure A) of 60 percent when tested for at 25 °C.
The asphalt binder producer shall provide the asphalt binder quality control plan annually to the ME for approval. Ensure that the quality control plan conforms to AASHTO R 26.
Submit to the ME a certification of compliance, as specified in 106.07, for the asphalt binder. The ME will perform quality assurance sampling and testing of each asphalt binder lot as defined in the approved quality control plan.
Use cutback asphalt of the rapid-curing types conforming to AASHTO M 81 and cutback asphalt of the medium-curing types conforming to AASHTO M 82.
For cutback asphalt that will not be used as a penetrating prime coat, use and store according to N.J.A.C 7:27-16 et seq., which includes a limitation for use only between October 15 and April 15.
The cutback asphalt producer shall provide the cutback asphalt quality control plan annually to the ME for approval.
Submit to the ME a certification of compliance, as specified in 106.07, for the asphalt binder. The ME will perform quality assurance sampling and testing of each cutback asphalt lot as defined in the approved quality control plan.
Use emulsified asphalts of the rapid-setting (RS), medium-setting (MS), and slow-setting (SS) types conforming to AASHTO M 140. Use cationic emulsified asphalts of the rapid-setting (CRS), medium-setting (CMS), and slow-setting (CSS) types conforming to AASHTO M 208.
The emulsified asphalt producer shall provide the emulsified asphalt quality control plan annually to the ME for approval.
Submit to the ME a certification of compliance, as specified in 106.07, for the asphalt binder. The ME will perform quality assurance sampling and testing of each emulsified asphalt lot as defined in the approved quality control plan.
Use a tack coat consisting of homogeneous cationic emulsified asphalt modified using styrene-butadiene, styrene-butadiene-styrene, natural latex, or synthetic latex and conforming to the requirements specified in Table 902.01.04-1.
| Table 902.01.04-1 Requirements for Polymer Modified Tack Coat |
|||
| Tests on Emulsion | Test Method | Minimum | Maximum |
| Elastic Recovery on Residue @10 °C, % | AASHTO T 301 | 58 | |
| Total Residue by Distillation, % | AASHTO T 591 | 63 | |
| Viscosity @ 25 °C, SSF | AASHTO T 72 | 20 | 100 |
| Particle Charge | AASHTO T 59 | Positive | |
| Storage Stability Test, 1 day, % | AASHTO T 59 | 1 | |
| Sieve Test, % mass (850 mm) | AASHTO T 59 | 0.10 | |
| Demulsibility, % | AASHTO T 592 | 55 | |
| 1 | AASHTO T 59 modified to maintain a temperature of 177 ± 5 °C for 15 minutes. Use an ASTM 16C thermometer to monitor the temperature of the emulsion during distillation. |
| 2 | For demulsibilty testing, use 35 mL of 0.8 percent dioctyl sodium sulfosuccinate solution. |
The requirements for specific HMA mixtures are identified by the abbreviated fields in the Item description as defined as follows:
HOT MIX ASPHALT 12.5H64 SURFACE COURSE
| Provide materials as specified: | ||
| Aggregates for Hot Mix Asphalt | 901.05 | |
| Asphalt Binder | 902.01.01 | |
Mix HMA in a plant that is listed on the QPL and conforms to the requirements for HMA Plants as specified in 1009.01.
Composition of the mixture for HMA surface course is coarse aggregate, fine aggregate, and asphalt binder, and may also include mineral filler and up to 15 percent Reclaimed Asphalt Pavement (RAP). Ensure that the finished mix does not contain more than a total of 1 percent by weight contamination from Crushed Recycled Container Glass (CRCG).
The composition of the mixture for HMA base or intermediate course is coarse aggregate, fine aggregate, and asphalt binder, and may also include mineral filler and up to 35 percent of recycled materials. The 35 percent of recycled materials may consist of a combination of RAP, CRCG, Ground Bituminous Shingle Material (GBSM), and RPCSA, with the following individual limits:
| Table 902.02.02-1 Use of Recycled Materials in HMA Base or Intermediate Course |
|
| Recycled Material | Maximum Percentage |
| RAP | 25 |
| CRCG | 10 |
| GBSM | 5 |
| RPCSA | 20 |
Combine the aggregates to ensure that the resulting mixture meets the grading requirements specified in Table 902.02.03-1. In determining the percentage of aggregates of the various sizes necessary to meet gradation requirements, exclude the asphalt binder.
Ensure that the combined coarse aggregate, when tested according to ASTM D 4791, has less than 10 percent flat and elongated pieces retained on the No. 4 sieve and larger. Measure aggregate using the ratio of 5:1, comparing the length (longest dimension) to the thickness (smallest dimension) of the aggregate particles.
Ensure that the combined fine aggregate in the mixture conforms to the requirements specified in Table 902.02.02-2. Ensure that the material passing the No. 40 sieve is non-plastic when tested according to AASHTO T 90.
| Table 902.02.02-2 Additional Fine Aggregate Requirements for HMA | ||
| Tests | Test Method | Minimum Percent |
| Uncompacted Void Content of Fine Aggregate | AASHTO T 304, Method A | 45 |
| Sand Equivalent | AASHTO T 176 | 45 |
Submit a mix design including a job mix formula (JMF) for each mixture on forms supplied by the ME. Include a statement naming the source of each component and a report showing that the results conform to the criteria specified in Table 902.02.03-1, Table 902.02.03-2, and Table 902.02.03-3. If a change in sources or properties of materials occur, the ME may require the HMA producer to establish a new mix design and to obtain approval before production can continue.
To establish the JMF for each mix design, determine the percentage of dry weight of aggregate passing each required sieve size and an optimum percentage of asphalt binder based upon the weight of the total mix. Determine the optimum percentage of asphalt binder according to AASHTO M 323 and R 35. Combine the aggregates to ensure that the resulting mixture conforms to the grading requirements specified in Table 902.02.03-1. In determining the percentage of aggregates of the various sizes necessary to conform to gradation requirements, exclude the asphalt binder.
| Table 902.02.03-1 HMA Mixtures Nominal Maximum Size of Aggregate – Grading Of Total Aggregate |
||||||||||||
| Sieve Size | Nominal Maximum Aggregate Size – Control Point (Percent Passing) | |||||||||||
| 37.5 mm | 25 mm | 19 mm | 12.5 mm | 9.5 mm | 4.75 mm | |||||||
| Min. | Max. | Min. | Max. | Min. | Max. | Min. | Max. | Min. | Max. | Min. | Max. | |
| 2" | 100 | – | – | – | – | – | – | – | – | – | – | – |
| 1-1/2" | 90 | 100 | 100 | – | – | – | – | – | – | – | – | – |
| 1" | – | 90 | 90 | 100 | 100 | – | – | – | – | – | – | – |
| 3/4" | – | – | – | 90 | 90 | 100 | 100 | – | – | – | – | – |
| 1/2" | – | – | – | – | – | 90 | 90 | 100 | 100 | – | 100 | – |
| 3/8" | – | – | – | – | – | – | – | 90 | 90 | 100 | 95 | 100 |
| No. 4 | – | – | – | – | – | – | – | – | – | 90 | 90 | 100 |
| No. 8 | 15 | 41 | 19 | 45 | 23 | 49 | 28 | 58 | 32 | 67 | – | – |
| No. 16 | – | – | – | – | – | – | – | – | – | – | 30 | 60 |
| No. 200 | 0 | 6 | 1 | 7 | 2 | 8 | 2 | 10 | 2 | 10 | 6 | 12 |
| Table 902.02.03-2 Gyratory Compaction Effort for HMA Mixtures | |||
| Compaction Level | ESALs1 (millions) | Ndes | Nmax |
| L | < 0.3 | 50 | 75 |
| M | 0.3 to < 3 | 75 | 115 |
| H | ≥3 | 100 | 160 |
| 1 | Design ESALs (Equivalent (80kN) Single-Axle Loads) refer to the anticipated traffic level expected on the design lane over a 20-year period. |
| Table 902.02.03-3 HMA Requirements for Design | ||||||||||
| Compaction Levels | Required Density(% of Theoretical Max. Specific Gravity) | Voids in Mineral Aggregate (VMA),% (minimum) | Voids Filled With Asphalt (VFA)1 % | Dust-to-Binder Ratio | ||||||
| Nominal Max. Aggregate Size, mm | ||||||||||
| @Ndes2 | @Nmax | 37.5 | 25.0 | 19.0 | 12.5 | 9.5 | 4.75 | |||
| L | 96.0 | ≤ 98.0 | 11.0 | 12.0 | 13.0 | 14.0 | 15.0 | 16.0 | 70 - 80 | 0.6 - 1.2 |
| M | 96.0 | ≤ 98.0 | 11.0 | 12.0 | 13.0 | 14.0 | 15.0 | 16.0 | 65 - 78 | 0.6 - 1.2 |
| H | 96.0 | ≤ 98.0 | 11.0 | 12.0 | 13.0 | 14.0 | 15.0 | 16.0 | 65 - 75 | 0.6 - 1.2 |
| 1 | For 37.5-mm nominal maximum size mixtures, the specified lower limit of the VFA is 64 percent for all design traffic levels. |
| 2 | As determined from the values for the maximum specific gravity of the mix and the bulk specific gravity of the compacted mixture. Maximum specific gravity of the mix is determined according to AASHTO T 209. Bulk specific gravity of the compacted mixture is determined according to AASHTO T 166. For verification, specimens must be between 95.0 and 97.0 percent of maximum specific gravity at Ndes. |
At the ME’s request, test the mix design to ensure that it meets a minimum tensile strength ratio of 80 percent, when tested according to AASHTO T 283. The ME will require tensile strength ratio testing for new aggregate sources and for aggregates suspected of stripping susceptibility.
For each mix design, submit with the mix design forms 2 gyratory specimens and 1 loose sample corresponding to the composition of the JMF. The ME will use these to verify the properties of the JMF. Compact the specimens to the design number of gyrations (Ndes). For the mix design to be acceptable, all gyratory specimens must comply with the requirements specified in Table 902.02.03-1 and Table 902.02.03-3. The ME reserves the right to be present at the time the gyratory specimens are molded.
The ME’s may verify a mix on an annual basis rather than on a project-to-project basis if the properties and proportions of the materials do not change. If written verification is submitted by the HMA supplier that the same source and character of materials are to be used, the ME may waive the requirement for the design and verification of previously approved mixes.
| Table 902.02.04-1 Hot Mix Asphalt Requirements for Control | ||||||||
| Compaction Levels | Required Density (% of Theoretical Max. Specific Gravity) | Voids in Mineral Aggregate (VMA), % (minimum) | Dust-to-Binder Ratio | |||||
| Nominal Max. Aggregate Size, mm | ||||||||
| @Ndes1 | 37.5 | 25.0 | 19.0 | 12.5 | 9.5 | 4.75 | ||
| L, M, H | 95.0 – 97.0 | 11.0 | 12.0 | 13.0 | 14.0 | 15.0 | 16.0 | 0.6 - 1.3 |
| 1 | As determined from the values for the maximum specific gravity of the mix and the bulk specific gravity of the compacted mixture. Maximum specific gravity of the mix is determined according to AASHTO T 209. Bulk specific gravity of the compacted mixture is determined according to AASHTO T 166. |
Mix OGFC and MOGFC in a plant that is listed on the QPL and conforms to the requirements for HMA plants as specified in 1009.01.
Composition of mixture for OGFC and MOGFC is coarse aggregate, fine aggregate and asphalt binder. Ensure that the mixture conforms to the following requirements:
Submit a mix design including JMF for each mixture on forms supplied by the Department. Include a statement naming the source of each component and a report with the results for the criteria specified in Table 902.03.03-1. Design the mix to meet the criteria in Table 902.03.03-1.
In the JMF for each mixture, establish the percentage of dry weight of aggregate passing each required sieve size and an optimum percentage of asphalt binder based upon the weight of the total mix. Determine the optimum asphalt binder content for OGFC as specified in NJDOT B-7. Determine the optimum asphalt binder content for MOGFC as specified in NJDOT B-8. Ensure that the JMF is within the master range specified in Table 902.03.03-1.
Prepare compacted test specimens for submittal to the ME at least 30 days before the initial production date. Prepare these specimens from material mixed according to the final JMF, using 50 gyrations of the Superpave gyratory compactor according to AASHTO T 312.
The ME will test 2 specimens to verify that the final JMF produces a mixture that has a minimum void content as specified in Table 902.03.03-1. The ME will determine percent air voids according to AASHTO T 209, and either NJDOT B-6 or AASHTO T 331.
The ME will test 6 specimens according to AASHTO T 283, except for the following:
If the tensile strength ratio falls below 80 percent, adjust the mixture to satisfy the minimum requirement. Adjustments may include the use of anti-stripping agents.
For MOGFC only, the ME will test 2 test specimens for abrasion and impact resistance using a modified L. A. Abrasion Test according to NJDOT B-8. The maximum allowable loss as calculated by this method is 30 percent.
Do not modify the JMF unless the ME approves the modification.
Perform and meet requirements for quality control testing as specified in 902.02.04.C. Ensure that the mix meets the requirements as specified in 902.02.04.A, otherwise the RE or ME will reject the material.
During production, the ME will take one random acceptance sample from each 700 tons of production to verify composition. Conduct air voids and draindown tests as directed by the ME.
If the composition testing results are outside of the production control tolerances specified in Table 902.03.03-2 for an acceptance sample, determine if a plant adjustment is needed and immediately run a quality control sample. If the quality control sample is also outside of the control tolerances in Table 902.03.03-2, immediately take corrective action to bring the mix into compliance. Take additional quality control samples after the corrective action to ensure that the mix is within the production control tolerances. If 2 consecutive acceptance samples are outside the tolerances specified in Table 902.03.03-2, immediately stop production. Obtain ME approval of a plant correction plan before resuming production. Upon restarting production, do not transport mixture to the Project Limits before the results of a QC sample from the mixture indicate that the mixture meets JMF tolerances. The ME will reject mixture produced at initial restarting that does not meet tolerances.
The ME will perform sampling according to NJDOT B-2 or ASTM D 3665, and will perform testing for composition according to AASHTO T 308 or NJDOT B-5. Perform testing for air voids according to AASHTO T 209 and either NJDOT B-6 or AASHTO T 331. Perform testing for draindown according to NJDOT B-7 or NJDOT B-8.
| Table 902.03.03-1 JMF Master Ranges and Mixture Requirements Open-graded Friction Course |
||||
| Mixture Designations (% Passing1) | ||||
| Sieve Sizes | OGFC – 9.5 mm | MOGFC – 12.5 mm | MOGFC – 9.5 mm | |
| 3/4" | 100 | |||
| 1/2" | 100 | 85 - 100 | 100 | |
| 3/8" | 80 - 100 | 35 - 60 | 85 - 100 | |
| No. 4 | 30 - 50 | 10 - 25 | 20 - 40 | |
| No. 8 | 5 - 15 | 5 - 10 | 5 - 10 | |
| No. 200 | 2.0 - 5.0 | 2.0 - 5.0 | 2.0 - 4.0 | |
| Minimum asphalt binder, %1 | 5.5 | 5.7 | 6.0 | |
| Minimum % Air Voids, design | 15% | 20% | 18% | |
| Minimum lift thickness, design | 3/4" | 1-1/4" | 3/4" | |
| 1 | Aggregate percent passing to be determined based on dry aggregate weight. Asphalt binder content to be determined based on total weight of mix. |
| Table 902.03.03-2 Production Control Tolerances for OGFC and MOGFC Mixtures |
|
| Sieve Sizes | Production Control Tolerances from JMF1 |
| 1/2" | ±6.0 |
| 3/8" | ±5.5 |
| No. 4 | ±5.5 |
| No. 8 | ±4.5 |
| No. 200 | ±2.0 |
| Asphalt binder, % (AASHTO T 308) | ±0.40 |
| Asphalt binder, % (NJDOT B-5) | ±0.15 |
| Minimum % Air Voids | 1.0% less than design requirement |
| 1 | Production tolerances may fall outside of the wide band gradation limits in Table 902.03.03-1. |
Mix ultra-thin HMA in a plant listed on the QPL conforming to the requirements for HMA plants specified in 1009.01.
Use ultra-thin HMA that consists of coarse aggregate, fine aggregate, and polymer modified asphalt binder and that may contain mineral filler. Do not add RAP, CRCG, GBSM, or RPCSA. Combine the material in such proportions that the total aggregate and asphalt binder conform to the composition percentages specified in Table 902.04.02-1.
To produce the ultra-thin HMA, use aggregates and asphalt binder that conforms to the following:
| Table 902.04.01-1 Coarse Aggregate Properties | ||
| Tests | Test Method | Maximum Percent |
| Percentage of wear, Los Angeles Abrasion Test | AASHTO T 96 | 25 |
| Micro Deval | AASHTO T 327 | 18 |
At least 30 days before the initial production date, submit a JMF, within the limits of Table 902.04.02-1, to the ME for approval on forms supplied by the Department. Include in the submission a statement naming the source of each component and the results of all applicable tests.
If the source of any component material changes, submit a new JMF and obtain ME approval before using the new material. When unsatisfactory results or other conditions make it necessary, the ME may require a new JMF.
Design the ultra-thin HMA so that it has a draindown of less than 0.1 percent when tested according to AASHTO T 305.
When tested for moisture sensitivity according to AASHTO T 283, ensure that the ultra-thin HMA has a tensile strength ratio of at least 80 percent. Prepare specimens according to AASHTO T 312, and test according to T 283 except for the following:
Size, uniformly grade, and combine aggregate fractions in proportions so that the grading of total aggregate and asphalt binder in the JMF conform to the composition by mass percentages specified in Table 902.04.02-1.
| Table 902.04.02-1 JMF Requirements for Ultra-Thin Friction Course | ||
| Sieve Size | Total % Passing By Mass | Production Control Tolerances from JMF |
| 1/2" | 100 | ±6.0 |
| 3/8" | 75-100 | ±5.5 |
| No. 4 | 23-38 | ±5.5 |
| No. 8 | 19-31 | ±4.5 |
| No. 16 | 15-23 | ±4.0 |
| No. 30 | 10-18 | ±4.0 |
| No. 50 | 8-14 | ±4.0 |
| No. 100 | 5-10 | ±3.0 |
| No. 200 | 4.0-7.0 | ±2.0 |
| Asphalt % | 4.5 - 5.7 | Ignition Oven ±0.40 Hot Bins ±0.15 |
Ensure that the mix meets the requirements as specified in 902.02.04.A, otherwise the RE or ME will reject the material. Maintain the temperature of the mix between 300 °F and 330 °F. Perform and meet requirements for quality control testing as specified in 902.02.04.C.
During production, the ME will take one random acceptance sample from each 700 tons of production to verify composition. Conduct draindown tests as directed by the ME.
If the composition testing results are outside of the production control tolerances specified in Table 902.04.02-1 for an acceptance sample, determine if a plant adjustment is needed and immediately run a quality control sample. If the quality control sample is also outside of the control tolerances in Table 902.04.02-1, immediately take corrective action to bring the mix into compliance. Take additional quality control samples after the corrective action to ensure that the mix is within the production control tolerances. If 2 consecutive acceptance samples are outside the tolerances specified in Table 902.04.02-1, immediately stop production. Obtain ME approval of a plant correction plan before resuming production. Upon restarting production, do not transport mixture to the Project Limits before the results of a QC sample from the mixture indicate that the mixture meets JMF tolerances. The ME will reject mixture produced at initial restarting that does not meet tolerances.
The ME will perform sampling according to NJDOT B-2 or ASTM D 3665, and will perform testing for composition according to AASHTO T 308, or NJDOT B-5. Perform testing for draindown according to NJDOT B-7 or NJDOT B-8.
Mix SMA in a plant that is listed on the QPL and conforms to the requirements for HMA plants as specified in 1009.01.
The composition of the SMA mixture is coarse aggregate, fine aggregate, mineral filler, mineral fibers or cellulose fibers, and polymer modified asphalt binder.
Use asphalt binder for SMA that is PG 76-22 as specified in 902.01.01.
For coarse aggregate in SMA, use crushed stone conforming to 901.05.01 and Table 902.05.01-1.
| Table 902.05.01-1 Coarse Aggregate Properties for SMA | ||
| Tests | Test Method | Maximum Percent |
| Percentage of wear, Los Angeles Abrasion Test | AASHTO T 96 | 30 |
| Flat and Elongated, 5 to 1 (Material Retained on the No. 4 Sieve) |
ASTM D 4791 | 5 |
| Flat and Elongated, 3 to 1 (Material Retained on the No. 4 Sieve) |
ASTM D 4791 | 20 |
For fine aggregate, use stone sand conforming to 901.05.02. Ensure that the combined fine aggregate in the mixture conforms to the requirements in Table 902.02.02-2.
For mineral filler, use rock dust or crushed limestone conforming to AASHTO M 17. Ensure that the mineral filler has a plasticity index of less than 4 percent when tested according to AASHTO T 90.
Do not add RAP, CRCG, GBSM, or RPCSA to the mixture.
Add stabilizing fibers consisting of mineral fiber or cellulose fiber conforming to AASHTO MP 8. Use only one type per mix design. If using mineral fibers, use between 0.4 and 0.6 percent by weight of total mix. If using cellulose fibers, use between 0.3 and 0.4 percent by weight of total mix. Provide control to accurately proportion the fibers into the mixture within ±10 percent of the required weight, and use equipment that ensures uniform dispersion of the fibers. If using pre-packaged bags of fibers added to the pugmill during the dry mix cycle, follow the manufacturer’s recommendations for the dry and wet mixing time. Store fibers in a dry location with a storage temperature not to exceed 120 °F. The supplier of the cellulose or mineral fibers shall provide a certification of compliance, as specified in 106.07, for the fibers. Ensure that a technical representative from the fiber supplier is at the HMA plant for the first full day of production for technical assistance.
Design the SMA to meet the requirements in Table 902.05.02-1 and Table 902.05.02-2. Prepare the JMF according to AASHTO R 46. Determine the JMF at 4 percent air voids and 75 gyrations of the Superpave gyratory compactor.
| Table 902.05.02-1 SMA Specification Band (% passing) nominal-maximum aggregate size |
||||
| Production Control Tolerances1 |
Sieve Size | 19 mm % Passing |
12.5 mm % Passing |
9.5 mm % Passing |
| 0% | 1" | 100 | 100 | 100 |
| ±5% | 3/4" | 90-100 | 100 | 100 |
| ±5% | 1/2" | 50-88 | 90-100 | 100 |
| ±5% | 3/8" | 25-60 | 50-80 | 70-95 |
| ±4% | No. 4 | 20-28 | 20-35 | 30-50 |
| ±4% | No. 8 | 16-24 | 16-24 | 20-30 |
| ±4% | No. 16 | – | – | 0-21 |
| ±3% | No. 30 | – | – | 0-18 |
| ±3% | No. 50 | – | – | 0-15 |
| ±2% | No. 200 | 8.0-11.0 | 8.0-11.0 | 8.0-12.0 |
| Coarse Aggregate Fraction | Portion Retained on No. 4 Sieve | Portion retained on No. 4 Sieve | Portion retained on No. 8 Sieve | |
| Minimum Lift Thickness | 2 inches | 1-1/2 inch | 1 inch | |
| 1 | Production tolerances may fall outside of the wide band gradation limits. |
| Table 902.05.02-2 SMA Mixtures Volumetrics For Design and Plant Production | ||
| Property | Production Control Tolerances |
Requirement |
| Air Voids | ±1% | 4.0% |
| Voids in Mineral Aggregate (VMA) | – | 17.0% minimum |
| VCAmix | – | Less than VCAdry |
| Draindown @ production temperature | – | 0.30% maximum |
| Asphalt Binder Content ( NJDOT B-5 ) | ±0.15% | 6% minimum |
| Asphalt Binder Content (AASHTO T 308) | ±0.40% | 6% minimum |
| Tensile Strength Ratio (AASHTO T 283) | – | 80% minimum |
Perform quality control testing as specified in 902.02.04.C. Ensure that the mix meets the requirements as specified in 902.02.04.A, otherwise the RE or ME will reject the material.
During production at the plant, the ME will take a sample from each 700 tons of production to verify composition and air voids. Conduct draindown, VCAmix, VCAdry, and VMA testing as directed by the ME. Perform tests according to AASHTO PP 41.
If the testing results are outside of the production control tolerances specified in Table 902.05.02-1 and Table 902.05.02-2 for an acceptance sample, determine if a plant adjustment is needed and immediately run a quality control sample. If the quality control sample is also outside of the control tolerances in Table 902.05.02-1, immediately take corrective action to bring the mix into compliance. Take additional quality control samples after completing the corrective action to ensure that the mix is within tolerances. If 2 consecutive acceptance samples are outside the tolerances specified in Table 902.05.02-1 and Table 902.05.02-2, immediately stop production. Obtain ME approval of a plant correction plan before resuming production. Upon restarting production, do not transport mixture to the Project Limits before the results of a QC sample from the mixture indicate that the mixture meets JMF tolerances. The ME will reject mixture produced at initial restarting that does not meet tolerances.
The ME will perform sampling according to NJDOT B-2 or ASTM D 3665, and will perform testing for composition according to AASHTO T 308, or NJDOT B-5. The ME will determine bulk specific gravity of the compacted sample according to AASHTO T 166 or AASHTO T 331. The ME will use the most current QC maximum specific gravity test result, obtained according to AASHTO T 209, in calculating the volumetric properties of the SMA. Perform testing for draindown according to AASHTO T 305.
Mix ASDC in a plant that is listed on the QPL and conforms to the requirements specified in 1009.01.
The mixture shall consist of asphalt binder and aggregate. Use asphalt binder that is PG 64-22 as specified in 902.01.01. Use aggregate that conforms to 901.05 and the gradation requirements specified in Table 902.06.01-1.
| Table 902.06.01-1 Gradation Requirements and Tolerances for ASDC | ||
| Production Tolerance (Variation From JMF) |
Sieve Size | JMF (Percent Passing) |
| ±0.0 | 1" | 100 |
| ±6.0 | 3/4" | 95 - 100 |
| ±5.5 | 1/2" | 85 - 100 |
| ±5.5 | 3/8" | 60 - 90 |
| ±5.5 | No. 4 | 15 - 25 |
| ±4.5 | No. 8 | 2 - 10 |
| ±2.0 | No. 200 | 2 - 5 |
Design the mixture to have an asphalt binder content of 3 ± 1/2 percent by weight of dry aggregate.
Submit to the ME for approval, a JMF for the material that includes the source of each component.
Establish with the JMF the percentage of dry weight of aggregate passing each required sieve size and the optimum percentage of asphalt binder based upon the weight of the total mix. Ensure that the design values of percent passing each sieve size are within the gradation band specified in Table 902.06.01-1. Design the mix to have a permeability of 2000 ± 500 feet per day.
At least 45 days before the production of the asphalt-stabilized drainage course, submit a mix design for approval. In addition, submit samples of the component materials to the ME for verification. Submit the following quantities:
| Table 902.06.02-1 Verification Samples for Asphalt-Stabilized Drainage Course |
|
| Component | Quantity |
| Each Aggregate Component | 35 pound |
| Asphalt Binder | 1 gallon |
| Anti-Stripping Agent, if needed | 0.264 gallon |
The ME will perform gradation testing according to AASHTO T 27 on the submitted aggregate sample. The ME will prepare the specimens for permeability testing according to AASHTO T 167. The ME will compact specimens at 260 °F. The ME will determine permeability according to NJDOT B-1.
At the ME’s option, verification may be done on an annual basis for a mix rather than on a project-to-project basis, provided the properties and proportions of the materials do not change. If written verification is submitted by the HMA supplier that the same source and character of materials are to be used, the ME may waive the requirement for the design and verification of previously approved mixes.
Perform quality control testing as specified in 902.02.04.C. Ensure that the mix meets the requirements as specified in 902.02.04.A, except that the temperature of the mix at discharge is required to be between 230 °F and 275 °F, otherwise the RE or ME will reject the material.
During production, the ME will take one random acceptance sample from each 700 tons of production to verify composition. Conduct draindown tests as directed by the ME.
If the composition testing results are outside of the production control tolerances specified in Table 902.06.01-1 for an acceptance sample, determine if a plant adjustment is needed and immediately run a quality control sample. If the quality control sample is also outside of the control tolerances specified in Table 902.06.01-1, immediately take corrective action to bring the mix into compliance. Take additional quality control samples after the corrective action to ensure that the mix is within tolerances. If 2 consecutive acceptance samples are outside the tolerances specified in Table 902.06.01-1, immediately stop production. Obtain ME approval of a plant correction plan before resuming production. Upon restarting production, do not transport mixture to the Project before the results of a QC sample from the mixture indicate that the mixture meets JMF tolerances. The ME will reject mixture produced at initial restarting that does not meet tolerances.
The ME will perform sampling according to NJDOT B-2 or ASTM D-3665 and will perform testing for composition according to AASHTO T 308 or NJDOT B-5. If directed by the ME, perform testing for draindown according to AASHTO T 305.
Mix AR-OGFC in a plant listed on the QPL and conforming to the requirements for HMA plants specified in 1009.01. Ensure the HMA plant is equipped with asphalt-rubber binder blending equipment as specified in 1009.03.
Composition of mixture for AR-OGFC is coarse aggregate, fine aggregate and asphalt-rubber binder. Ensure that the mixture conforms to the following requirements:
- Ground Crumb Rubber. Ensure that the ground crumb rubber has a specific gravity of 1.15 ± 0.05, is free of wire or other contaminating materials, and contains not more than 0.5 percent fabric. Use crumb rubber that is ambient ground and conforms to the gradation requirements specified in Table 902.07.02-1. Ensure that the moisture content is less than 0.75 percent. The Contractor may add up to four percent calcium carbonate by weight of the granulated rubber, to prevent the particles from sticking together.
Sieve Size
Percent Passing1, 2 No. 8
100
No. 16
65 – 100
No. 30
20 – 100
No. 50
0 – 45
No. 200
0 – 5
1. Perform gradation according to AASHTO T27 using a minimum 50 gram sample 2. Ensure that the gradation is performed as specified in NJDOT B-11. Submit to the ME a certification of compliance, as specified in 106.07, for the ground crumb rubber. In addition, ensure that the certificates confirm that the rubber is a crumb rubber, derived from processing whole scrap tires or shredded tire materials; and the tires from which the crumb rubber is produced are taken from automobiles, trucks, or other equipment owned and operated in the United States. Include with the certifications verifications that the processing did not produce, as a waste product, casings, or other round tire material that can hold water when stored or disposed of above ground.
- Asphalt Binder.
1. Organic additives such as a paraffin wax or a low molecular weight esterified wax.
2. Chemical additive that acts as a surfactant or dispersing agent.Do not use controlled asphalt foaming systems or any other steam injection processes or steam introducing additives. WMA is a method of producing asphalt pavement at a mixing and compaction temperatures at least 30 ºF lower than Hot Mix Asphalt (HMA) by using one or more of the types of WMA additives listed above. Submit information on the WMA additive or process with the Paving Plan required in 402.03.02.A. Include in the submission, the name and description of the additive or process, the manufacturer’s recommendations for usage of the additive or process, recommendations for mixing and compaction temperatures, and details on at least one project on which the additive was successfully used in the United States on a crumb rubber modified asphalt mixture. In the details of a project, include tonnage, type of mix, dosage, mixing and compaction temperatures, available test results, and contact information for project. If a WMA additive is pre-blended in the asphalt binder, ensure that the asphalt binder meets the requirements of the specified grade after the addition of the WMA additive. If a WMA additive is added at the HMA plant, ensure that the addition of the additive will not negatively impact the grade of asphalt binder. The ME will evaluate the impacts to performance grade of the asphalt binder based upon certification from manufacturer in conjunction with laboratory data indicating the effects of the additive on the asphalt binder properties. Follow the manufacturer’s recommendations for the dosage of WMA additive needed and approved blending method(s).
Ensure that a technical representative of the WMA additive manufacturer is on-site or available for consultation during the production and placement of the AR-OGFC with the warm mix additive.
Document that the proportions are accurate and that the rubber has been uniformly incorporated into the mixture. Report as directed by the ME. Ensure that the crumb rubber and asphalt-cement are thoroughly mixed before beginning the one-hour reaction period. Rubber floating on the surface or agglomerations of rubber particles is evidence of insufficient mixing. Maintain the temperature of the asphalt-rubber binder immediately after mixing between 325 and 375 °F. Maintain the temperature of the asphalt-rubber binder for at least one hour before using.
Properties. Prepare asphalt-rubber binder using the “wet process.” Physical properties are required to comply with the requirements of ASTM D 6114, Type II, except for the properties specified in Table 902.07.02-2.
| Table 902.07.02-2 Asphalt-Rubber Binder Properties | ||
| Property | Test Procedure | Requirement |
| Resilience: 77 °F; %, minimum | ASTM D 5329 | 25 |
| Rotational Viscosity1 350 °F; cP | NJDOT B-12 | 2000 – 4000 |
|
||
For each load or batch of asphalt-rubber binder, provide the RE with the following:
Submit binder and mix designs including JMF for each mixture performed by an AASHTO accredited lab with at least five successfully completed asphalt-rubber open-graded friction course projects greater than 5,000 tons each. Include a statement naming the source of each component and a report with the results for the criteria specified in Table 902.07.03-1. Include a report detailing the rotational viscosity of the asphalt-rubber binder at 60, 90, 135, 240, and 1440 minutes. Submit lab qualifications and references to the ME for approval prior to beginning work.
Design the mix to meet the criteria in Table 902.07.03-1.
Determine and verify the JMF according to NJDOT B-8. Ensure that the JMF is within the master range specified in Table 902.07.03-1.
Prepare compacted test specimens for submittal to the ME at least 30 days before the initial production date. Prepare these specimens from material mixed according to the final JMF, using 50 gyrations of the Superpave gyratory compactor according to AASHTO T 312.
The ME will test 2 specimens to verify stone-on-stone contact according to NJDOT B-8 and that the final JMF produces a mixture that has a minimum void content as specified in Table 902.07.03-1. The ME will determine percent air voids according to AASHTO T 209 and AASHTO T 331.
The ME will test 2 test specimens for abrasion and impact resistance using a modified L.A. Abrasion Test according to NJDOT B-8. The maximum allowable loss as calculated by this method is 30 percent.
Do not modify, which includes changing the asphalt cement supplier, the JMF unless the ME approves the modification.
General Acceptance Requirements. The RE or ME may reject and require disposal of any batch or shipment that is rendered unfit for its intended use due to contamination, segregation, improper temperature, lumps of cold material, or incomplete coating of the aggregate. For other than improper temperature, visual inspection of the material by the RE or ME is considered sufficient grounds for such rejection.
For AR-OGFC with WMA additive, ensure that the temperature of the mixture at discharge from the plant or surge and storage bins meets the WMA additive manufacturer’s recommendations. Do not allow the mixture temperature to exceed 300 °F at discharge from the plant.
Combine and mix the aggregates and asphalt-rubber binder to ensure that at least 95 percent of the coarse aggregate particles are entirely coated with asphalt-rubber binder as determined according to AASHTO T 195. If the ME determines that there is an on-going problem with coating, the ME may obtain random samples from 5 trucks and will determine the adequacy of the mixing on the average of particle counts made on these 5 test portions. If the requirement for 95 percent coating is not met on each sample, modify plant operations, as necessary, to obtain the required degree of coating.
Quality Control Testing. The HMA producer is required to provide a quality control (QC) technician who is certified by the Society of Asphalt Technologists of New Jersey as an Asphalt Technologist, Level 2. The QC technician may substitute equivalent technician certification by the Mid-Atlantic Region Technician Certification Program (MARTCP). Ensure that the QC technician is present during periods of mix production for the sole purpose of quality control testing and to assist the ME. The ME will not perform the quality control testing or other routine test functions in the absence of, or instead of, the QC technician.
The QC technician is required to perform sampling and testing according to the approved quality control plan, to keep the mix within the limits specified for the mix being produced. The QC technician may use acceptance test results or perform additional testing as necessary to control the mix.
For each acceptance test, perform maximum specific gravity testing according to AASHTO T 209 on a test portion of the sample taken by the ME. Sample and test coarse aggregate, fine aggregate and mineral filler according to the approved quality control plan for the plant.
Acceptance Testing. During production, the ME will take one random acceptance sample from each 700 tons of production to verify composition. The ME will perform sampling according to NJDOT B-2 or ASTM D 3665, and will perform testing for composition according to AASHTO T 308 or NJDOT B-5. Perform testing for air voids according to T 209 and either B-6 or T 331. Perform testing for draindown according toNJDOT B-8.
Conduct air voids and draindown tests as directed by the ME.
If the composition testing results are outside of the production control tolerances specified in Table 902.07.04-1 for an acceptance sample, determine if a plant adjustment is needed and immediately run a quality control sample. If the quality control sample is also outside of the control tolerances in Table 902.07.04-1, immediately take corrective action to bring the mix into compliance. Take additional quality control samples after the corrective action to ensure that the mix is within the production control tolerances. If two consecutive acceptance samples are outside the tolerances specified in Table 902.07.04-1, immediately stop production. Obtain ME approval of a plant correction plan before resuming production. Upon restarting production, do not transport mixture to the Project Limits before the results of a QC sample from the mixture indicate that the mixture meets JMF tolerances. The ME will reject mixture produced at initial restarting that does not meet tolerances.
| Table 902.07.04-1 Production Control Tolerances for AR-OGFC Mixtures | ||
| Sieve Sizes |
|
|
1/2" |
±6.0 |
|
3/8" |
±5.5 |
|
No. 4 |
±5.5 |
|
No. 8 |
±4.5 |
|
No. 200 |
±2.0 |
|
Asphalt-rubber binder, % (AASHTO T 308) |
±0.40 |
|
Asphalt-rubber binder, % (NJDOT B-5) |
±0.15 |
|
Minimum % Air Voids |
1.0% less than design requirement |
|
| 1. Production tolerances may fall outside of the wide band gradation limits in Table 902.07.03-1. | ||
Mix HPTO in a plant that is listed on the QPL and conforms to the requirements for HMA Plants as specified in 1009.01. The composition of the mixture for HPTO is coarse aggregate, fine aggregate, and asphalt binder, and may also include mineral filler. Do not use Reclaimed Asphalt Pavement (RAP), Ground Bituminous Shingle Material, Remediated Petroleum Contaminated Soil Aggregate, or Crushed Recycled Container Glass (CRCG). Use asphalt binder and aggregates that meet the following requirements:
At least 45 days before initial production, submit a job mix formula for the HPTO on forms supplied by the Department. Include a statement naming the source of each component and a report showing the results meet the criteria specified in Tables 902.08.03-1 and 902.08.03-2.
For the job mix formula for the HPTO mixture, establish the percentage of dry weight of aggregate passing each required sieve size and an optimum percentage of asphalt binder based upon the weight of the total mix. Determine the optimum percentage of asphalt binder according to AASHTO R 35 and M 323 with an Ndes of 50 gyrations. Before maximum specific gravity testing or compaction of specimens, condition the mix for 2 hours according to the requirements for conditioning for volumetric mix design in AASHTO R 30, Section 7.1. If the absorption of the combined aggregate is more than 1.5 percent according to AASHTO T 84 and T 85, condition the mix for 4 hours according to AASHTO R 30, Section 7.2 prior to compaction of specimens (AASHTO T 312) and determination of maximum specific gravity (AASHTO T 209). Ensure that the job mix formula is within the master range specified in, Table 902.08.03-1.
Ensure that the job mix formula provides a mixture that meets a minimum tensile strength ratio (TSR) of 85 percent when prepared according to AASTHO T 312 and tested according to AASHTO T 283 with the following exceptions:
For each mix design, submit three gyratory specimens and one loose sample corresponding to the composition of the job mix formula, including the design asphalt content. The ME will use these samples for verification of the properties of the job mix formula. Compact the specimens to the design number of gyrations (Ndes). To be acceptable all three gyratory specimens must comply with the gradation and asphalt content requirements in Table 902.08.03-1 and with the control requirements in Table 902.08.03-2. The ME reserves the right to be present at the time of molding the gyratory specimens.
In addition, submit 6 gyratory specimens and a 5 gallon bucket of loose mix to the ME. Compact the additional gyratory specimens according to AASHTO T 312. Ensure that the 6 gyratory specimens are 77 millimeters high and have an air void content of 5.0 ± 0.5 percent. The ME will use the additional samples for performance testing of the HPTO mix. The ME will test the specimens using an Asphalt Pavement Analyzer according to AASHTO TP 63 at 64 °C, 100 pounds per square inch hose pressure, and 100 pound wheel load. The ME will approve the job mix formula if the average rut depth for the 6 specimens in the asphalt pavement analyzer testing is not more than 4 millimeters in 8,000 loading cycles. If the job mix formula does not meet the APA criteria, redesign the HPTO mix.
If unsatisfactory results for any specified characteristic of the work make it necessary, establish a new job mix formula for approval. In such instances, if corrective action is not taken, the ME may require an appropriate adjustment.
If a change in sources is made or a change in the properties of materials occurs, the ME will require that a new job mix formula be established and approved before production can continue.
Ensure that the temperature of the HPTO at discharge from the plant or surge and storage bins is maintained between 300 and 330 °F.
Combine and mix the aggregates and asphalt binder to ensure that at least 95 percent of the coarse aggregate particles are entirely coated with asphalt binder as determined according to AASHTO T 195. If the ME determines that there is an on-going problem with coating, the ME may obtain random samples from 5 trucks and will determine the adequacy of the mixing on the average of particle counts made on these 5 test portions. If the requirement for 95 percent coating is not met on each sample, modify plant operations, as necessary, to obtain the required degree of coating.
Sampling. The ME will take 5 stratified random samples of HPTO for volumetric acceptance testing from each lot of approximately 3500 tons of a mix. When a lot of HPTO is less than 3500 tons, the ME will take samples at random for each mix at the rate of one sample for each 700 tons. The ME will perform sampling according to AASHTO T 168, NJDOT B-2, or ASTM D 3665.
Use a portion of the samples taken for composition testing, unless composition is determined by hot bin analysis. If using hot bin analysis at a fully automated batch plant, take 5 samples from each lot corresponding to the volumetric acceptance samples, under the supervision of the ME.
Quality Control Testing. The HMA producer is required to provide a quality control (QC) technician who is certified by the Society of Asphalt Technologists of New Jersey as an Asphalt Technologist, Level 2. The QC technician may substitute equivalent technician certification by the Mid-Atlantic Region Technician Certification Program (MARTCP). Ensure that the QC technician is present during periods of mix production for the sole purpose of quality control testing and to assist the ME. The ME will not perform the quality control testing or other routine test functions in the absence of, or instead of, the QC technician.
The QC technician is required to perform sampling and testing according to the approved quality control plan, to keep the mix within the limits specified for the HPTO mix being produced. The QC technician may use acceptance test results or perform additional testing as necessary to control the mix.
To determine the composition, perform ignition oven testing according to AASHTO T 308. For fully automated plants, the QC technician may determine composition using hot bin analysis according to NJDOT B-5. Use only one method for determining composition within a lot.
For each acceptance test, perform maximum specific gravity testing according to AASHTO T 209 on a test portion of the sample taken by the ME. Sample and test coarse aggregate, fine aggregate, mineral filler, and RAP according to the approved quality control plan for the plant.
Acceptance Testing and Requirements. The ME will determine volumetric properties at Ndes for acceptance from samples taken, compacted, and tested at the HMA plant. The ME will compact HPTO to 50 gyrations, using equipment according to AASHTO T 312. The ME will determine bulk specific gravity of the compacted sample according to AASHTO T 166. The ME will use the most current QC maximum specific gravity test result in calculating the volumetric properties of the HPTO.
The ME will determine the dust-to-binder ratio from the composition results as tested by the QC technician.
Ensure that the HMA mixture conforms to the requirements specified in Table 902.08.03-2, and to the gradation requirements in Table 902.08.03-1. If 2 samples in a lot fail to conform to the gradation or volumetric requirements, immediately initiate corrective action.
The ME will test a minimum of 1 sample per lot for moisture, basing moisture determinations on the weight loss of an approximately 1600-gram sample of mixture heated for 1 hour in an oven at 280 ± 5 °F. Ensure that the moisture content of the mixture at discharge from the plant does not exceed 1.0 percent.
Performance Testing. Provide 6 gyratory specimens and a 5 gallon bucket of loose mix to the ME. Compact the additional gyratory specimens according to AASHTO T 312. Ensure that the 6 gyratory specimens are 77 millimeters high and have an air void content of 5.0 ± 0.5 percent. The first sample is required to be taken in the first lot of production. Thereafter, every third lot is required to be sampled. The ME will use the samples for performance testing of the HPTO mix. The ME will test the specimens using an Asphalt Pavement Analyzer according to AASHTO TP 63 at 64 °C, 100 pounds per square inch hose pressure, and 100 pounds wheel load. If the HPTO mix exceeds the APA criteria of 4 mm in 8000 loading cycles, the ME may stop production until corrective action is taken. If the HPTO mix exceeds the APA criteria of 12 mm in 8000 loading cycles, the RE may require removal and replacement of the lot of HPTO.
Sieve Size
Percent Passing by Mass
3/8”
100
#4
65-85
#8
33-55
#16
20-35
#30
15-30
#50
10-20
#100
5-15
#200
5.0-8.0
Minimum Percent Asphalt by Mass of Total Mix
7
Use cement, listed on the QPL, that is either portland cement or blended hydraulic cement and conforms to the following:
| Portland Cement, Type I, II, and Type III | ASTM C 150 | |
| Blended Hydraulic Cement, Type IS and IP | ASTM C 595 |
The Contractor may only use Type III portland cement for class V concrete, prestressed Items, or precast Items.
For blended hydraulic cement, the Contractor may use portland cement pre-blended with a maximum of 25 percent fly ash, by weight, or a maximum of 5 percent silica fume by weight, or with a maximum of 50 percent slag by weight. If more than 30 percent slag is used, ensure that a scaling test according to ASTM C 672 is completed on the mix design and the concrete has a visual rating less than 3 after 50 cycles.
When blended hydraulic cement is used, do not add additional mineral admixtures at the concrete plant unless approved by the ME.
Do not mix different brands of cement, the same brand of cement from different mills, or different types of cement.
Provide suitable means for storing and protecting the cement against dampness. The ME will reject cement that has become partially set or that contains lumps of caked cement. Ensure that the temperature of the cement at the time of delivery to the mixer does not exceed 160 °F.
Use air-entraining admixtures for concrete that are listed on the QPL and conform to AASHTO M 154, except that the tests for bleeding and volume change are not required.
The ME will test for uniformity through the use of infrared spectrophotometry, pH values, specific gravity, and solids content.
Keep all bulk storage tanks inside a heated area with an ambient temperature of not less than 32 °F. Do not reuse air-entraining admixture that has been allowed to freeze until it has been agitated and retested.
Use chemical admixtures for concrete that are listed on the QPL and conform to AASHTO M 194.
Use chemical admixtures of the following types:
Do not use chemical admixtures that contain calcium chlorides or any other chlorides that may initiate or promote corrosion of the reinforcement steel.
Locate all bulk storage tanks for chemical admixtures inside a heated area with an ambient temperature of not less than 32 °F. Do not use chemical admixtures that have been allowed to freeze until they have been agitated and retested.
The ME may require certification from the manufacturer stating that the material is identical to that originally approved and has in no way been changed or altered. The ME will test for uniformity through the use of infrared spectrophotometry, pH values, specific gravity, and solids content.
If needed for self-consolidating concrete, use a viscosity modifying admixture that is listed on the QPL and that, when evaluated according to the test methods and mix design proportions in AASHTO M 194, conforms to the following physical requirements:
When required, use a calcium nitrite based corrosion inhibitor admixture to reduce the potential of corrosion of embedded steel. Use the following guidelines for calcium nitrite:
Compose concrete of cement, coarse aggregate, fine aggregate, admixtures, and water. Concrete may include fly ash, slag or silica fume.
| Provide materials as specified: | ||
| Aggregates | 901.06 | |
| Cement | 903.01 | |
| Admixtures: | ||
| Air-Entraining | 903.02.01 | |
| Chemical | 903.02.02 | |
| Mineral | 903.02.03 | |
| Corrosion Inhibitor | 903.02.05 | |
| Water | 919.08 | |
Use chemical admixtures according to the admixture manufacturer’s recommendation for the mix design and anticipated field conditions, including the admixture dosage rate and the location and method for introducing it into the mixture.
If fly ash is added to control alkali-silica reactivity, use at least 15 percent fly ash by weight of the total cementitious material. If AASHTO T 303 testing results in an expansion greater than 0.40 percent, use at least 20 percent fly ash. If slag is used to control alkali-silica reactivity, use at least 25 percent slag by weight of the total cementitious material. If a low alkali cement is used to control alkali-silica reactivity, use cement with equivalent alkali of less than 0.60 percent.
Use the combined weight of fly ash, slag, silica fume, and cement content to determine compliance with the minimum cement content and water-cement ratio requirements specified in Table 903.03.06-3. Include free water from the aggregates and the water in the admixtures and additives along with the mixing water when calculating the water-cement ratio.
Design at least 1 mix to equal or exceed the required verification strengths specified in Table 903.03.06-3 for each class of concrete included on the Project. A single mix design may satisfy the requirements for more than 1 class of concrete. Compute and set up the designs according to ACI Standard 211.1 or 211.2, as applicable.
At least 45 days before the start of concrete placement, submit each mix design on concrete mix design forms provided by the ME. Identify the sources of materials and test data on the forms.
The ME will be present at the time of verification batching to confirm that the proportions and ingredients batched are according to the proposed mix designs. If directed by the ME, mix at least 3 cubic yards of concrete in a central mix plant or transit truck for verification. The ME will direct that the verification batch be mixed in the top half of the allowable slump and air content ranges. Test for and report the slump and air content of the trial batch. The ME will reject the verification batch if the slump, air content, or yield is not acceptable. Prepare at least six 4 × 8-inch test cylinders from each acceptable batch and cure according to AASHTO T 23 or AASHTO R 39. Between 2 and 5 days after molding, deliver the cylinders to the ME for testing. The ME will test 3 cylinders at 7 days and 3 cylinders at 28 days to determine the 7-day and 28-day compressive strengths, respectively.
At the ME’s option, verification may be done on an annual basis for a concrete plant rather than on a project-to-project basis, provided the properties and proportions of the materials do not change. If the Contractor submits written verification that the same source and character of materials are to be used, the ME may waive the requirement for the design and verification of previously approved mixes.
Provide concrete conforming to the approved mix design. If using a previously approved mix design, notify the ME at least 1 day before making the change. Do not change the source, type, or proportions of materials until approved and the requirements for design and verification have been satisfied.
| Table 903.03.05-1 Sampling and Testing Methods | |
| Designation | Test Method |
| AASHTO T 221 | Compressive Strength of Cylindrical Concrete Specimens (Including the Annex providing for use of neoprene caps) |
| AASHTO T 232 | Making and Curing Concrete Test Specimens in the Field |
| AASHTO T 243 | Obtaining and Testing Drilled Cores and Sawed Beams of Concrete |
| AASHTO T 97 | Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading) |
| AASHTO T 119 | Slump of Hydraulic Cement Concrete |
| AASHTO T 121 | Weight Per Cubic Foot, Yield and Air Content (Gravimetric) of Concrete |
| AASHTO T 1414 | Sampling Fresh Mixed Concrete |
| AASHTO T 152 | Air Content of Freshly Mixed Concrete by the Pressure Method |
| AASHTO T 196 | Air Content of Freshly Mixed Concrete by the Volumetric Method |
| AASHTO T303 | Accelerated Detection of Potentially Deleterious Expansion of Mortar Bars Due to Alkali-Silica Reaction. |
| AASHTO R 39 | Making and Curing Concrete Test Specimens in the Laboratory |
| ASTM C 567 | Unit Weight of Structural Lightweight Concrete |
| ASTM C 3115 | Sampling and Testing Fly Ash or Natural Pozzolans for Use as a Mineral Admixture in Portland Cement Concrete. |
| NJDOT C-1 | Determination of Yield of Concrete Produced by Mobile Truck Mixers |
| 1 | Use 4 × 8-inch (diameter × height) compression test cylinders, except use 6 × 12-inch (diameter × height) test cylinders for concrete mixes containing coarse aggregate sizes exceeding a nominal maximum size of 1 inch. |
| 2 | Cure compression test cylinders for strength acceptance according to the Standard Cure Method in AASHTO T 23. For determining early strength for form removal, early loading of members, or opening to traffic, cure compression test cylinders according to the Field Cure Method in AASHTO T 23. |
| 3 | Obtain and prepare cores for compressive strength testing according to AASHTO T 24, except for the provisions for moisture conditioning. For moisture conditioning, soak cores in a lime bath at 73.4 ± 3 °F for at least 40 hours immediately prior to testing. After making any necessary corrections to the core results for ratio, the ME will divide each core result by 0.85 before reporting the final compressive strength. |
| 4 | Sample according to AASHTO T 141, except do not take a composite sample to represent a truck. Take the sample after approximately 1 cubic yard of concrete has been discharged from the truck to be sampled. |
| 5 | The Department may modify the sampling rate for individual and composite samples. |
| Where: | |
| ∑ = Summation | |
| Xi = Individual test result (average strength of a test cylinder pair) | |
| N = Number of test results for the lot |
| Q = | ALS − CDS |
|
|
|
||
|
S |
| Where: |
| CDS = Class design strength in pounds per square inch from Table 903.03.06-3 for the specified class of concrete. |
| Quality | Percent Pay Adjustment | |
| Equation 1 | PD < 50 | PPA = 3.0 − 0.3 PD |
| Equation 2 | PD ≥ 50 | PPA = 26.0 − 0.76 PD |
| Table 903.03.05-2 Estimated Percentage of Concrete in Items | |
| Item | Estimated Percentage of Concrete |
| INLET, TYPE ___ | 30 |
| INLET, TYPE ___, USING EXISTING CASTING | 30 |
| MANHOLE, ___' DIAMETER | 30 |
| MANHOLE, USING EXISTING CASTING | 30 |
| MANHOLE, SANITARY SEWER | 30 |
| MANHOLE, SANITARY SEWER, USING EXISTING CASTING | 30 |
| GRANITE CURB | 25 |
| RESET GRANITE CURB | 25 |
| BEAM GUIDE RAIL TERMINALS AND ANCHORAGES | 25 |
| CHAIN-LINK FENCE, ___' HIGH | 25 |
| CHAIN-LINK FENCE, ALUMINUM-COATED STEEL, ___' HIGH | 25 |
| CHAIN-LINK FENCE, PVC-COATED STEEL, ___' HIGH | 25 |
| GATE, CHAIN-LINK FENCE, ___' WIDE | 25 |
| GATE, CHAIN-LINK FENCE, ALUMINUM-COATED STEEL, ___' WIDE | 25 |
| GATE, CHAIN-LINK FENCE, PVC-COATED STEEL, ___' WIDE | 25 |
| TEMPORARY CHAIN-LINK FENCE, ___' HIGH | 25 |
| GUIDE SIGN, TYPE GA, BREAKAWAY SUPPORTS | 20 |
| GUIDE SIGN, TYPE GA, NON-BREAKAWAY SUPPORTS | 20 |
| Table 903.03.06-1 Requirements for Roadway Concrete Items | ||||
| Concrete Class |
Slump1 (inch) |
Percent Air Entrainment for Coarse Aggregate1 | ||
| No. 57 & No. 67 | No. 8 | |||
| Cast-in-Place Items | ||||
| Surface Course, Base Course | B | 2 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Inlets, Manholes, Headwalls, Sidewalks, Driveways, Islands | B | 3 ± 1 | 6.0 ± 1.5 | 7.0±1.5 |
| Slope Gutters, Vertical Curb, Sloping Curb, Barrier Curb, Concrete Islands | B | 4 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Foundations for: Inlets, Manholes and Electrical Items |
B | 3 ± 1 | 7.5 max | 8.5 max |
| Signs | B | 3 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Footings for: Fence Post, Beam Guide Rail Terminals, and Anchorages |
B | 3 ± 1 | 7.5 max | 8.5 max |
| Culverts | A | 3 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Monuments | A | 3 ± 1 | 7.5 max | 8.5 max |
| Slope Protection | B | 2 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Pipe Bedding, Thrust Blocks, Pipe Plugs, Encasements, Saddles | B | 3 ± 1 | 7.5 max | 8.5 max |
| Precast Items | ||||
| Culverts | P | 3 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Inlets, Manholes, Junction Boxes, Headwalls, Reinforced Concrete End Sections | B | 3 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Concrete Barrier Curb | B | 3 ± 1 | 7.0 ± 2.0 | 8.0 ± 2.0 |
| Slip-Form Items | ||||
| Surface Course, Base Course | B | 1-1/2 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| 1 | When using a Type F or G admixture, change the requirements for Slump and Air Content for the given concrete item as follows: | |
| 1.1 | Slump: 6 ± 2 inches | |
| 1.2 | Air Content: Increase both the target value and tolerance percentages by 0.5. | |
| Table 903.03.06-2 Requirements for Structural Concrete Items | ||||
| Concrete Class |
Slump1 (inches) |
Percent Air Entrainment for Coarse Aggregate1 | ||
| No. 57 & No. 67 | No. 8 | |||
| Cast-in-Place Items | ||||
| Bridge Approach | A | 3 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Footings, Piles | B | 3 ± 1 | 7.5 max | 8.5 max |
| Abutments, Wing Walls, Pier Shafts, Retaining Walls | B | 3 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Drilled Shafts2 | A | 7 ± 12 | – | 7.5 ± 1.5 |
| Concrete Barrier Curb, Bridge | B | 4 ± 1 | 7.0 ± 2.0 | 8.0 ± 2.0 |
| Pier Columns and Pier Caps, Arch Spans, Culverts | A | 3 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Decks, Sidewalks, Curbs, Parapets, Concrete Patch | A | 3 ± 1 | 6.0 ± 1.5 |
7.0 ± 1.5 |
| Seal (Tremie) Concrete | S | 7 ± 2 | 7.5 max | 8.5 max |
| Prestressed Items | ||||
| Beams | P, P-1,& P-2 | 2 ± 1 | 5.0 ± 1.5 | 5.0 ± 1.5 |
| Piles | P | 2 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Precast Items | ||||
| Piles | B | 3 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Culverts, Parapet | P | 3 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Modular Bin Units, MSE Wall Panels, Leveling Pads | P | 2 ± 1 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| Slip-Form Items | ||||
| Parapet | A | 1 ± 1/2 | 6.0 ± 1.5 | 7.0 ± 1.5 |
| 1 | When using a Type F or G admixture, change the requirements for Slump and Air Content for the given concrete item as follows: | |
| 1.1 | Slump: 6 ± 2 inches | |
| 1.2 | Air Content: increase both the target value and tolerance percentages by 0.5. | |
| 2 | For drilled shaft concrete, use Type F or G admixture to achieve the required slump. If concrete in the drilled shaft is placed under a drilling fluid, the required slump is changed to 8±1. | |
| Table 903.03.06-3 Mix Design Requirements | ||||||
| Class A | Class B | Class S | Class P | Class P-1 | Class P-2 | |
| Class Design Strength2 (28 days, psi) |
4600 | 3700 | 2000 | 5500 | 6000 | 6500 |
| Verification Strength2 (28 days, psi) |
5400 | 4500 | – | 6000 | 6500 | 7000 |
| Maximum Water-Cement Ratio3 (lb/lb) | 0.443 | 0.488 | 0.577 | 0.400 | 0.400 | 0.400 |
| Minimum Cement Content (lb/cy) | 611 | 564 | 658 | 1 | 1 | 1 |
| 1 | According to PCI MNL-116. |
| 2 | Record all concrete test results to the nearest 10 psi. |
| 3 | When a Type F or G water-reducing, high range admixture is used as specified in Table 903.03.06-1 and Table 903.03.06-2, reduce the maximum water-cement ratio by 0.043 for all classes of concrete except for Classes P, P-1 and P-2. |
| Table 903.03.06-4 Lot Sizes, Sampling Rates, and Retest Limits | |||||||
| Class A | Class B | Class S | Class P | Class P-1 | Class P-2 | ||
Lot Size1, 2 (maximum) |
Day’s Production | Day’s Production of a Single Steam Bed | |||||
| Pay-Adjustment Items | |||||||
| Initial Sampling Rate3, 4 | 5/Lot | 5/Lot | – | 5/Lot | 5/Lot | 5/Lot | |
| Retest Sampling Rate5 (minimum) | 5/Lot | 5/Lot | – | 5/ Unit or Load Test | |||
| Non-Pay-Adjustment Items | |||||||
| Initial Sampling Rate 3, 4 | 3/Lot | 2/Lot | 1/Lot | 5/Lot | 5/Lot | 5/Lot | |
| Retest Limit (psi) | 4400 | 3600 | 2000 | 5400 | 5900 | 6400 | |
| Retest Sampling Rate5 | 5/Lot | 5/Lot | 5/Lot | 5/Lot | 5/Lot | 5/Lot | |
| 1 | The lot sizes are maximums. The ME may subdivide a lot into 2 or more smaller lots. When a subdivision is made, the specified sampling rate applies to each of the smaller lots. |
| 2 | The ME will not include more than 1 class of concrete in a lot. |
| 3 | An initial sample is defined as 2 cylinders taken from a concrete sample. |
| 4 | The ME will sample at the specified sampling rates except that no more than 1 test per truckload or batch of concrete will be required (except for air and slump tests when retempering). The ME may accept nonstructural concrete lots consisting of 20 cubic yards or less without strength tests. |
| 5 | A retest sample is defined as 1 core. |
Use Class V or E concrete for concrete pavement repair and replacement. Ensure that the composition of Class V and E concrete complies with 903.03.01 except that Class V concrete is required to use an accelerating admixture and a high range water-reducing admixture.
Ensure that the composition of Class V or E concrete conform to the composition requirements specified in 903.03.01, except use an accelerating admixture and a high range water-reducing admixture for Class V concrete.
Design and verify Class V and E concrete as specified in 903.03.02, except for the following:
| Table 903.04.02-1 Mix Design Requirements | ||
| Class V | Class E | |
| Class Design Strength | ||
| 28-day Compressive Strength, psi | 3700 | 3700 |
| 6.5-Hour Flexural Strength, psi | 350 | – |
| 72-Hour Compressive Strength, psi | – | 3000 |
| Verification Strength | ||
| 28-day Compressive Strength, psi | 4500 | 4500 |
| 6.5-Hour Flexural Strength, psi | 390 | – |
| 72-Hour Compressive Strength, psi | – | 3700 |
| Maximum Water-Cement Ratio (lb/lb) | .40 | .40 |
| Minimum Cement Content (lb/cy) | 611 | 611 |
Mix Class V and E concrete as specified in 903.03.03 or 903.03.04.
Produce HPC conforming to the composition requirements specified in 903.03.01, except for the following:
Design an HPC mix that conforms to the requirements in Table 903.05.02-1. Submit a report documenting these results to the ME. Obtain the results of these standard tests from an AASHTO accredited testing agency that is accredited for the test being performed. Design mixes according to the HPC-1 criteria for use in bridge decks, parapets, and bridge sidewalks. Design mixes meeting the HPC-2 criteria for use in pier column protection.
| Table 903.05.02-1 Design and Verification Requirements for HPC | |||
| Performance Characteristic | Test Method | Requirements | |
| HPC-1 | HPC-2 | ||
| Scaling Resistance1 @ 50 cycles (visual rating of the surface, maximum) |
ASTM C 672 | 3 | – |
| Abrasion Resistance (average depth of wear in inches, maximum) |
ASTM C 944 | – | 0.04 |
| Freeze-Thaw Durability (relative dynamic modulus of elasticity after 300 cycles, minimum) |
ASTM C 666 Proc. A |
80% | 80% |
| Chloride Permeability2 @ 56-days (coulombs, maximum) |
AASHTO T 277 | 1000 | 1000 |
| Compressive Strength3 @ 56-days (pounds per square inch, minimum) |
AASHTO T 22 | 5400 | 5400 |
| Water-Cement Ratio (maximum) | – | 0.40 | 0.40 |
| 1 | For the scaling resistance testing, moist cure specimens for 14 days and then air cure for 14 days. |
| 2 | If the chloride permeability requirement has been achieved in 28 days, consider the chloride permeability acceptable. If the required chloride permeability is not achieved in 28 days, test the HPC sample at 56 days. |
| 3 | If the compressive strength requirement has been achieved in 28 days, consider the strength acceptable. If the required compressive strength is not achieved in 28 days, test the HPC samples at 56 days. |
At least 90 days before the planned start of the concrete placement, submit the mix design to the ME for approval and verification as specified in 903.03.02. Include the results of the required performance testing in the submission.
In addition to verifying the compressive strength of the HPC mix, the ME will verify the chloride permeability testing according to AASHTO T 277. Submit 4 additional cylindrical samples, having a 4-inch diameter and a length of at least 8 inches, to the ME for this verification testing. The ME will average the values of tests on 2 specimens for each mix design.
Mix HPC concrete as specified in 903.03.03. During production, do not change the components of the mix in any way from the approved mix design. If the components must be changed, redesign and re-verify the mix.
With the exception that the ME may perform compression testing at 56 days, the ME will enforce the requirements specified in 903.03.05 for control and acceptance testing of non-pay adjustment Class A concrete in the fabrication of the HPC elements.
Produce HPC that conforms to the acceptance testing criteria in Table 903.05.04-1.
| Table 903.05.04-1 Acceptance Requirements for HPC | ||
| Performance Characteristic | Test Method | Requirement |
| Percent Air Entrainment1 | AASHTO T 152 | 6.0 ± 1.5 (No. 57/67 Aggregate) 7.0 ± 1.5 (No. 8 Aggregate) |
| Slump (inches)1, 2 | AASHTO T 119 | 3 ± 1 |
| Chloride Permeability @ 56-days3, 4 (coulombs, maximum) |
AASHTO T 277 | 2000 |
| Compressive Strength @ 56-days5 (pounds per square inch, minimum) |
AASHTO T 22 | 4400 |
| 1 | If using a Type F or G admixture, change the Slump and Air Content values for the HPC as follows: | |
| 1.1 | Slump: 6 ± 2 inches | |
| 1.2 | Air Content: increase both the target value and tolerance percentages by 0.5 | |
| 2 | For slip-formed parapet, design and produce a mix with a slump of 1 ± 1/2 inch. | |
| 3 | The ME will not test for the chloride permeability requirements for HPC used for Items other than bridge decks. | |
| 4 | For chloride permeability testing, the ME will mold 4 additional cylinders, taking 2 cylinders each from 2 randomly selected delivery trucks for testing at 56-days. | |
| 5 | For compressive strength testing, the initial rate for the HPC is 6 per lot. The retest limit is 4400 pounds per square inch. | |
The ME will test 2 specimens for chloride permeability and will average the results of the 2 specimens to determine the test result. The ME will perform 2 tests on each lot from samples taken from 2 randomly selected delivery trucks. The lot is eligible for 100 percent payment provided that the test results are equal to or below 2000 coulombs.
If, upon testing at 56 days, 1 or more individual test results exceed 2000 coulombs, the RE may:
| Table 903.06.01-1 Requirements for SCC for Drilled Shafts | ||
| Property | Test Method | Requirement |
| Air Content | ||
| Coarse Aggregate No. 57 | AASHTO T 152 | 6.5 ± 2.0 percent |
| Coarse Aggregate No. 67 | 6.5 ± 2.0 percent | |
| Coarse Aggregate No. 8 | 7.5 ± 2.0 percent | |
| Slump Flow | NJDOT C-4 | 21 ± 3 inches |
| Visual Stability Index | ||
| Plastic Concrete | NJDOT C-4 | 1 maximum |
| Hardened Concrete | NJDOT C-5 | 1 maximum |
| Table 903.06.02-1 Requirements for SCC for Precast Concrete | ||
| Property | Test Method | Requirement |
| Slump Flow | NJDOT C-4 | 24 to 28 inches |
| Visual Stability Index | ||
| Plastic Concrete | NJDOT C-4 | 1 maximum |
| Hardened Concrete | NJDOT C-5 | 1 maximum |
Use quick-setting patch material that is listed on the QPL and is ready for mixing according to the manufacturer’s recommendations. Follow the manufacturer’s recommendations regarding the required water demand for the patching material. Use patching material that is concrete gray in color and contains no calcium chloride or other ingredients that cause corrosion to steel reinforcement. If adding coarse aggregate to patching material, use broken stone conforming to 901.03.01. Ensure that the material is quick-setting for use in concrete patching where fast setting, rapid strength gain, non-shrink, and high bond strength characteristics are needed. The ME will add products to the QPL only after testing and evaluation in the field, after service for 1 year.
The classifications for quick-setting patch materials are as follows:
If liquid activator, other additives, adhesive, or bonding agents are integral to the performance of the patch material, the manufacturer shall provide the material so that 1 package of additive, activator, adhesive or bonding agent is required for 1 package of patch material. Mix patch material as specified in 903.03.04.
Use quick setting patch material that meets the requirements in Table 903.07-1 when tested according to NJDOT C-2. Mix quick-setting patch according to the manufacturer’s recommendations.
| Table 903.07-1 Requirements for Quick Setting Patch Material | ||
| Type 1, 1A, 1B | Type 2 | |
| Bond Strength | ||
| 7-day (minimum) | 1000 psi | 1000 psi |
| 28-day (minimum) | 2000 psi | 2000 psi |
| Expansion/ Shrinkage | ||
| Cured in Water (maximum) | +0.20% | +0.20% |
| Cured in Air (maximum) | −0.20% | −0.20% |
| Difference (maximum) | 0.30% | 0.30% |
| Durability | ||
| Retained strength at 50 cycles (minimum) | 90% | 90% |
| Visual condition rating at 50 cycles (maximum) | 3 | 3 |
| Permeability (maximum chloride content at 2 inches) | 2.5 lbs/yd3 | 2.5 lbs/yd3 |
| Compressive Strength | ||
| 3-hour (minimum) | 2000 psi | – |
| 1-day (minimum) | 3000 psi | 1000 psi |
| 7-day (minimum) | 4000 psi | 2000 psi |
| 28-day (minimum) | 4500 psi | 3000 psi |
| Time of Set in minutes (minimum) | 15 | 15 |
To produce mortar, mix 1 part cement to 2 parts fine aggregate. Add water to form the proper consistency. Do not temper or use mortar after it has begun to set.
| Provide materials as specified: | ||
| Fine Aggregate | 901.06.02 | |
| Cement | 903.01 | |
| Water | 919.08 | |
| Provide materials as specified: | ||
| Cement, Type I, II, III | 903.01 | |
| Chemical Admixtures | 903.02.02 | |
| Fly Ash | 903.02.03.A | |
| Water | 919.08 | |
| Table 903.08.03-1 Requirements for Pozzolan Grout | ||
| Property | Test Method | Requirements |
| Compressive Strength, 7-Day (psi) | AASHTO T 106 | 600 minimum |
| Flow Cone Time (s) | ASTM C 939 | 9 - 16 |
| Table 903.08.03-2 Requirements for High-Density Polyurethane Grout |
||
| Property | Test Method | Requirements |
| Density (pcf) | ASTM D 1622 | 5.65 to 5.90 |
| Compressive Strength (psi)1 | ASTM D 1621 | 65 to 95 |
| Tensile Core (psi) | ASTM D 1623 | 70 to 100 |
| Shear Strength (psi) | ASTM C 273 | 40 to 85 |
| Closed Cell Content % | ASTM D 2858 | 85 to 95 |
| Percent Volume Change | ||
| Humid - 28 Days (158 °F, 95% Humidity) | ASTM D 2126 | +5.0 to +11.0 |
| Freeze - 5 Days (−20°F, Dry) | −0.1 to −0.9 | |
| 1 | Ensure high-density polyurethane grout reaches 90 percent of the full compressive strength within 15 minutes of injection. |
| Provide materials as specified: | ||
| Fine Aggregate | 901.06.02 | |
| Cement | 903.01 | |
| Chemical Admixtures | 903.02.02 | |
| Water | 919.08 | |
Use CLSM that consists of a mixture of cement, water, fine aggregate, and admixtures. Proportion the CLSM mixture to provide a backfill material that is self-compacting and capable of being excavated with hand tools at a later date. Proportion the CLSM to produce a 28-day compressive strength of 50 to 150 pounds per square inch. If fast-setting CLSM is required, use an accelerating admixture to produce a fast setting flowable mixture. Ensure that the CLSM for backfilling of conduit and piping has a permeability of 1.7 × 10−3 ± 0.2 × 10−3 centimeters per second when tested according to ASTM D 5084.
At least 45 days before the start of any CLSM placement, prepare trial batches of CLSM of the same materials and proportions proposed for use in the Contract. Submit each mix design on concrete mix design forms provided by the Department, naming the sources of materials and test data.
The ME will be present at the time of verification batching to confirm that the proportions and materials batched conform to the proposed mix designs. Prepare at least six 6 × 12-inch compression test cylinders for each batch to be tested according to ASTM D 5971 for 28-day strengths except for fast setting mixes. Test fast-setting CLSM at the specified cure time. If fly ash is used in the CLSM, the ME will take an additional set of cylinders to ensure that the strength of the CLSM does not exceed 150 pounds per square inch in 90 days.
For acceptance testing, the ME will take 1 sample per day but may waive the testing if less than 20 cubic yards is placed in a day. If strength does not comply, the ME may require a new mix design for the CSLM.
Use burlap cloth made from jute or kenaf conforming to AASHTO M 182, Class 4. The ME may sample 1 square yard of burlap cloth from each source for testing. If requested by the RE, submit a certification of compliance as specified in 106.07.
Use liquid membrane-forming compounds conforming to AASHTO M 148, Type 1-D, clear or translucent with fugitive dye. The ME may sample 1 quart of liquid membrane-forming compound from each lot for testing. If requested by the RE, submit a certification of compliance as specified in 106.07.
Use white polyethylene sheeting conforming to AASHTO M 171 for white opaque polyethylene film. The ME may sample a 1-foot strip (cut across full width) from each source for testing. If requested by the RE, submit a certification of compliance as specified in 106.07.
| Provide materials as specified: | ||
| Concrete | 903.03 | |
| Self-Consolidating Concrete (SCC) | 903.06.02 | |
| Mortar | 903.08.01 | |
| Curing Materials | 903.10 | |
| Reinforcement Steel | 905.01 | |
Welded steel wire fabric used for reinforcement need not be galvanized.
Fabricate precast concrete at a plant as specified in 1011.01.
Cure according to the PCI MNL-116, except for steam curing. Do not strip forms until the piece has attained a stripping strength of 2000 pounds per square inch.
If steam curing, delay the application of steam within the enclosure for 4 hours or until the concrete has attained an initial set as determined according to ASTM C 403. Maintain an ambient temperature between 50 °F and 90 °F during the delay. Ensure that the maximum rate of temperature increase in the enclosure is 40 °F per hour. Monitor the temperature in the enclosure using recording thermometers placed at a minimum of 2 locations. Ensure that the enclosure temperature is maintained between 90 °F and 150 °F until 2 concrete test cylinders, field cured according to AASHTO T 23, have attained the stripping strength.
Ensure that items remain in forms for the duration of the curing operation. Remove forms when concrete has attained the stripping strength. If handling devices are used, remove and fill the holes with concrete or mortar. Provide a Class 1 finish as specified in 504.03.02.H.1. Complete surface finishing operations before placing the piece in storage.
Store, stack, and transport the pieces using methods that do not cause the development of cracks or other damage. Do not ship pieces until the class design strength as specified in Table 903.03.06-3 has been attained.
Notify the ME before start of production.
For quality control, keep applicable records according to PCI Division 1, Quality Control, or NPCA requirements, and supply copies of these records to the ME as requested. Ensure that the quality control technician performing all tests is certified as an ACI Field Testing Technician, Grade 1.
Submit certification of compliance as specified in 106.07.
If the concrete piece is spalled, honeycombed, chipped, or otherwise defective, the ME or RE will reject the piece.
| Provide materials as specified: | ||
| Concrete | 903.03 | |
| Self-Consolidating Concrete (SCC) | 903.06.02 | |
| Mortar | 903.08.01 | |
| Curing Materials | 903.10 | |
| Reinforcement Steel | 905.01 | |
Welded steel wire fabric used for reinforcement need not be galvanized.
Use a system listed on the QPL to fabricate prefabricated modular walls or mechanically stabilized earth walls. Fabricate precast concrete at a plant as specified in 1011.01.
| Table 904.02.02-1 Dimensional Tolerances | |
| For MSE Walls | |
| All Panel Dimensions | ±1/4 inch |
| Deviation from Vertical | 1/8 inch per 5 feet |
| For Modular Walls | |
| Length and Height of Face | ±3/16 inch |
| Deviation from Square for Units < 10 feet wide1 | 5/16 inch maximum |
| Deviation from Square for Units ≥ 10 feet wide1 | 3/4 inch maximum |
| 1 | Measure deviation from square on the diagonal. |
Cure as specified in 904.01.03, except that the required stripping strength is 3000 pounds per square inch.
Remove forms and finish concrete as specified in 904.01.04.
Handle and ship as specified in 904.01.05.
Notify the ME in writing at least 21 days before start of production.
For quality control, keep applicable records according to PCI Division 1, Quality Control, or NPCA requirements, and supply copies of these records to the ME as requested. Ensure that the quality control technician performing all tests is certified as an ACI Field Testing Technician, Grade 1.
During production, the ME will inspect the quality of materials and the process of manufacture. The ME will accept the concrete as specified in 903.03.05 and will inspect the finished pieces before shipping for dimensional tolerances and damage. The ME will reject units for any of the following:
| Provide materials as specified: | ||
| Concrete | 903.03 | |
| Self-Consolidating Concrete (SCC) | 903.06.02 | |
| Mortar | 903.08.01 | |
| Curing Materials | 903.10 | |
| Reinforcement Steel | 905.01 | |
| Bolts and Bolting Materials | 908.01 | |
| Epoxy Waterproofing | 912.02.02 | |
Fabricate precast concrete at a plant as specified in 1011.01. Provide an office for the ME as specified in 1011.03.
| Table 904.03.02-1 Fabrication Requirements for Culverts | |
| Wall Thickness | 8 inches minimum |
| Top and Bottom Slab Thickness | 10 inches minimum |
| Concrete Cover for Walls and Bottom Slab | 1-1/2 inches minimum |
| Concrete Cover for Top Slab | 2 inches minimum |
| Table 904.03.02-2 Fabrication Requirements for Precast Concrete Arch Structures |
|
| Concrete Cover Outside Face | 2 inches minimum |
| Concrete Cover Inside Face | 1.5 inches minimum |
| Internal Dimension Tolerance | ±1% or ±2 inches, whichever is less |
| Wall Thickness Tolerance1 | −5% or −1/2 inch, whichever is more |
| Difference in Side Lengths2 | ±3/4 inch |
| 1 | The ME will not reject structures having thicknesses that exceed that shown in the approved working drawing. |
| 2 | Requirement waived for skewed ends for laying curves. |
Cure as specified in 904.01.03, except that the required stripping strength is 4000 pounds per square inch.
Ensure that units remain in their steel forms for the duration of the curing operation.
Upon removal of the forms, provide a Class 1 finish as specified in 504.03.02.H.1 to the entire precast concrete culvert unit, including exterior, interior, and lap surfaces. For culverts, after approval of the Class 1 finish, apply 1 coat of an epoxy waterproofing on the exterior of the roof slab. Apply this coating in the precaster’s plant not earlier than 72 hours after fabrication, and after the concrete compressive strength has reached 4000 pounds per square inch. Ensure that the concrete surfaces of the precast units are dry during application of the epoxy waterproofing. Apply the epoxy waterproofing according to the product manufacturer’s recommendations.
Handle and ship as specified in 904.01.05.
Notify the ME in writing at least 21 days before start of production.
For quality control, keep applicable records according to PCI Division 1, Quality Control, or NPCA requirements, and supply copies of these records to the ME as requested. Ensure that the quality control technician performing all tests is certified as an ACI Field Testing Technician, Grade 1.
During production, the ME will inspect the quality of materials and the process of manufacture. The ME will accept the concrete as specified in 903.03.05 and will inspect the finished pieces prior to shipping for dimensional tolerances and damage. If the concrete piece is spalled, honeycombed, chipped, or otherwise defective, the ME may reject the piece or approve repairs.
| Provide materials as specified: | ||
| Concrete | 903.03 | |
| Mortar | 903.08.01 | |
| Curing Materials | 903.10 | |
| Reinforcement Steel | 905.01 | |
| Prestressing Reinforcement | 905.02 | |
| Bolts and Bolting Materials | 908.01 | |
| Epoxy Waterproofing | 912.02.02 | |
| Epoxy Bonding Compound | 919.07 | |
In the construction of prestressed concrete I-beams or prestressed concrete slab and box beams, when the use of galvanized reinforcement steel is planned for the deck construction, galvanize all reinforcement steel that will provide composite action.
For prestressed concrete piles in a marine environment, use grit impregnated epoxy-coated prestressing steel strands as specified in 905.02. When storing, cover the strands with an opaque polyethylene sheeting or other suitable protective material to protect the reinforcement from exposure to sunlight, salt spray, and weather. For stacked bundles, drape the protective covering around the perimeter of the stack. Adequately secure the covering; however, allow air circulation to prevent condensation under the covering. Do not store epoxy-coated prestressing steel within 1000 feet of ocean or tidal water for more than 2 months.
Fabricate prestressed concrete at a plant as specified in 1011.02. Provide an office for the ME as specified in 1011.03.
| Table 904.04.02-1 Maximum Allowable Wire Breaks | |
| Number of Strands | Maximum Allowable Wire Breaks |
| Less than 20 strands | 0 |
| 20 to 39 strands | 1 |
| 40 to 59 strands1 | 2 |
| 60 and more strands1 | 3 |
| 1 | Replace the strand if more than 1 break occurs in an individual strand. |
Cure as specified in 904.01.03, except that the required stripping strength is 4000 pounds per square inch for Class P, 4500 pounds per square inch for Class P-1, and 5000 pounds per square inch for Class P-2 concrete. In addition, when the ambient air temperature is above 100 °F, initiate a water cure or other approved method as soon as the concrete is able to receive the water without physical damage to its surface. The fabricator may discontinue this cure upon introduction of steam, provided that a relative humidity of 100 percent is maintained.
Do not remove side forms until the strength of 2 cylinders, similarly cured as the member, achieves at least 2500 pounds per square inch. Do not move the member from the bottom forms before detensioning.
Upon the removal of forms, the ME may reject any member that has 1 prestressing strand exposed for a length in excess of 24 diameters, or 2 or more strands visually exposed. In addition, the ME may reject any unit that is honeycombed to such an extent that chipping away from honeycombed concrete results in the conditions described for exposed strands. If the ME determines that the defective areas can be repaired, submit a repair procedure to the ME for approval. Perform approved patching before detensioning.
Provide a Class 1 finish, as specified in 504.03.02.H.1, on formed surfaces of the concrete members. For surfaces of concrete exposed to view in the finished structure, perform additional finishing by rubbing mortar on the surface using burlap. Ensure that the rubbing produces a smooth surface of uniform color and texture. Transversely score the top surface of members using a stiff wire brush. After the removal of hold-down devices from the bottom of the beams, coat the resulting holes with an epoxy bonding compound, and plug the holes with mortar while the epoxy bonding compound is still tacky. If the epoxy bonding compound dries out before the placement of the mortar, sandblast the area and reapply the bonding compound. Patch vent holes for box beams upon removal from forms after the internal void drains are opened.
Treat portions of prestressed concrete beams as shown on the Plans with an epoxy waterproofing. Do not apply the epoxy waterproofing to the top surface of a beam. Use an epoxy waterproofing that closely matches the color of the concrete. Do not apply the epoxy waterproofing sooner than 72 hours after detensioning. Ensure that the concrete surface is dry and clean of oil, grease, and dirt before applying the coating. Apply the epoxy waterproofing by brush only, unless otherwise approved by the ME. Ensure that the epoxy waterproofing is applied uniformly and provides adequate coverage.
The fabricator may handle members immediately after completion of detensioning. Before placing members in storage, ensure that surface finishing operations are completed and the member is approved by the ME. Do not remove a girder from the bed unless the differential between girder and air temperature is less than 80 °F. Before box and slab beams are moved to storage, inspect nonmetallic draining devices and open to provide for passage of water.
Notify the ME at least 2 days before shipping. Do not ship until the class design strength as specified in Table 903.03.06-3 has been attained and a minimum of 72 hours have elapsed following detensioning. Determine shipping strength by testing a complete set of cylinders that represent the lot of concrete and were cured with the item.
Transport girders in an upright position. Ensure that the points of support and directions of the reactions with respect to the girder are approximately the same during transportation and storage as in its final erection position. Request the Department’s approval for transportation or storage of girders in any other position.
Notify the ME in writing at least 21 days before start of production.
For quality control, keep applicable records in conformance with PCI Division 1, Quality Control, or NPCA requirements, and supply copies of these records to the ME as requested. Ensure that the quality control technician performing all tests is certified as an ACI Field Testing Technician, Grade 1.
During production, the ME will inspect the quality of materials and the process of manufacture. The ME will accept the concrete as specified in 903.03.05 and will inspect the finished pieces prior to shipping for dimensional tolerances and damage. If concrete is placed on the same bed at different times in the day, the ME will split the day’s production into separate lots. If the concrete member is spalled, honeycombed, chipped, or otherwise defective, the ME may reject the piece or approve repairs.
For uncoated reinforcement steel, submit a certification of compliance as specified in 106.07. Attach copies of the mill certifications for each heat of reinforcement steel. The ME will randomly sample and test heats of uncoated reinforcement steel for quality assurance.
The ME will inspect galvanized and epoxy coated reinforcement steel before and after fabrication. For coated steel reinforcement bars, the ME will inspect the coating and take four 2-1/2-foot samples from each production heat for testing. For coated welded wire reinforcement, the ME will inspect the coating and take one 2-square foot sample from each production heat for testing. Provide the ME with mill certifications for each heat of reinforcement steel.
Use deformed bars according to ASTM A 615, Grade 60. Fabricate using the detailing dimensions for hooks, bends, and tolerances according to the CRSI Manual of Standard Practice. Bend bars using the cold method with positive powered machines in the shop or field. Compute the weight of reinforcement steel according to ASTM A 615.
If specified, galvanize according to ASTM A 767, Class I. Fabricate bends and details before galvanizing.
If specified, apply epoxy coating according to ASTM A 775.
Use spiral reinforcement that is plain round hot-rolled steel bars according to ASTM A 615, Grade 60. Compute the weight of reinforcement steel according to ASTM A 615.
Use plain steel welded wire reinforcement according to ASTM A 185 or deformed steel welded wire reinforcement according to ASTM A 497. When used for concrete pavement, use welded wire reinforcement mats at least 5 feet in width.
When approved as an alternate to galvanized reinforcement bars, use galvanized welded wire reinforcement that meets the requirements of ASTM A 641, Table 1, Class 1.
Ensure that structural shapes, plates, and bars used for reinforcement or other miscellaneous embedded metal work conform to the requirements for structural steel specified in 906.01. Galvanize according to ASTM A 123.
Use plain reinforcement bars according to ASTM A 615, Grade 60. Galvanize according to ASTM A 123.
The ME will sample and test each heat of steel reinforcement prior to use for acceptance. For prestressing strand, the ME will test two 4-foot cables with flame cut ends and one 1-foot piece with sawcut ends from each heat. For high-strength alloy bars, the ME will test one 6-foot bar from each heat. For post-tensioning, the ME will test one 6-foot cable (between fittings) from each reel or one 6-foot bar (between threads) from each lot. Provide a certification of compliance as specified in 106.07. Attach the mill certification for each heat used with the certification of compliance.
Use high-tensile-strength, low-relaxation 7-wire strand for prestressing reinforcement according to ASTM A 416, Grade 270. When specified, use grit impregnated epoxy-coated steel strands according to ASTM A 882.
Use high-tensile strength alloy bars for prestressing or post-tensioning according to ASTM A 722.
For tie bars and joint ties in longitudinal joints for concrete pavement, use epoxy coated deformed reinforcement steel bar as specified in 905.01.01.
Provide certifications of compliance as specified in 106.07. Attach a mill certification for each heat used to the certification of compliance.
For tie bolts in longitudinal joints for concrete pavement, use epoxy coated plain reinforcement steel bar that meets the requirements as specified in 905.01.01. Perform all required bending of tie bolts in a fabrication shop. Do not field bend tie bolts. Use rebar coupling devices as specified in 905.04.
Provide certifications of compliance as specified in 106.07. Attach a mill certification for each heat used to the certification of compliance.
For dowel bars in transverse joints, use epoxy-coated, Grade 60, plain reinforcement steel according to ASTM A 615. If shown on the Plans, use dowel bars fitted with end caps. Ensure that the end caps are non-metallic and designed to prevent the entrance of grout or mortar into the expansion void.
Provide certifications of compliance as specified in 106.07. Attach a mill certification for each heat used to the certification of compliance.
To splice reinforcement steel, use a rebar coupling device that is listed on the QPL. Ensure that the mechanical coupling device develops a minimum of 125 percent of the specified yield strength of the reinforcement steel. If the reinforcement steel has either galvanizing or epoxy coating, use a mechanical coupling device with a matching coating system. Provide certifications of compliance as specified in 106.07.
Provide structural steel materials conforming to the requirements in Table 906.01-1 and as shown on the Plans.
| Table 906.01-1 Structural Steel Materials Requirements | ||
| Product | Test Method | Type/ Grade/ Class |
| Structural Steel Plate1 | ASTM A 709 | Grade 36, 50, 50W, or HPS70W2 |
| Tie rods, plate washers, tie backs, turnbuckles, plates, shapes, and shims | ASTM A 709 | Grade 36 |
| Steel tube and pipe for Sign Structures 3, 4 | ASTM A 53 | Type S, Grade B or Type E, Grade B |
| Steel Piles | ||
| Steel H-piles | ASTM A 572 | Grade 50 |
| Steel sheet piles | ASTM A 572 | Grade 50 |
| Steel pipe piles | ASTM A 252 | Grade 2 |
| Casings for Drilled Shafts5 | ASTM A 252 | Grade 2 |
| Flooring | ||
| Grid Flooring | ASTM A 709 | Grade 36 |
| Formed Steel Flooring | ASTM A 1011 | Grade 30 |
| Steel Forgings | ASTM A 668 | Class C |
| Shear Connector Studs6 | ASTM A 108 | Grades G1015, 1018, or 1020 |
| Stay-In-Place (SIP) Forms7 | ASTM A 653 | Grades 33, 37, 40, 49, or 80 |
| 1 | For steel used in tension zones, ensure that the steel conforms to Zone 2 impact testing requirements. |
| 2 | For the manufacture of Grade HPS70W, the Department will allow the use of the Thermo-Mechanical Controlled Process. |
| 3 | For sizes less than or equal to 24 inches in diameter, only use electric resistance welded single seam pipe. |
| 4 | For pipe with wall thickness greater than 1/2 inch, the fabricator may substitute API Specification 5L, Grade B. |
| 5 | For casings, use smooth, non-corrugated steel pipe. |
| 6 | For shear connector studs, use cold-drawn bars that are killed or semi-killed. |
| 7 | For SIP, use a galvanized coating designation G235 or Z700. |
Before using, submit to the ME a representative sample of each size for material testing and approval. Provide a mill certification that indicates the chemical and physical properties for each heat of material. For SIP forms, steel forgings and shear connector studs, submit certifications of compliance, as specified in 106.07, with the mill certifications attached.
Use materials as specified in 906.01. When used in a marine environment, coat piles with coal tar epoxy paint as specified in 912.01.03.
Ensure that the closure plate for steel pipe piles is equal to the pile outside diameter and has a minimum thickness of 3/4 inch. Weld around the entire circumference.
For H-pile tips, use steel castings that conform to AASHTO M 103, Grade 65-35 or 70-36 or high-strength steel castings that conform to ASTM A 148.
Submit certifications of compliance, as specified in 106.07, with mill certifications attached.
Use materials as specified in 906.01. Ensure that the casing is capable of withstanding handling and driving stresses and the pressures of the concrete and surrounding earth. Use a casing with an inside diameter that is at least as large as the indicated shaft size. The Contractor may increase the size of the casing to facilitate construction operations.
For permanent casings, clean and coat the exterior surfaces with prime coat of an inorganic zinc coating system as specified in 906.06.
Submit certifications of compliance, as specified in 106.07, with mill certifications attached.
Ensure that the structural steel fabricating plant is certified under the AISC Quality Certification Program in the following categories by the type of work performed:
Structural steel fabricators that are certified by AISC for Major Steel Bridges are automatically certified for Simple Steel Bridges.
Before fabrication, submit a copy of the proposed welding procedures to the ME for approval. Follow the approved welding procedures and ensure that welders are qualified according to ANSI/ AWS D1.5.
Use structural steel materials as specified in 906.01 and bolting materials as specified in Section 908. Fabricate according to AASHTO LRFD Bridge Construction Specifications and as shown on the working drawings. Construct welds according to the requirements of ANSI/ AASHTO/ AWS D1.5 Bridge Welding Code, as modified by the following:
Induce camber in structural steel girders at the mill, or fabricate structural steel girders in the shop in a manner that provides a true curve without abrupt changes.
In the shop, completely pre-assemble stringers involving field splices and built-up girders with field splices.
Submit to the Department, for approval, all changes in the number or location of shop or field splices.
Without the Department’s approval, do not weld to members or parts of members subject to tension or reversal of stress. If necessary to weld in these areas, ensure that the actual stress range (FSR) at the point of attachment does not exceed the value for Category F according to the AASHTO LRFD Bridge Design Specification.
Obtain the ME’s approval for all shop fabrication and assembly before blast cleaning and coating.
Notify the ME at least 3 days before shipping to the Project so that a final quality inspection can be performed. The ME will seal all materials approved for shipping and provide written approval to the fabricator.
Ensure that members are loaded, hauled, and unloaded so that they are not deformed, damaged, or subjected to stresses in excess of those provided for in the design. When hauling and storing steel members, to the extent possible, place the members in a position similar to their final erected position.
Ensure that all steel girders are shipped and stored with their webs vertical, unless their size precludes vertical shipment. Place points of bearing within 20 percent of the length of the girder from the ends, and secure with chain tie downs. If not provided for in the design, brace long members during shipment with temporary vertical stiffeners extending the full height of the web on both sides of the member. Place the temporary stiffeners at the bearing points, mid-span, and at additional locations to ensure that the maximum interval between bracing does not exceed 25 feet. Ensure that temporary stiffeners are in full contact with the web and both flanges. Pad the temporary stiffeners with a material that will minimize damage to the painted surface.
For girders requiring shipment with their web horizontal, or for girders that will extend over 20 percent of the length beyond points of bearing, submit working drawings for approval. Include the following information:
Notify the ME, in writing, at least 15 days before beginning work at the fabrication shop. The ME may reject any work done in his absence if proper notification was not received.
Perform at least the minimum specified number of quality control inspections according to the applicable ANSI/ AASHTO/ AWS specification and any other tests and inspections necessary to control the quality of the work. The ME will perform non-destructive testing quality assurance inspections following the non-destructive testing quality control (QC) inspection performed by the fabricator.
Ensure that all quality control inspectors are AWS Certified Welding Inspectors, qualified according to the provisions of AWS QC1.
Inspect and test structural steel bridge members according to ANSI/ AASHTO/ AWS D1.5 Bridge Welding Code, as modified by the following:
Ensure that the fabricating plant is certified under the AISC Quality Certification Program as specified in 906.04.01. Before fabrication, submit a copy of the proposed welding procedures to the ME for approval. Follow the approved welding procedures, and ensure that welders are qualified according to ANSI/AWS D1.1 or ANSI/AWS D1.2, as appropriate.
To fabricate sign structures, use structural steel materials as specified in 906.01, bolting materials as specified in Section 908, and aluminum materials conforming to ASTM B 308, Alloy 6061-T6. Weld and fabricate according to AWS D1.1, Structural Welding Code. For aluminum members, weld and fabricate according to ANSI/AWS D1.2 Structural Welding Code – Aluminum. Do not flame cut aluminum alloy materials. For cantilever sign support structures, ensure that the splice plates and truss chords do not warp during fabrication.
After fabrication and welding, hot-dip galvanize the steel assemblies as specified in 912.02.01. After galvanizing, but before shipment to the Project, return the truss and posts to the fabricator for final shop assembly to verify camber, alignment, and contact of splice mating surfaces.
Notify the ME at least 3 days before shipping to the Project or galvanizer so that a final quality inspection can be performed. The ME will seal all materials approved for shipping and provide written approval to the fabricator.
Ensure that members are loaded, hauled, and unloaded so that they are not deformed, damaged, or subjected to stresses in excess of those provided for in the design.
Notify the ME, in writing, 15 days in advance of beginning work at the fabrication shop, so that arrangements for inspection may be made.
Perform at least the minimum specified number of quality control inspections according to the applicable ANSI/ AASHTO/ AWS specification, and any other tests and inspections necessary to control the quality of the work. The ME will perform non-destructive testing quality assurance inspections following the non-destructive testing quality control (QC) inspection performed by the fabricator.
Ensure that all quality control inspectors are AWS Certified Welding Inspectors, qualified according to the provisions of AWS QC1.
Inspect and test according to ANSI/ AASHTO/ AWS D1.1 Welding Code and the following:
Use an Inorganic Zinc coating system (IEU) of an inorganic zinc-rich primer, epoxy intermediate coat, and a urethane finish coat. Ensure that the coating system is as specified in 912.01.01.
In the fabrication of steel box girders, apply the IEU coating system to all exterior surfaces. Coat the interior of the box girders with only a prime coat of an organic zinc primer selected from an organic zinc coating system (OEU) listed on the QPL and as specified in 912.01.01. Unless approved by the ME, use an organic zinc primer from the same manufacturer as the IEU system for the exterior of the girder.
Before blasting, remove any oil and grease, according to SSPC-SP 1, using No. 1 solvent. Reclean after blasting if contamination remains.
Blast-clean all surfaces to a near-white condition, as defined in SSPC-SP 10. Ensure that the surface area of steel being blast cleaned is not greater than the surface area of steel that can be prime coated in the same day. If shot blast is used, use a NACE No. 2 Visual Standard T.M.-01-75 or Maryland Pictorial Standard to define the near-white blast condition. If sand or grit is used, use SSPC Pictorial Standard VIS-1 (Grade 2-1/2) to define the near-white condition. Blast clean to an anchor profile, from 1.5 mils to 3.0 mils deep. Grind any flame cut edges that do not attain the required anchor profile. Determine the profile depth using the elcometer surface profile gauge or Testex replica tape. Ensure that the pH of the abrasive is within the range of 6.0 to 8.5.
Remove fins, tears, slivers, and burred or sharp edges that are present, or that appear during the blasting operations, by grinding, and ensure that the reblasted area provides the required anchor profile.
Before blast cleaning steel, ensure that all reaming and drilling of holes in the steel has been completed, and the steel is free of burrs or other imperfections, such as torn or ragged edges. Remove all abrasive residue and dust from steel surfaces, and keep the surfaces clean until the prime coat is applied. Protect freshly coated surfaces from subsequent blast cleaning operations. Repair blast damaged primed surfaces using a wire brush, or, if visible rust occurs, reblast the surface to a near-white condition, re-clean, and re-prime the repaired area.
Perform shop painting in an enclosure that is maintained at the required atmospheric conditions and that prevents exposure to inclement weather before the paint has completely cured. Perform painting according to the conditions specified in SSPC-PA 1 and the following:
Mix paint according to the manufacturer’s recommendations. Apply paint as specified in SSPC-PA 1 and the following:
Apply all 3 coats in the shop. Ensure that the dry film thickness meets the minimum requirement as specified in Table 906.06.05-1 but does not exceed the manufacturer’s recommendation for maximum thickness. Determine dry film thickness according to SSPC-PA 2.
| Table 906.06.05-1 Dry Film Thickness Requirements | |
| Coat | Minimum Thickness (mils) |
| For the prime coat | 1 mil more than the measured anchor profile |
| For the intermediate coat | 3.5 |
| For the finish coat | 2 |
| For the 3-coat system | 8.5 |
Ensure that the dry film thickness of the prime coat at the contact surfaces of bolted friction splices on main members, and the top of top flanges where stud shear connectors are to be welded, is within the range of 1 to 2.5 mils.
After the final coat has dried, stencil the following information in 4-inch high, C series, letters and numerals on the outside web of both fascia beams, on both ends of the structure:
Stencil using a black paint that is the same type of paint as the finish coat. Locate the information at least 2 inches above the lower flange and within 3 feet from the abutment.
Allow the paint to dry before loading and shipping the steel. Protect the coated steel from the binding chains using softeners. Use padded hooks and slings to hoist steel. Space diaphragms and similar pieces to prevent damage to the coating during shipment. Before shipping, submit to the RE for approval, all shipping and work site storage details.
Notify the ME, in writing, at least 15 days in advance of beginning work at the fabrication shop, so that arrangements for inspection may be made.
The ME will reject the coating system if rusting occurs; the paint lifts, blisters, wrinkles, or has excessive runs or sags; workmanship is poor; or unapproved paint is used. In addition, the ME will reject the total coating system if it is determined by measurement with a Tooke gauge that the dry film thickness of the prime, intermediate, or finish coat is less than the minimum specified or if the total dry film thickness is less than the 8.5-mil minimum for the 3-coat system.
For 4-bar open steel parapet, provide anchor studs, washers, and exposed bolts according to ASTM F 568, Class 8.8, and all other bolts and nuts according to ASTM F 568, Class 4.6. Also, provide rail bars according to ASTM A 500 or A 501, rail post according to ASTM A 709, Grade 50, and all other shapes and plates according to ASTM A 709, Grade 36.
Fabricate 4-bar steel parapet according to 906.04 and paint according to 906.06.
Provide high-load multi-rotational (HLMR) or seismic isolation bearing assemblies conforming to the loads shown on the Plans. Provide the design from the manufacturer for each HLMR or seismic isolation bearing assembly.
Ensure that the materials and fabrication of bridge bearing assemblies conform to Section 18 of the AASHTO LRFD Bridge Construction Specification.
Ensure that the fabricating plant is certified under the AISC Quality Certification for Simple Steel Bridge Structures. Consider steel bridge bearings and HLMR bearing assemblies to be main load carrying members. Perform welding and ensure that welders are qualified according to the ANSI/ AASHTO/ AWS D1.5 Bridge Welding Code.
Unless otherwise specified, provide hot-dipped galvanized steel bearing components as specified in 912.02.01. When painting of steel surfaces is required, paint as specified in 906.06.
Mark each structural bearing in indelible ink on 2 sides with the Department Project Number, the structure number, location, orientation, order number, lot number, bearing identification number, and elastomer type and grade. For seismic isolation bearings, make a permanent mark on 2 of the 4 sides of each isolator, consisting of an isolator number specified by the supplier, the date of fabrication (month and year), the isolator type, and the supplier (name and address).
Ensure that the bearings are packaged to be protected against damage from handling, shipping, and storage. Securely bolt, strap, or otherwise fasten to prevent all relative movement. Wrap the bearings in moisture resistant and dust resistant material to protect them from weather.
When providing seismic isolation bearing assemblies, assemble the isolators and their mounting plates at the shop. Provide temporary assembly ties so that the entire assembly is shipped, in protective packaging, as a unit. Provide the RE with elastomeric bearing test results for both compression stiffness and combined compression and shear according to Section 15 of the AASHTO Guide Specifications for Seismic Isolation Design.
Enclose a copy of the materials, fabrication, and testing compliance certifications with each shipment. Supply a separate sheet showing the materials, critical dimensions, and clearances for each bearing.
Notify the ME, in writing, 15 days before the start of fabrication, so that arrangements for inspection may be made.
Ensure that quality control inspectors are AWS Certified Welding Inspectors, qualified according to the provisions of AWS QC1.
Test and inspect structural bearing assemblies according to Section 18 of the AASHTO LRFD Bridge Construction Specifications. Provide test results to the ME at the time of inspection.
Provide to the ME certifications of compliance, as specified in 106.07, for all non-ferrous metals, PTFE, adhesives, dowel bars, and bolts. Include with the certifications mill test reports for all steels used and material test reports for all elastomeric components.
Provide reinforced elastomeric bearings conforming to the requirements shown on the Plans. Reinforced elastomeric bearing assemblies consist of circular or rectangular reinforced elastomeric bearings that are Grade 3 with a durometer hardness of 60. Fabricate reinforced elastomeric bearing assemblies according to Section 18 of the AASHTO LRFD Bridge Construction Specifications.
Ensure that the materials and fabrication of bridge bearing assemblies conform to Section 18 of the AASHTO LRFD Bridge Construction Specification.
Enclose a copy of the materials, fabrication, and testing compliance certifications with each shipment. Supply a separate sheet showing the materials, critical dimensions, and clearances for each bearing.
Provide to the ME certifications of compliance, as specified in 106.07. Include material test reports.
Provide elastomeric pads conforming to the requirements shown on the Plans. Provide elastomeric bearing pads that are a Grade 2 with a durometer hardness of 60 according to Section 18.2 of the AASHTO LRFD Bridge Construction Specifications.
Ensure that the materials and fabrication of bridge bearing pads conform to Section 18 of the AASHTO LRFD Bridge Construction Specifications.
Provide to the ME certifications of compliance, as specified in 106.07. Include material test reports.
Before using, submit a sample of each size of bolt, anchor, washer, and nut to the ME for testing and approval. Provide a mill certification for each heat.
Use steel bolts conforming to ASTM A 307. If galvanizing is specified, use the hot-dipped method according to ASTM A 153.
Use nuts and washers according to ASTM A 194 or ASTM A 563. Ensure that plain nuts are Grade 2H, DH, DH3, 2, C, D, or C3. Ensure that galvanized nuts are Grade 2H, DH, or DH3. Use washers with high-strength steel bolts conforming to ASTM F 436.
If galvanizing is specified, use the hot-dipped method according to ASTM A 153.
For anchor bolts intended for anchoring structural supports to concrete foundations, including piers, columns, column supports for sign support structures, lighting fixtures, traffic signals, steel bearing plates, and similar applications, use ASTM A 307, Grade C, or ASTM F 1554, Grade 36, 55, or 105, anchor bolts, as shown on the Plans.
If galvanizing is specified, use the hot-dipped method according to ASTM A 153.
Use anchor bolts conforming to ASTM A 307, Grade C. If galvanizing is specified, use the hot-dipped method according to ASTM A 153. Ensure that the adhesive anchor bolt system conforms to the following proof loading requirements:
After concrete has achieved a minimum compressive strength of 3000 pounds per square inch, perform proof loading on 10 percent of the installed adhesive anchors at each location where the anchors have been placed. Provide calibration certificates for the test equipment before testing. Perform all testing in the presence of the RE. Tension test the anchor bolt system according to ASTM E 488 to 90 percent of the yield strength of the anchor bolts. If the location of the anchor bolts precludes the proof loading of anchor bolts according to ASTM E 488, propose an alternate testing method to the RE for approval. Repair all spalls or cracks caused by the testing.
Based on satisfactory performance in proof loading, the RE will approve the adhesive anchor bolt installation. The RE will reject the anchor bolt installation for failure to conform to the proof loading requirements. With the approval of the RE, replace the adhesive anchor bolt installation by using larger size anchors, increasing the embedment depth, or using another anchor bolt system.
For structural steel erection and for steel to steel chord splices of sign structures, use high-strength steel bolts, including nuts and plain hardened washers according to ASTM A 325 or ASTM A 490.
When galvanizing is specified, use the hot-dipped method according to ASTM A 153. Treat galvanized bolts, washers, and nuts as an assembly. Store and ship the assembly in plastic bags placed inside wood or metal containers.
Use ASTM A 325, Type 3 high-strength steel bolts for bolting unpainted corrosion resistant (weathering) steel.
Record the results of all tests. Also report the date and location of testing.
Ship bolts, nuts, and washers from each rotational-capacity lot in the same container. If there is only one production lot number for each size of nut and washer, the manufacturer or distributor may ship the nuts and washers in separate containers. Permanently mark each container with the rotational-capacity lot number to allow identification at any stage before installation.
Treat galvanized bolts and nuts as an assembly and ship together.
Supply mill certifications, manufacturer certified test reports, and distributor certified test reports for each rotational-capacity lot to the RE and ME.
Use direct tension indicators conforming to ASTM F 959. If galvanizing of the bolt assembly is required, mechanically galvanize DTIs according to ASTM B 695, Class 50. If DTIs are used with ASTM A 325, Type 3 bolts, coat the DTIs with a black epoxy. Test DTIs according to ASTM F 959 and verify according to NJDOT S-3.
Provide manufacturer’s certification and attach test results.
Use stainless steel bolts, screws, studs, anchor bolts, nuts, and washers that conform to ASTM A 320, Class 1, Grade B8. Prior to use, submit a sample of each size of bolts, anchors, washers, and nuts to the ME for testing and approval. Provide a mill test report for each heat.
Use bolts, nuts, set screws, and pins that conform to ASTM B 211, Alloy 2024-T4 with No. 205 Alumilite Finish. Ensure that bolt heads and nuts are American National Standard, Regular Series, hexagonal, semi-finished, conforming to ANSI B18.2.1 to B18.2.2, and that threads are American National Standard, Coarse Series, Class 2 Fit, conforming to ANSI B1.13M. Finish bolts with an anodic coating thickness of not less than 0.0002 inches and chromate seal.
Use washers conforming to ASTM B 209, Alloy 2024-T3.
Before using, submit a sample of each size of bolts, set screws, pins, washers, and nuts to the ME for testing and approval. Provide a mill test report for each heat.
Use concrete as specified in 903.03.
Use sand or sandy soil with 100 percent passing the 3/8-inch sieve and no more than 10 percent passing the No. 200 sieve.
Use a granular soil conforming to the gradation requirements in Table 909.01-1.
| Table 909.01-1 Gradation for Class C Bedding | |
| Sieve Size | Percent Passing |
| 1 inch | 100 |
| No. 4 | 80 - 100 |
| No. 200 | 0 - 12 |
Use coarse aggregate No. 8 as specified in 901.03.
In the manufacture of reinforced concrete pipe, use concrete that is composed of cement, coarse aggregate, fine aggregate, and water. Concrete may include admixtures, fly ash, or slag.
| Provide materials as specified: | ||
| Aggregates | 901.06 | |
| Admixtures: | ||
| Air-Entraining | 903.02.01 | |
| Chemical | 903.02.02 | |
| Fly Ash | ASTM C 618, Class C or F |
| Slag | 903.02.03.B | |
| Cement | 903.01 | |
| Water | 919.08 |
If fly ash is used to control alkali-silica reactivity, use Class F fly ash.
Manufacture reinforced concrete culvert pipe, storm drain, and sewer pipe to conform to AASHTO M 170, Class III, Wall B, unless otherwise designated. For jacked pipe, use reinforced concrete culvert pipe conforming to AASHTO M 170, Class V, Wall B. Manufacture reinforced concrete elliptical culvert, storm drain, and sewer pipe to conform to AASHTO M 207, Class HE-III, unless otherwise designated.
If required for watertight flexible joints, use preformed flexible joint sealants conforming to AASHTO M 198.
Notify the ME at least 2 days before shipping pipe to the Project. The ME will inspect and approve pipe in the supplier’s yard after manufacture. For approval of the concrete pipe, perform 3-point loading in the supplier’s yard at a frequency directed by the ME.
Use corrugated HDPE drainage pipe that conforms to AASHTO M 294 and is Type S (smooth interior with annular corrugations) with gasketed silt-tight joints.
Use HDPE pipe from a manufacturer who is an Eastern States Consortium (ESC) qualified manufacturer of HDPE. For a list of qualified manufacturers, see the ESC website at www.nh.gov/dot/espc/.
Submit a certification of compliance, as specified in 106.07, for HDPE pipe.
Use corrugated polyethylene drainage pipe according to AASHTO M 252, or use PVC drainage pipe according to ASTM D 2729.
Submit a certification of compliance, as specified in 106.07, for plastic drainage pipe.
Use corrugated aluminum alloy culvert pipe and pipe arches conforming to ASTM B 745, Types I or II, and the following:
Submit a certification of compliance, as specified in 106.07, for corrugated aluminum alloy pipe and pipe arches.
Use corrugated aluminum alloy underdrain pipe conforming to ASTM B 745, Type III. Fabricate the pipe using 0.048-inch-thick sheet metal.
Submit a certification of compliance, as specified in 106.07, for corrugated aluminum alloy underdrain pipe.
Use corrugated steel pipe and pipe arches conforming to ASTM A 760, Types I and II. Use special sections, such as elbows and flared end sections, that conform to ASTM A 760 and are of the same thickness as the conduit to which they are joined. Ensure that corrugated steel pipe and pipe arches and special sections also comply with the following:
Ensure that corrugated steel pipe, coupling bands, elbows, and flared end sections have a polymeric coating conforming to AASHTO M 246, Grade 36/11 (interior 0.010 inches and exterior 0.003 inches).
Submit a certification of compliance, as specified in 106.07, for corrugated steel pipe and pipe arches.
Fabricate steel alloy pipe and fittings from alloy steel conforming to the chemical analysis of ASTM A 53, Grade B or ASTM A 500. The Contractor may use ductile iron pipe conforming to ASTM A 377 (ANSI/ AWWA C151/ A21.51) as an alternate. Ensure that the pipe and fittings are zinc-coated (galvanized) according to ASTM A 123. Weld steel pipe and fittings together before galvanizing.
If ductile iron pipe is used, ensure that ductile iron pipe fittings conform to ASTM A 48, Class 30. Bend pipe using the long radius type of bend. Form pipe joints using groove-type couplings, consisting of a housing clamp keyed into a groove cut around the full pipe circumference. Provide a gasket of molded or extruded butyl rubber or ethylene propylene diene monomer to create a sealed joint. Use track-type bolts, conforming to ASTM A 183, with oval necks and heavy hexagonal standard nuts. Galvanize the assembly according to ASTM A 153.
Submit a certification of compliance, as specified in 106.07, for steel alloy pipe.
Use ductile iron water pipe conforming to ANSI/ AWWA C151/ A21.51. Use threaded flanges conforming to ANSI/ AWWA C115/ A21.15, and fittings conforming to ANSI/ AWWA C110/ A21.10 or C153/ A21.53. Do not field weld ductile iron pipe. Perform required welding of a ductile iron pipe assembly in a fabrication shop.
Submit a certification of compliance, as specified in 106.07, for ductile iron water pipe.
Fabricate fiberglass pipe conforming to ASTM D2996, RTRP-12EA1-2122 and fiberglass pipe fittings conforming to ASTM D3840.
Ensure that all fiberglass pipe, fittings and adhesives use pigmented resin throughout the wall and the color is concrete gray or designated color with UV stabilized resin. Painted gel-coat or exterior coating is not acceptable.
Ensure that adhesives are in accordance with the pipe manufacturer and adhesive manufacturer’s recommendations.
Ensure that castings, grates, extension rings, extension frames, and covers for inlets and manholes are capable of withstanding HS-25 loading when tested as a complete, assembled unit and conform to the following:
For gray iron castings, notify the ME at least 2 days before shipping to the Project. The ME will inspect and approve castings in the supplier’s yard after fabrication. For approval of the gray iron casting, perform proof load or test bar testing according to AASHTO M 306 in the supplier’s yard at a frequency directed by the ME.
For Items other than gray iron castings, submit certifications of compliance as specified in 106.07.
Use clay or shale brick conforming to AASHTO M 114, Grade MW, with the dimensions as specified in Table 910.01-1.
| Table 910.01-1 Dimensions of Clay or Shale Brick | |
| Length | 7-3/4 – 8-1/4 inches |
| Width | 3-1/2 – 3-7/8 inches |
| Depth | 2-1/8 – 2-3/8 inches |
Submit a certification of compliance as specified in 106.07.
In the manufacture of concrete block, use cement as specified in 903.01 and aggregates conforming to the requirements for concrete aggregates as specified in 901.06. Manufacture concrete block according to ASTM C 139. The manufacturer shall sample and test concrete block according to ASTM C 140.
Manufacture blocks to be either rectangular in shape or curved with the inside and outside surfaces curved to the required radii, whichever is appropriate for the shape of the structure. Ensure that the length is between 12 and 18 inches, the height is between 5 and 8 inches, and the width is at least 6 inches.
For the reduction of cross-sectional area of the cones or tops of manholes, the Contractor may use blocks of special shapes and heights. The Contractor may also use blocks of special shapes and heights in the top courses of all structures so that the head castings is set at the required elevation on a mortar bed not more than 1/2 inch thick without cutting the blocks.
Ensure that all blocks have an interlocking-type joint at the ends and are sound and free from cracks or other defects.
Submit a certification of compliance as specified in 106.07.
In the manufacture of concrete brick, use cement as specified in 903.01 and aggregates conforming to the requirements for concrete aggregates as specified in 901.06. Manufacture concrete brick to conform to ASTM C 139 and to the dimensions specified in Table 910.01-1. The manufacturer shall sample and test concrete brick according to ASTM C 140.
Submit a certification of compliance as specified in 106.07.
Use stone curbs that are of a lithology, color, and texture as specified in the Special Provisions. Fabricate stone curb from a commercially available material with an established history of satisfactory durability and resistance to weathering. Use curb stones from a single quarry with the same color and texture. The Department may allow reasonable variations in color and texture if the variations do not affect the architectural qualities or the structural properties of the stone.
| Table 910.04-1 Maximum Allowable Deviations for Dressed Stone |
||
| Depression (inches) | Projection (inches) | |
| Top | 1/4 | 1/4 |
| Front, dressed part | 1/4 | 1/4 |
| Front, undressed part | 1-1/2 | 1/2 |
| Back, dressed part | 1/2 | 1/2 |
| Back, undressed part | 1-1/2 | 1-1/2 |
| Ends, dressed part | 1/4 | 1/4 |
| Ends, rough-dressed part | 1/2 | 1/4 |
| Ends, undressed part | 1-1/2 | 1/4 |
The Contractor may use straight-cut stone for curved curb having a radius of more than 50 feet, but shall dress the curb to true radius after it is set in place. For curved curb having radii smaller than 50 feet, cut the stone to the required radius, and cut the ends so that the joints are less than 1/4 inch wide for the full depth.
Submit a certification of compliance as specified in 106.07.
Use stone facing for pier shafts that is of a lithology, color, and texture as specified in the Special Provisions. Ensure that the stone is sound, durable, and free from flaws, discoloration, and structural defects. Granite and stone of similar lithologies normally exhibit a relatively uniform color and texture. The Department may allow a reasonable variation in color and texture and an occasional irregular distribution of the component minerals of the granite, termed waves, or knots, if the variations do not impair the architectural qualities or affect the structural properties of the stone. Quarry the stone from quarries that have ample production capacity both as to quantity and quality.
Submit 1 × 1-foot duplicate samples to the Department to indicate the range of color, texture, and surface finish of the stone to be provided. After approval of the samples, the Department will return 1 set of samples for guidance. Ensure that all stone used in the Project matches the samples.
Ensure that the stone provided is capable of withstanding a crushing stress of 20,000 pounds per square inch on 2-1/2-inch diameter cores tested air-dry.
Submit a certification of compliance as specified in 106.07. Include with the certification a performance history indicating that the stone proposed for use has satisfactorily withstood prolonged exposure in environments similar to that of the Project.
For stone paving block, use new or used stone block of good quality. Ensure that the color, texture, and uniformity conform to the requirements specified in the Special Provisions. Ensure that reclaimed blocks are free of bituminous and cement grout coatings and other foreign matter.
Submit a certification of compliance as specified in 106.07.
| Table 911.01.01-1 Aluminum Sign Components | ||
| Aluminum Items | Test Method | Alloy and Temper |
| Flat Sign Sheets1 (0.080", 0.100", 0.125" thicknesses) | ASTM B 209 | 5052-H38 or 6061-T6 |
| Extruded Sign Panels1,2 | ASTM B 221 | 6063-T6 |
| Demountable Letters, Numerals, Symbols (0.040" thickness) | ASTM B 209 | 5052-H38 or 6061-T6 |
| Bars and Rods | ASTM B 221 | 6063-T6 |
| Washers, Alclad | ASTM B 209 | 2024-T4 |
| Flange Splicing Material | ASTM B 209 | 6061-T6 |
| Shims | ASTM B 209 | 1100-O |
| Posts, Truss Chords, Truss Bracing Members | ASTM B 221 | 6061-T6 |
| Post and Chord Caps | ASTM B 26 | 356.0-T6 |
| Post Clips | ASTM B 26 | 356.0-T6 |
| Structural Shapes (Z-Bar Reinforcement) | ASTM B 308 | 6061-T6 |
| Nuts, 5/16 inch and larger | ASTM B 211 | 6061-T6 |
| Tamperproof Nuts, 1/4 inch and under | ASTM B 211 | 2017-T4 |
| Rivets (size and length recommended by the manufacturer) | ASTM B 316 | 5052-0 |
| Bolts (finished bolts with at least 0.002" chromated sealed anodic coating) | ASTM B 211 | 2024-T4 |
| 1 | For flat sign sheets and extruded sign panels, ensure that aluminum is chromate conversion coated according to ASTM B 449, Class 2. |
| 2 | For extruded panels, use lightweight panels. |
| Table 911.01.01-2 Allowable Sign Sheeting Types | ||
| Sign Type | Test Method | Type |
| Regulatory and Warning Signs | ASTM D 4956 | Type III |
| Guide Signs Mounted on Steel “U” Posts | ASTM D 4956 | Type III |
| Guide Signs Mounted on Overhead Sign Structures, Breakaway Sign Supports, or Non-breakaway Sign Supports | ASTM D 4956 | Type VIII or Type IX |
| Table 911.01.02-1 Requirements for Sheet Aluminum Thickness for Flat Panel Signs |
|
| Sign Type | Thickness (inches) |
| Signs measuring less than 8.0 square feet (except One-Way signs) | 0.080 |
| Signs measuring 8.0 square feet or greater | 0.100 |
| One Way Signs | 0.125 |
Package, ship, and store panels on edge and according to the sheeting manufacturer’s recommendations. Ensure that all signs are packaged so that they are protected from moisture and damage during shipment and storage.
Notify the ME at least 3 days before shipping to the Project so that arrangements for inspection can be made. The ME will reject signs not fabricated according to the MUTCD Manual of Standard Highway Signs and the Plans. The ME will ensure that finished signs are clear and legible without smudging, blisters, delamination, loose edges, or other blemishes. The ME will also ensure that the colors have a consistent chromaticity across all signs of the same color.
At the time of the inspection, provide copies of mill certifications for the aluminum components and copies of certification of compliance, as specified in 106.07, for the sign sheeting.
Use steel “U” post sign supports conforming to ASTM A 499, Grade 50 or 60, with the length of post and minimum pounds per foot as shown on the Plans. Provide 18-8 stainless steel 5/16 × 18 UNC hexagonal headed bolts and nuts conforming to ASTM A 320, Grade B8, Class 1, for securing the signs to the steel “U” post. Provide sign mounting bolts that are sized to extend beyond the end of each nut by no more than 3/4 inches when fully tightened.
Submit a certification of compliance, as specified in 106.07, for “U” posts.
Fabricate and construct breakaway sign supports for ground mounted signs using materials conforming to the requirements in Table 911.02.02-1.
| Table 911.02.02-1 Materials for Breakaway Sign Supports | |||
| Item | Test Method | Type or Grade | Galvanizing |
| Aluminum Materials (other than bracket) | 911.01.01 | ||
Bracket |
B308 |
6061-T6 |
|
Structural steel shapes |
ASTM A709 |
Grade 36 |
ASTM A123 |
Steel Sheet |
ASTM A1011 |
Grade 36 |
ASTM A 653 |
Bolts (except special bolt for coupling) |
ASTM A325 |
ASTM A153 | |
Special bolt for coupling |
ASTM A449 |
ASTM A153 | |
Cap Screw |
ASTM A307 |
ASTM A153 | |
Lock Washer |
ANSI B18-21-1 |
ASTM A153 | |
Nut |
ASTM A563 |
Grade DH |
ASTM A153 |
Coupling |
AMS 6378 F |
ASTM A153 | |
| Steel Hinge Plate | AISI 4130 |
ASTM 123 | |
Anchor Rod |
AISI 1045 |
||
Anchor Coil |
AISI 1008 |
||
Anchor Washer |
908.04 |
||
Anchor Ferrule |
908.04 |
||
Submit mill certificates for the component materials.
THE text of this subpart is deleted.
This subpart is INTENTIONALLY left blank
Use timber posts conforming to the requirements for sawn timber posts as specified in 915.01.
Provide brackets for mounting signs (including future signs) to the structure. Ensure that the brackets are adjustable to allow mounting of the sign faces at any angle between a truly vertical position and 3 degrees from vertical. Obtain this angle by rotating the front lower edge of the sign forward of the top edge. Fabricate brackets to lengths equal to the height of the signs being supported.
Submit mill certifications for the brackets.
Ensure that flexible delineator units are made of a fiberglass reinforced, thermosetting, high-density polymer resin or an extruded polycarbonite resin, which are resistant to ultraviolet and infrared radiation, and which meet the following minimum physical and performance requirements:
Design the base of the unit to mount over the I-beam blockout or to the top of a wood or synthetic blockout, of the beam guide rail.
Submit a certification of compliance, as specified in 106.07, for delineators.
Use paint systems for coating structural steel that are Northeast Protective Coating Committee (NEPCOAT) approved and listed on the QPL. Use the appropriate paint type for the application as follows:
Ensure that the primer is tinted to contrast with the base metal. Use white or an approved color that contrasts with the prime and finish coats for the intermediate coat.
Use the finish color coat noted on the Plans. When the colors Lake Blue, Foliage Green, Brown, or Black are specified, match the color chips of FED-STD-595B as specified in Table 912.01.01-1.
| Table 912.01.01-1 – Finish Coat Colors for Structural Steel |
|
| Color | Chip Number |
| Lake Blue | 25189 |
| Foliage Green | 24172 |
| Brown | 30111 |
| Black | 27038 |
Before using paint, submit each lot to the ME for quality assurance testing and approval. The ME will verify that the pigment content, total solids, and infrared curve match that of the initial qualifying material. Do not use paint until the ME has approved the paint lot.
Use aluminum paint conforming to AASHTO M 69, Type II. Submit certifications of compliance as specified in 106.07.
Use coal tar epoxy-polyamide paint that conforms to SSPC-Paint No. 16 and is black or dark red in color. Submit certifications of compliance as specified in 106.07.
To stain concrete, use a penetrating stain that is a single component, water-based, thermoplastic acrylic emulsion that carries its color and water repellent protection into the concrete. Ensure that the stain conforms to the requirements in Table 912.01.04-1.
| Table 912.01.04-1 Requirements for Concrete Stain | ||
| Property | Test Method | Requirement |
| Solids By Weight | ASTM D 2369 | 57 ± 2 percent |
| Gloss | ASTM G 23 | Flat |
| Viscosity | ASTM D 562 | 70 - 75 Krebs Units |
Submit certifications of compliance as specified in 106.07.
Apply hot-dip galvanized coating to iron and steel plates, pipe, tube, and structural shapes according to ASTM A 123.
Apply hot-dip galvanized coating to iron and steel hardware according to ASTM A 153.
Repair hot dipped galvanized coating on iron and steel plates, pipe, tube, structural shapes, and hardware according to ASTM A 780.
For concrete waterproofing, use epoxy-resin that conforms to ASTM C 881, Type 7, Grade 1, 2, or 3, Class D, E, or F, and is listed on the QPL. Ensure that the color is gray to match the color of the adjacent concrete.
Submit certifications of compliance as specified in 106.07.
For use below ground level, use an asphalt waterproofing conforming to ASTM D 449, Type I. For use above ground level, use an asphalt waterproofing conforming to ASTM D 449, Type II or III. Use a primer conforming to ASTM D 41.
Formulate a color coating with a pure acrylic vehicle that is durable, weather resistant, and suitable for use on bituminous surfaces. Use lusterless brown tint matching Federal chip No. 30277.
| Table 912.03.01-1 Composition of Epoxy Resin | ||
|
Percent By Weight | |
| Pigment Composition | Minimum | Maximum |
| White: | ||
| Titanium Dioxide1 (ASTM D 476, Type II or III) | 18.0 | 25.0 |
| Epoxy Resin | 75.0 | 82.0 |
| Yellow: | ||
| Organic Non-Lead Yellow | 7.0 | 8.0 |
| Epoxy Resin | 75.0 | 79.0 |
| Titanium Dioxide (ASTM D 476, Type II or III) | 14.0 | 17.0 |
| 1 | Use titanium dioxide for the entire pigment composition for white epoxy. |
| Table 912.03.01-2 Gradation Requirements for Large Glass Beads |
|
| Sieve Size | Percent Passing by Weight1 |
| No.10 | 100 |
| No. 12 | 95 – 100 |
| No. 14 | 80 – 95 |
| No. 16 | 10 – 40 |
| No. 18 | 0 – 5 |
| No. 20 | 0 - 2 |
| 1 | According to ASTM D 1214 |
For long-life traffic markings, use either preformed or hot extruded thermoplastic conforming to AASHTO M 249, except that for preformed thermoplastic, the minimum thickness requirement is 90 mils. Use beads conforming to AASHTO M 247, Type 1, with a moisture resistant coating. Ensure that glass beads do not contain more than 200 ppm of lead, 200 ppm of antimony, or 200 ppm of arsenic.
Submit certifications of compliance, as specified in 106.07, for each batch of materials used on the contract.
Use raised pavement markers (RPMs) made of ductile iron castings with a 2-way, snow-plowable, replaceable prismatic reflector conforming to the following requirements:
| Table 912.03.03-1 Requirements for Lenses | |
| Property | Requirement |
| Nominal Dimensions | 4 × 2 × 0.5 inch |
| Slope of reflecting surface | 30 to 35 degrees |
| Area of each reflecting surface | 1.44 to 1.87 square inches |
Submit a certification of compliance as specified in 106.07.
For temporary traffic stripes, use latex traffic paint that is a fast-drying white, or non-lead yellow, ready-mixed pigmented binder emulsified in water and capable of anchoring reflective glass beads that are separately applied. Ensure that the color matches FED-STD-595B color chip No. 33538 for yellow and No. 37886 for white. Ensure that the paint has a maximum no-track time of 120 seconds when applied in a wet film thickness of 15 ± 1 mil, at 140 °F, and with 12 pounds per gallon of glass beads. In addition, ensure that the finished product meets the following:
Use glass beads conforming to AASHTO M247, Type 1, with a moisture resistance coating. Ensure that glass beads do not contain more than 200 ppm of lead, 200 ppm of antimony, or 200 ppm of arsenic.
If requested by the RE, provide a certification of compliance, as specified in 106.07, for latex or glass beads.
| Table 912.04.02-1 Requirements for Temporary Pavement Tape | ||
| Property | White | Yellow |
| Minimum Specific Luminance (mcd/sq foot/foot-candles) ASTM D 40611 | 500 | 300 |
| Minimum Tensile Stress (psi)2 ASTM D 638 | 40 | 40 |
| FED-STD-595B Color Chip No. | 37778 | 33538 |
| 1 | Use an entrance angle of 88.76° and an observation angle of 1.05°. |
| 2 | Perform tensile stress testing with a testing speed of 6 inches per minute. |
Provide temporary pavement markers that have a maximum width of 4 inches perpendicular to traffic and a maximum height of 3/4 inch. Mold marker castings using acrylonitrile butadiene styrene, acrylic, polycarbonate, or high impact polystyrene of the same color as the retroreflective lens.
Use either mono-directional white or bi-directional yellow retroreflective lenses as shown on the Plans. Ensure that the lenses used for the retroreflective material are molded of methylmethacrylate conforming to ASTM D 788, PMMA0131V0, or PMMA0231V0 and meet the retroreflectance values specified in Table 912.04.03-1:
| Table 912.04.03-1 Retroreflectance Requirements for Temporary Pavement Markers | |||
| Observation Angle (Degrees) |
Entrance Angle (Degrees) |
White (mcd/foot-candles) |
Yellow (mcd/foot-candles) |
| 0.2 | 0.0 | 2.0 | 1.4 |
| 0.2 | 20 | 1.0 | 0.7 |
Ensure that the underside of the marker is precoated with a pressure sensitive adhesive to bond the marker to the roadway surface and is capable of withstanding traffic immediately after installation and for the duration of the intended service. Ensure that markers are capable of being removed without damage to the underlying surface.
If requested by the RE, provide a certification of compliance, as specified in 106.07, for temporary pavement markers.
Fabricate rail element according to AASHTO M 180, Class A, Type I in Table 2. Ensure that the weight of the zinc coating conforms to AASHTO M 180, Type I in Table 1.
Notify the ME at least 3 days before shipment to the Project for inspection at the supplier’s yard. Provide mill certifications to the ME at the time of inspection.
Use non-gating, guide rail end treatments that are NCHRP 350 tested, test level 3 (TL-3), approved and are listed on the QPL. Ensure that the components of the end treatment comply with the NCHRP 350 approved end treatment details.
Notify the ME at least 3 days before shipment to the Project for inspection at the supplier’s yard. Provide mill certifications to the ME at the time of inspection.
For steel posts and blockouts, use structural steel conforming to ASTM A 709, Grade 36, that is galvanized according to ASTM A 123.
Use wood timber blockouts and posts as specified in 915.01.
Use synthetic routed blockouts that are NCHRP 350 tested, test level 3 (TL-3), approved and are listed on the QPL. Ensure that the name of the manufacturer and model number are stamped on each blockout and that the blockouts are of the same material and dimensions as the spacers that were NCHRP tested.
Notify the ME at least 3 days before shipment to the Project for inspection at the supplier’s yard. Provide mill certifications for steel components to the ME at the time of inspection. Provide certifications of compliance, as specified in 106.07, for wood and synthetic components.
For rub rail, use steel channels or bent plate of structural steel conforming to ASTM A 36 and galvanized according to ASTM A 123.
Notify the ME at least 3 days before shipment to the Project for inspection at the supplier’s yard. Provide mill certifications to the ME at the time of inspection.
Ensure that connections or splices, nuts, bolts, washers, and plates conform to AASHTO M 180, except as follows:
Notify the ME at least 3 days before shipment to the Project for inspection at the supplier’s yard. Provide mill certifications to the ME at the time of inspection.
Ensure that the materials for chain-link fence conform to AASHTO M 181. Submit certifications of compliance, as specified in 106.07, for fence materials. Attach mill certification to the certification of compliance.
Ensure that the materials for caution fence conform to the following:
Ensure that the materials for snow fence conform to the following:
Submit certifications of compliance, as specified in 106.07, for fence materials.
Fabricate steel railing from structural steel as specified in 906.01. Construct welds according to the requirements of AWS D1.1 Structural Welding Code. Use bolts and bolting materials as specified in 908.01. When specified, paint as specified in 906.06 or galvanize as specified in 912.02.01. Submit certifications of compliance, as specified in 106.07 and copies of mill certifications.
Fabricate aluminum railing from aluminum components as specified in Table 913.03.02-1. Construct welds according to the requirements of ANSI/AWS D1.2 Structural Welding Code - Aluminum. Use bolts and bolting materials as specified in 908.01. When specified, paint as specified in 906.06. Submit certifications of compliance, as specified in 106.07, and copies of mill certifications.
| Table 913.03.02-1 Aluminum Alloys for Railings | ||
| Component | Test Method | Alloy and Temper |
| Castings, Sand | ASTM B 26 | 356.0-F or 356.0-T6 |
| Die Castings, Permanent Mold | ASTM B 108 | 356.0-T6 |
| Extruded Bars, Rods, Shapes, and Pipe | ASTM B 221 | 6061-T6 |
| Pipe | ASTM B 241 | 6061-T6 |
| Plates and Sheets | ASTM B 209 | 6061-T6 |
| Rolled Shapes, Rods, and Bars | ASTM B 211 | 6061-T6 |
Use preformed joint fillers conforming to AASHTO M 33 or AASHTO M 213. For concrete pavement applications, punch holes in preformed joint filler to admit the dowels. Provide the filler for each joint in a single piece for the full depth and width required for the joint. If the RE approves the use of more than 1 piece for a joint, fasten the abutting ends securely, and hold to shape by stapling or other means of means of positive fastening.
Submit a certification of compliance, as specified in 106.07, for joint filler.
For sealing joints and cracks in HMA and concrete pavements, use a hot-poured joint sealer that is listed on the QPL and conforms to ASTM D 6690. Use the following types in the listed applications:
For concrete pavements, use cold-poured joint sealer that is listed on the QPL and conforms to ASTM D 5893, Type SL, except that ultimate elongation is required to be a minimum of 1200 percent.
In vertical applications, use cold-poured joint sealers that are listed on the QPL and conform to ASTM D 5893, Type NS, with a minimum ultimate elongation of 600 percent. If recommended by the manufacturer, apply primer before applying the sealer.
Use backer rod in conjunction with cold-poured joint sealer that conforms to ASTM D 5249, Type 1. Use backer rod with a width that is at least 25 percent greater than the width of the pavement joint or crack. Ensure that the backer rod is clean and dry at the time of installation.
Submit a certification of compliance, as specified in 106.07, for joint sealers and backer rods. Attach test results to the certification. The ME will randomly sample joint sealers at the source of manufacture or at the work site.
For longitudinal cold joints in HMA paving, use polymerized joint adhesive that is a hot-applied asphaltic joint adhesive listed on the QPL and conforms to the requirements in Table 914.03-1:
| Table 914.03-1 Requirements for Polymerized Joint Adhesive |
||
| Property | Test Method | Requirement |
| Cone Penetration, 25 °C | ASTM D 5329 | 60-100 |
| Flow, 60 °C | ASTM D 5329 | 5 mm maximum |
| Resilience, 25 °C | ASTM D 5329 | 30% minimum |
| Ductility, 4 °C | ASTM D 113 | 30 cm minimum |
| Tensile Adhesion, 25 °C | ASTM D 5329 | 500% minimum |
| Softening Point | ASTM D 36 | 77 °C minimum |
| Asphalt Compatibility | ASTM D 5329 | Pass |
Ensure that the polymerized joint adhesive has a viscosity at the recommended pour temperature to allow for proper application of the material. Obtain documentation of recommended pour temperature and safe heating temperature for the material from the manufacturer. Submit a certification of compliance, as specified in 106.07, for polymerized joint adhesive. Attach test results to the certification. The ME will randomly sample joint adhesive at the source of manufacture or at the work site.
| Table 914.04-1 Minimum Lengths of Samples for Testing | |
| Sealer Size Width (w) in inches | Minimum Length (inches) |
| w < 2 | 84 |
| 2 ≤ w < 3 | 66 |
| 3 ≤ w < 4 | 50 |
| w ≥ 4 | 42 |
| Table 914.05-1 Tests for Neoprene Strip Seal Gland | ||
| Property | Test Method | Requirement |
| Tensile strength, minimum psi | ASTM D 412 | 2000 |
| Elongation at break, minimum % | ASTM D 412 | 250 |
| Hardness, Type A durometer | ASTM D 2240 | 60 ± 5 |
| Oven aging, 70 hours at 212 °F | ||
| Tensile strength loss, maximum % Elongation loss, maximum % Hardness, Type A durometer, points change |
ASTM D 573 | 20 20 0 to +10 |
| Ozone resistance 20% strain, | ||
| 300 ppm in air, 70 hours at 104 °F |
ASTM D 1149 | No Cracks |
| Oil swell, ASTM oil No. 3 | ||
| 70 hours at 212 °F Weight change, maximum % |
ASTM D 471 | +45 |
| Table 914.05-2 Requirements for Strip Seal Adhesive | |
| Property | Requirement |
| Average weight per gallon | 8 ± 1 pounds |
| Solids content by weight | 65 percent (minimum) |
| Temperature range at which material is in fluid from | 5 to 120 °F |
| Film strength (ASTM D 412) | 2000 pounds per square inch (minimum) |
| Elongation | 250 percent (minimum) |
| Table 914.06-1 Tests for Neoprene Strip Seals | ||
| Property | Test Method | Requirement |
| Tensile strength, minimum psi | ASTM D 412 | 2000 |
| Elongation at break, minimum % | ASTM D 412 | 250 |
| Hardness, Type A durometer | ASTM D 2240 | 55 to 70 |
| Compression Set at 72 hr at 212 °F, maximum % | ASTM D 395 | 40 |
Manufacture sawn timber posts, timber spacers, and routed timber spacers from Southern pine or Douglas fir with extreme fiber stress in bending in excess of 1200 pounds per square inch, as assigned according to Southern Pine Inspection Bureau or West Coast Lumber Inspection Bureau grading rules. The manufacturer may rough saw or dress timber posts, timber spacers, and routed timber. Treat timber as specified in 915.05.
Submit certification of compliance as specified in 106.07.
In the manufacture of round timber piling, use Southern pine or Douglas fir conforming to AASHTO M 168 and ASTM D 25, except that untreated piles having smooth, tight bark need not be peeled. Treat piling as specified in 915.05.
Submit certification of compliance as specified in 106.07.
Manufacture sheet piling using Southern pine or Douglas fir No. 2 or better, dressed on 4 sides. Manufacture sheet piling to be tongue and grooved or grooved for splines. Treat sheet piling as specified in 915.05.
Submit certification of compliance as specified in 106.07.
Use dimension lumber, timber, glued-laminated timber, and decking for structures that conform to AASHTO M 168 with the following modifications:
Submit certification of compliance as specified in 106.07.
Treat wood species according to AASHTO M 133 and AWPA Standards C1, C2, C3, C14, C18, and C28, as summarized in Table 915.05-1, Table 915.05-2, and Table 915.05-3.
| 915.05-1 Treatment for Timber Posts | |||
| Type of Wood |
Location/ Environment |
Allowable Treatments |
AWPA Standard Reference for Minimum Retention Level |
| Southern Pine | Soil or Fresh Water | CCA or Pentachlorophenol | C14 |
| Douglas Fir | Soil or Fresh Water | ACZA | C14 |
| 915.05-2 Treatment for Round Timber Piles | |||
| Type of Wood |
Location/ Environment |
Allowable Treatments |
AWPA Standard Reference for Minimum Retention Level |
| Southern Pine | Soil or Fresh Water | CCA | C14 |
| Southern Pine | Marine | CCA | C14 |
| Douglas Fir | Soil or Fresh Water | ACZA | C14 |
| Douglas Fir | Marine | ACZA | C14 |
| 915.05-3 Treatment for Timber Sheet Piling and Timber for Structures |
|||
| Type of Wood |
Location/ Environment |
Allowable Treatments |
AWPA Standard Reference for Minimum Retention Level |
| Southern Pine | Soil or Fresh Water | CCA, or Pentachlorophenol | C14 |
| Southern Pine | Marine | CCA | C14 |
| Douglas Fir | Soil or Fresh Water | ACZA | C14 |
| Douglas Fir | Marine | ACZA | C14 |
Notify the ME at least 14 days before treating timber. If directed by the ME, perform an assay to determine the retention of preservative according to AASHTO M 133. Submit certification of compliance as specified in 106.07. Attach the assay report to the certification.
Use timber connectors and hardware that conform to Section 16 of the AASHTO LRFD Bridge Construction Specifications. Galvanize timber connectors and hardware as specified in 912.02.01.
Submit a certification of compliance as specified in 106.07.
Provide fiberglass reinforced plastic lumber (FRPL) that is listed on the QPL and conforms to the following material properties:
| Table 916.01-1 Plastic Material Properties | |||
| Property | Test Method | Component | Requirement |
| Density | ASTM D 792 | Skin | 55-63 lbs/ft3 |
| Density | ASTM E 1547 | Core | 34-48 lbs/ft3 |
| Water Absorption | ASTM D 570 | Skin | 2 hrs: < 1.0% wt. increase 24 hrs: < 3.0% wt. increase |
| Brittleness | ASTM D 746 | Skin | No break at −40 °F |
| Impact Resistance | ASTM D 746 | Skin | Greater than 4 ft-lbs/inch |
| Hardness | ASTM D 2240 | Skin | 44-75 (Shore D) |
| Abrasion Cycles = 10,000 Wheel = CS17 Load = 2.2 lbs |
ASTM D 4060 | Skin | Weight Loss: < 0.03 g Wear Index: 2.5 to 3.0 |
| Chemical Resistance Sea Water Gasoline No. 2 Diesel |
ASTM D 543 | Skin/Core | < 1.5% weight increase < 7.5% weight increase < 6.0% weight increase |
| Tensile Properties | ASTM D 638 | Skin/Core | Minimum 500 psi at break |
| Compressive Modulus | ASTM D 695 | Skin/Core | Minimum 40 ksi |
| Coefficient of Friction | ASTM F 489 | Skin | Maximum 0.25, wet or dry |
| Nail Pull-Out | ASTM D 1761 | Skin/Core | Minimum 60 lbs |
| Table 916.01-2 Dimensions and Tolerances | ||
| Plastic Timber | Dimension | Tolerance |
| Length | Per order | ±6 in |
| Width | As shown on Plans | ±0.25 in |
| Height | As shown on Plans | ±0.25 in |
| Corner Radius | 1.75 inches | ±0.25 in |
| Outer Skin Thickness | 0.1875 inches | ±0.125 in |
| Distance from outer surface to rebar elements | 1.5 inches | ±0.625 in |
| Straightness (gap, bend or bulge inside lying on a flat surface) | < 1.5 in per 10 ft length | |
| Table 916.01-3 Structural Properties of 10 and 12-inch FRPL | ||
| Property | 10 × 10-inch | 12 × 12-inch |
| Modulus of Elasticity, minimum1 | 521 ksi | 405 ksi |
| Stiffness, E.I., minimum1 | 4.05E+08 lb-in2 | 6.58E+08 lb-in2 |
| Yield Stress in Bending, minimum1 | 5.8 ksi | 4.4 ksi |
| Weight | 30-37 lbs/ft | 42-51 lbs/ft |
| 1 | Determine the modulus of elasticity, stiffness, and yield stress according to ASTM D 790 and the following: | ||
| a. | Use a deflection rate of 0.25 inches per minute. | ||
| b. | Use a minimum span length of 12 feet to perform testing on a full size FRPL specimen. | ||
| c. | Use the following equations for calculations: | ||
| 1) | Strain = [6 × (depth of cross-section) × (deflection)] / (span length)2 | ||
| 2) | Calculate the modulus at a strain of 0.01 inches per inch as follows: Modulus of Elasticity = [(load) × (span length)3] / [(48) × (deflection) × (moment of inertia)] |
||
| 3) | Calculate the yield stress from the maximum load reached prior to failure. | ||
| Table 916.01-4 Structural Properties of FRPL Smaller than 10 inches | ||
| Property | Test Method | Requirement |
| Modulus of Elasticity, minimum | ASTM D 6109 | 175,000 psi |
| Flexural Strength | ASTM D 6109 | No fracture at 1800 psi |
| Compressive Strength, minimum | ASTM D 6108 | 1500 psi |
| Compressive Strength Parallel to Grain, minimum | ASTM D 6112 | 1750 psi |
| Compressive Strength Perpendicular to Grain, minimum | ASTM D 6112 | 600 psi |
| Screw Withdrawal, minimum | ASTM D 6117 | 350 lbs |
Submit a certification of compliance, as specified in 106.07, with the test results for the plastic material properties attached.
Provide fiberglass reinforced plastic piles (FRPP) that are listed on the QPL and conform to the following material properties:
| Table 916.02-1 Plastic Material Properties | |||
| Property | Test Method | Component | Requirement |
| Density | ASTM D 792 | Skin | 55-63-lbs/ft3 |
| Density | ASTM E 1547 | Core | 34-48-lbs/ft3 |
| Water Absorption | ASTM D 570 | Skin | 2 hrs: < 1.0% wt. increase 24 hrs: < 3.0% wt. increase |
| Brittleness | ASTM D 746 | Skin | No break at −40 °F |
| Impact Resistance | ASTM D 746 | Skin | Greater than 4 ft-lbs/inch |
| Hardness | ASTM D 2240 | Skin | 44-75 (Shore D) |
| Abrasion1 | ASTM D 4060 | Skin | Weight Loss: < 0.03g Wear Index: 2.5 to 3.0 |
| Chemical Resistance in Sea Water in Gasoline in No. 2 Diesel |
ASTM D 543 | Skin/Core | < 1.5% weight increase < 7.5% weight increase < 6.0% weight increase |
| Tensile Properties | ASTM D 638 | Skin/Core | Minimum 500 psi at break |
| Compressive Modulus | ASTM D 695 | Skin/Core | Minimum 40 ksi |
| Coefficient of Friction | ASTM F 489 | Skin | Maximum 0.25, wet or dry |
| Nail Pull-Out | ASTM D 1761 | Skin/Core | Minimum 60 lbs |
| 1 | The duration of the abrasion test will be 10,000 cycles using a CS17 wheel with a load of 2.2 pounds. |
| Table 916.02-2 Dimensions and Tolerances | ||
| FRPP | Dimension | Tolerance |
| Length | Per order (105 ft max) | +6.0 in / −0.0 in |
| Outside Diameter | 10.000 in / 12.875 in / 16.250 in | ±0.375 in |
| Outer Skin Thickness | 0.1875 in / 0.1875 in / 0.1875 in | ±0.125 in |
| Distance from outer surface to rebar elements (FRPP) | 0.880 in /0.750 in / 1.250 in | ±0.375 in |
| Straightness (gap, bend, or inside lying on a flat surface) | < 1.5 in per 10 feet | |
| Table 916.02-3 Structural Properties | |||
| Member Size | 10-inch OD | 13-inch OD | 16-inch OD |
| Modulus of Elasticity,1 minimum | 458 ksi | 1054 ksi | 997 ksi |
| Stiffness, EI, minimum | 2.25E+09 lb-in2 | 1.48E+09 lb-in2 | 3.21E+09 lb-in2 |
| Yield Stress in Bending, minimum | 4.3 ksi | 8.6 ksi | 7.8 ksi |
| Bending Moment at Yield, minimum | 422 in-kips | 1860 in-kips | 3168 in-kips |
| Weight | 24-29 lbs/ft | 45-55 lbs/ft | 66-81 lbs/ft |
| 1 | Determine the modulus of elasticity, stiffness, and yield stress according to ASTM D 790 and the following: | ||
| a. | Use a deflection rate of 0.25 inches per minute. | ||
| b. | Use a minimum span length of 12 feet to perform testing on a full size FRPL specimen. | ||
| c. | Use the following equations for calculations: | ||
| 1) | Strain = [6 × (depth of cross-section) × (deflection)] / (span length)2 | ||
| 2) | Calculate the modulus at a strain of 0.01 inches per inch as follows: Modulus of Elasticity = [(load) × (span length)3] / [(48) × (deflection) × (moment of inertia)] |
||
| 3) | Calculate the yield stress from the maximum load reached prior to failure. | ||
| Where: | |
| M = bending moment at yield (in-lbs). | |
| f = yield stress in bending (lb/in2). | |
| I = moment of inertia of cross-section (in4). | |
| c = distance from neutral axis to point where stress is desired (inches). | |
Submit a certification of compliance, as specified in 106.07, with the test results for the plastic material properties of the FRPP attached.
Provide fiberglass-concrete composite piles (FCCP) consisting of a hollow composite tube, a concrete core, and a durable coating. Ensure that the FCCP is listed on the QPL and conforms to the following material properties:
| Table 916.03-1 Tolerances for Composite Tubes | |
| Property | Tolerance |
| Minimum Length | +1 foot, −0 inches |
| Maximum Sweep1 | 0.08% of total length |
| Ends out of Square | 1.0% of diameter |
| 1 | Sweep is the deviation from straightness, measured at several points around the pile circumference while the pile is not subjected to bending stresses. |
| Table 916.03-2 Requirements for Fiberglass Composite Tubes | |
| Class | RTRP (reinforced thermosetting resin pipe) |
| Type | Type I (filament wound) |
| Grade | Grade 1 (glass fiber reinforced epoxy resin pipe) Grade 2 (glass fiber reinforced polyester resin pipe), or vinylester resin |
| Table 916.03-3 Physical Properties of Composite Tube | |||||
| Nominal Tube Diameter | |||||
| Stress Direction | Test Method | 12-inch | 14-inch | 16-inch | |
| Elastic Moduli (ksi) | axial-tensile | ASTM D 2105 | 4000 | 3350 | 2800 |
| axial-compressive | ASTM D 6951 | 2800 | 2350 | 1900 | |
| hoop-tensile | ASTM D 1599 | 4500 | 4500 | 4500 | |
| Strength (ksi) | axial-tensile | ASTM D 2105 | 70 | 58 | 49 |
| axial-compressive | ASTM D 6951 | 39 | 35 | 29 | |
| hoop-tensile | ASTM D 1599 | 35 | 35 | 35 | |
| Wall thickness | 0.200 | 0.210 | 0.230 | ||
| 1 | Modify ASTM D 695 as follows: | |
| 1.1 | Test Specimen Dimensions: Diameter is equal to full diameter of tube being tested and Height is equal to 1 inch. | |
| 1.2 | Do not use the compression tool described in ASTM D 695. Center the specimen in the compression testing machine and place a steel plate on top of the specimen to distribute the load from the test machine. | |
| Table 916.03-4 Allowable Degradation of Coated Composite Tube1 | ||
| Property | Test Method | Maximum Allowable Loss |
| Axial Tensile Strength Loss | ASTM D 2105 | 10% |
| Axial Compressive Strength Loss | ASTM D 6952 | 10% |
| Hoop Tensile Strength Loss | ASTM D 1599 | 10% |
| Color Film Adhesion Loss | ASTM D 4541 | 10% |
| 1 | After exposure to light and salt spray for a duration of 3600 hours | |
| 2 | Modify ASTM D 695 as follows: | |
| 2.1 | Test Specimen Dimensions: Diameter is equal to full diameter of tube being tested and Height is equal to 1 inch. | |
| 2.2 | Do not use the compression tool described in ASTM D 695. Center the specimen in the compression testing machine and place a steel plate on top of the specimen to distribute the load from the test machine. | |
Submit a certification of compliance, as specified in 106.07, with the test results for the fiberglass composite material properties and the concrete infill compressive strengths of the FCCP attached.
Provide topsoil containing no stones, lumps, roots, or similar objects larger than 2 inches in any dimension. Ensure that topsoil meets the following quality standards:
| Table 917.01-1 Requirements for pH of Topsoil | |
| pH Range | Acceptability/ Remediation |
| pH < 4.1 | Topsoil is unacceptable. |
| 4.1 ≤ pH < 5.8 | Add pulverized lime to increase the pH to 6.5 before use. |
| 5.8 ≤ pH < 7.0 | Topsoil is acceptable. No remediation needed. |
| 7.0 ≤ pH < 7.2 | Decrease pH to at least 6.8 before use.1 |
| pH ≥ 7.2 | Topsoil is unacceptable.2 |
| 1 | Obtain Departmental approval of remediation method to lower pH. |
| 2 | The Department may approve the use of existing topsoil stripped from the Project Limits with a pH greater than 7.2. |
| Table 917.01-2 Particle Size Distribution for Topsoil | |
| Particle Size | Percent |
| Sand (2.0 mm to 0.05 mm) | 40 - 80 |
| Silt (0.05 mm to 0.005 mm) | 0 - 30 |
| Clay (0.005 mm and smaller) | 10 - 301 |
| 1 | If more than 50 percent of the sand portion is larger than 0.5 millimeters, the allowable range for clay is 15 to 30 percent. |
The Department will sample topsoil at a rate of at least 1 sample per source to ensure conformance to the requirements.
Use composted sewerage sludge consisting of a stabilized, screened mixture of wood chips and sewerage sludge processed according to NJDEP. Obtain composted sewerage sludge from facilities operating in compliance with a New Jersey Pollutant Discharge Elimination System Permit or under an approved NJDEP Memorandum of Agreement. Ensure that the compost product is registered with the New Jersey Department of Agriculture according to the New Jersey Commercial Fertilizer and Soil Conditioner Act of 1970.
Use composted sewerage sludge that has a minimum organic content of 50 percent by weight and a pH of 6.0 or greater. If the average water content of the stabilized composted sludge exceeds 55 percent by weight, correct for the excess water content.
For shipments of composted sewerage sludge, provide delivery tickets with the certified weight and the name of the producer or supplier. The Department may take samples to verify the organic content, pH, and water content.
Use compost that is a stable, humus-like organic material produced by the biological and biochemical decomposition of source-separated compostable materials. Materials used in producing compost may include leaves, yard trimmings, food scraps, food processing residuals, manure, other agricultural residuals, forest residues, bark, and paper. Do not add non-organic materials such as sand, soil, or glass to the compost. Ensure that the compost contains no heavy metals or substances toxic to plants and has no objectionable odor. Ensure that the raw materials have decomposed sufficiently to be unrecognizable and that the compost meets the requirements of Table 917.02.02-1.
| Table 917.02.02-1 Requirements for Compost | ||
| Property | Test Method | Requirement |
| Organic Content, minimum | ASTM D 2974 | 30% |
| Moisture Content | ASTM D 2974 | 35 - 60% |
| Particle Size (percent passing the 1" sieve) | AASHTO T 27 | 100% |
| pH | TMECC 04.111 | 5.5 - 8.0 |
| Maturity | Solvita Maturity Test | 6 or higher |
| Soluble Salt, maximum | Determined using 1 part compost to 1 part distilled water | 4.0 mmhos/cm |
| 1 | Electrometric pH determination according to the Test Methods for the Examination of Composting and Compost (TMECC) by the US Composting Council |
Provide compost that is either commercially packaged or in bulk form. Obtain compost material from NJDEP regulated, permitted or approved facilities. For shipments of compost, provide delivery tickets with the certified weight and the name of the producer or supplier. The Department may take samples to verify the organic content, pH, and water content.
Use fertilizer for establishing turf that has a commercial designation of 10-20-10, or use any 1-2-1 ratio fertilizer containing a minimum of 5 percent nitrogen, 10 percent available phosphoric acid, and 5 percent soluble potash.
If the fertilizer is to be applied with mechanical spreader in dry form, ensure that a minimum of 75 percent passes a No. 8 sieve, a minimum of 75 percent is retained on a No. 16 sieve, and the maximum free moisture content is 2 percent.
Use fertilizer for establishing sod that is any 1-2-2 ratio fertilizer containing a minimum of 5 percent nitrogen, 10 percent available phosphoric acid, and 10 percent soluble potash.
With each delivery of fertilizer, provide a delivery ticket showing the weight and a certified chemical analysis of the composition of the fertilizer from the manufacturer.
Use pulverized limestone composed of more than 85 percent calcium and magnesium carbonates equivalent to more than 40 percent calcium and magnesium oxides.
With each delivery of pulverized limestone, provide a delivery ticket indicating its weight and a certified analysis of the chemical composition and gradation, including calcium and magnesium oxide equivalents.
Provide grass seed mixtures that are not older than the sell by date and that conform to the requirements specified in Table 917.05.01-1 through Table 917.05.01-7.
| Table 917.05.01-1 Type A Grass Seed Mixture | |||
| Kind of Seed | Minimum Purity, Percent | Minimum Germination, Percent | Percent of Total Weight of Mixture |
| Kentucky Bluegrass | 85 | 75 | 20 |
| Red Fescues (Creeping or Chewings) | 95 | 80 | 35 |
| Kentucky 31 | 95 | 80 | 20 |
| Redtop | 92 | 85 | 10 |
| Perennial Ryegrass | 98 | 85 | 10 |
| White Clover | 97 | 90 | 5 |
| Table 917.05.01-2 Type A-3 Grass Seed Mixture | |||
| Kind of Seed | Minimum Purity, Percent | Minimum Germination, Percent | Percent of Total Weight of Mixture |
| Tall Fescue | 95 | 80 | 60 |
| Kentucky Bluegrass | 85 | 75 | 10 |
| Chewing or Hard Fescue | 95 | 85 | 20 |
| Perennial Ryegrass | 98 | 85 | 10 |
| Table 917.05.01-3 Type A-4 Grass Seed Mixture | |
| Kind of Seed | Percent of Total Weight of Mixture |
| Spreading Fescue | 30 |
| Chewing or Hard Fescue | 30 |
| Kentucky Bluegrass | 30 |
| Perennial Rye | 10 |
| Table 917.05.01-4 Type B Grass Seed Mixture | |||
| Kind of Seed | Minimum Purity, Percent |
Minimum Germination, Percent |
Percent of Total Weight of Mixture |
| Redtop | 92 | 85 | 10 |
| Red Fescues (Creeping or Chewings) | 95 | 80 | 45 |
| Blackwells Switchgrass | 95 | 85 | 15 |
| Weeping Love Grass | 95 | 85 | 10 |
| Perennial Ryegrass | 98 | 85 | 5 |
| Kentucky 31 | 95 | 80 | 15 |
| Table 917.05.01-5 Type D Grass Seed Mixture | |||
| Kind of Seed | Minimum Purity, Percent |
Minimum Germination, Percent |
Percent of Total Weight of Mixture |
| Kentucky Bluegrass | 85 | 75 | 50 |
| Red Fescues (Creeping or Chewings) | 95 | 85 | 35 |
| Redtop | 92 | 85 | 5 |
| Perennial Ryegrass | 95 | 80 | 10 |
| Table 917.05.01-6 Type F Grass Seed Mixture | ||
| Kind of Seed | Minimum Purity, Percent |
Minimum Germination, Percent |
| Perennial Ryegrass | 95 | 90 |
| Table 917.05.01-7 Type W Wetland Grass Seed Mixture | |||
| Kind of Seed | Minimum Purity, Percent |
Minimum Germination, Percent |
Percent of Total Weight of Mixture |
| Blackwell Switchgrass (Panicum virgatum) | 95 | 85 | 25 |
| Virginia Wildrye (Elymus virginicus) | 95 | 85 | 25 |
| Red Top (Agrostis alba) | 92 | 85 | 25 |
| Annual Rye (Lolium multiflorum) | 85 | 85 | 25 |
Provide wildflower seeds that conform to the requirements in Table 917.05.02-1.
| Table 917.05.02-1 Wildflower Seed Mixture | |
| Kind of Seed | By Weight Per Acre |
| Coreopsis lanceolata | 40 oz. |
| Rudbeckia hirta | 40 oz. |
| Echinacea purpurea | 79 oz. |
| Festuca ovina | 64 oz. |
| Total | 223 oz. |
With each shipment of seed mixture, provide a certified weigh ticket and an analysis of the composition, purity, germination, germination test date, and sell by date of the seed mixture, certified by the seed house.
The Department may sample and test seed according to the New Jersey State Seed Law and with the Rules and Regulations for Testing Seeds adopted by the Association of Official Seed Analysts.
Use straw that is derived from threshed, unrotted stalks of oat, wheat, rye, or barley and that is relatively free from seeds, noxious weeds, and other foreign material.
Use wood cellulose fiber containing no growth or germination inhibiting materials. With each shipment, provide a manufacturer’s certification indicating composition and weight.
Use shredded wood mulch produced by a shredding machine that produces a wood particle varying in size from 5/8 to 3 inches, or use wood chip mulch produced by a wood chipping machine that produces a wood particle varying in size from 5/8 to 3 inches.
Ensure that the shredded wood mulch and wood chip mulch are clean, hard, and not decomposed and contain no leaves, twigs, wood shavings, dirt, stones, toxic material, or other foreign material. Do not use wood pallets, chemically treated wood, or materials from building demolition to produce mulch. Ensure that the pH is above 3.0.
Submit samples of shredded or wood chip mulch before delivery to the Project. The Department will visually inspect each shipment of shredded or wood chip mulch. Obtain the Department’s approval before using wood mulch that is produced within the Project Limits.
With each shipment, provide a delivery ticket and a certification that the material was not derived from wood pallets, chemically treated wood, or material from building demolition.
Use shredded hardwood bark mulch derived from the bark of hardwood trees. Ensure that it contains no leaves, twigs, wood shavings, dirt, stones, weed seeds, toxic material, or other foreign material. With each shipment, provide a delivery ticket indicating source and weight of the shredded hardwood bark.
For stone mulch, use coarse aggregate No. 4, as specified in 901.03.01. Before use, submit a sample for the Department’s approval of size and color. With each shipment, provide a delivery ticket indicating source and weight of the stone mulch.
For gravel mulch, use an uncrushed washed gravel No. 4, as specified in 901.03.02. Before use, submit a sample for the Department’s approval of size and color. With each shipment, provide a delivery ticket indicating source and weight of the gravel mulch.
Provide 1 of the following tackifiers for straw mulch:
Provide Type 1 Mats conforming to the following:
Provide a machine-produced mat of organic, biodegradable mulch material, such as straw, coconut fiber, or other approved materials that is covered on both sides with a 1/2 × 1/2-inch photodegradable polypropylene mesh netting. Ensure that the mesh contains an accelerant that will cause breakdown of the mesh within 6 months. Ensure that the Type 2 mat conforms to the property values specified in Table 917.08.02-1.
| Table 917.08.02-1 Requirements for Type 2 Mat | ||
| Property | Test Method | Minimum Requirement |
| Mass per Unit Area of Blanket | ASTM D 5261 | 0.5 lb/yd2 |
| Performance @ shear stress of 1.75 lb/ft2 | ASTM D 6460 | acceptable |
| Breaking Force | ASTM D 5035 | 75 lb/ft |
Provide a machine-produced, 3-dimensional matrix of UV stabilized, pre- or post-consumer, non-degradable synthetic fibers, filaments, nettings, and/or wire mesh designed for permanent and critical hydraulic applications where design discharge velocities and shear stresses exceed the limits of mature, natural vegetation. Ensure that the TRM provides sufficient thickness, strength and void space to allow soil filling or retention and the development of vegetation within the matrix. Ensure that the TRM conforms to the property values specified in Table 917.08.03-1.
| Table 917.08.03-1 Requirements for TRM | ||
| Property | Test Method | Minimum Requirement |
| Thickness | ASTM D 6525 | 0.25 in. |
| Performance @ shear stress of 10.0 lb/ft2 | ASTM D 6460 | acceptable |
| Breaking Force | ASTM D 6818 | 175 lb/ft |
| UV Stability @ 500 hours | ASTM D 4355 | 80% |
Provide a hydraulically applied, flexible erosion control blanket composed of long strand, thermally processed wood fibers, crimped, interlocking fibers, and performance enhancing additives. Ensure that the MBFM requires no curing period, and upon application, forms an intimate bond with the soil surface, creating a continuous, porous, absorbent erosion resistant blanket that allows for rapid germination and accelerated plant growth.
Ensure that the MBFM conforms to the property values specified in Table 917.08.04-1.
| Table 917.08.04-1 Requirements for MBFM | ||
| Property | Test Method | Minimum Requirement |
| Physical | ||
| Mass Per Unit Area | ASTM D 6566 | 11.5 oz/yd2 |
| Thickness | ASTM D 6525 | 0.19 in |
| Percent Light Penetration | ASTM D 6567 | 99% |
| Water Holding Capacity | ASTM WK2652 | 1500% |
| Color (fugitive dye) | Observed | Green |
| Endurance | ||
| Functional Longevity | Observed | 1 yr |
| Performance | ||
| Cover Factor (6 in/hr event) | ECTC Test Method No. 2 | 0.0066 |
| Percent Effectiveness | ECTC Test Method No. 2 | 99.34% |
| Shear Stress | ECTC Test Method No. 3 | 1 lb/ft2 |
Machine cut sod at a uniform soil thickness of 5/8 ± 1/4 inch at the time of cutting. Exclude top growth and thatch when measuring for thickness. Ensure that individual strips of sod are of a uniform width. The Department may reject broken strips and torn or uneven strips. If using strip sod, ensure that the strips of sod are strong enough to support their own weight and retain their size and shape when suspended vertically from the upper 10 percent of the strip. If using rolled sod, ensure that the sod is strong enough to be mechanically laid and adjusted without tearing.
Use sod that is Kentucky Bluegrass blend or Kentucky Bluegrass-fescue blend, inspected and certified by the New Jersey Department of Agriculture. Fasten sod on slopes using pegs of wood lath or similar pieces of wood that are at least 9 inches long. Submit certification at the time of delivery that lists the blend of grass seed used.
| Table 917.10-1 Required Ball Sizes of Shade Trees and Deciduous Shrubs | |||
| Shade Trees | Deciduous Shrubs | ||
| Caliper (inches) | Minimum Diameter (inches) | Height (feet) | Minimum Diameter (inches) |
| 1/2 − 3/4 | 12 | 1 − 1-1/2 | 8 |
| 3/4 − 1 | 14 | 1-1/2 − 2 | 9 |
| 1 − 1-1/4 | 16 | 2 − 3 | 10 |
| 1-1/4 − 1-1/2 | 18 | 3 − 4 | 12 |
| 1-1/2 − 1-3/4 | 20 | 4 − 5 | 14 |
| 1-3/4 − 2 | 22 | 5 − 6 | 16 |
| 2 − 2-1/2 | 24 | 6 − 7 | 18 |
| 2-1/2 − 3 | 28 | 7 − 8 | 20 |
| 3 − 3-1/2 | 32 | 8 − 9 | 22 |
| 3-1/2 − 4 | 38 | 9 − 10 | 24 |
| 4 − 4-1/2 | 42 | 10 − 11 | 26 |
| 4-1/2 − 5 | 48 | ||
| 5 − 5-1/2 | 54 | ||
| Table 917.10-2 Required Ball Sizes of Small Trees | |||
| Height (feet) | Minimum Diameter (inches) | Caliper (inches) | Minimum Diameter (inches) |
| 1-1/2 − 2 | 10 | 3/4 − 1 | 16 |
| 2 − 3 | 12 | 1 − 1-1/2 | 18 |
| 3 − 4 | 13 | 1-1/2 − 1 | 20 |
| 4 − 5 | 15 | 3/4 | 22 |
| 5 − 6 | 16 | 1-3/4 − 2 | 24 |
| 6 − 7 | 18 | 2 − 2-1/2 | 28 |
| 7 − 8 | 20 | 2-1/2 − 3 | 32 |
| 8 − 9 | 22 | 3 − 3-1/2 | 38 |
| 9 − 10 | 24 | 3-1/2 − 4 | 42 |
| 10 − 12 | 26 | 4 − 4-1/2 | 48 |
| 4-1/2 − 5 | 54 | ||
| 5 − 5-1/2 | |||
| Table 917.10-3 Required Ball Sizes of Columnar Conifers | |||
| Regular Growing Type | Rapid Growing Type | ||
| Height (feet) | Minimum Diameter (inches) | Height (feet) | Minimum Diameter (inches) |
| 1 − 1-1/2 | 10 | 1 − 2 | 8 |
| 1-1/2 − 2 | 10 | 2 − 3 | 9 |
| 2 − 3 | 12 | 3 − 4 | 11 |
| 3 − 4 | 13 | 4 − 5 | 12 |
| 4 − 5 | 14 | 5 − 6 | 14 |
| 5 − 6 | 16 | 6 − 7 | 16 |
| 6 − 7 | 18 | ||
| 7 − 8 | 20 | ||
| 8 − 9 | 22 | ||
| 9 − 10 | 24 | ||
| 10 − 12 | 27 | ||
| 12 − 14 | 30 | ||
| 14 − 16 | 33 | ||
| 16 − 18 | 36 | ||
| 18 − 20 | 40 | ||
| Table 917.10-4 Required Ball Sizes of Conifers and Broadleaf Evergreens | |||
| Spreading, Semi-Spreading, and Globe or Dwarf Type |
Conical and Broad Upright Type | ||
| Height (feet) | Minimum Diameter (inches) | Height (feet) | Minimum Diameter (inches) |
| 3/4 − 1 | 8 | 1-1/2 − 2 | 10 |
| 1 − 1-1/4 | 9 | 2 − 3 | 12 |
| 1-1/4 − 1-1/2 | 10 | 3 − 4 | 14 |
| 1-1/2 − 2 | 10 | 4 − 5 | 16 |
| 2 − 2-1/2 | 12 | 5 − 6 | 20 |
| 2-1/2 − 3 | 14 | 6 − 7 | 22 |
| 3 − 3-1/2 | 16 | 7 − 8 | 24 |
| 3-1/2 − 4 | 18 | 8 − 9 | 27 |
| 4 − 5 | 21 | 9 − 10 | 30 |
| 5 − 6 | 24 | 10 − 12 | 34 |
| 6 − 7 | 28 | 12 − 14 | 38 |
| 7 − 8 | 32 | 14 − 16 | 42 |
| 8 − 9 | 36 | 16 − 18 | 46 |
| 18 − 20 | 50 | ||
| Table 917.10-5 Container Sizes | ||
| Container | Minimum Diameter (inches) | Minimum Depth (inches) |
| 4" | 4 | 4 |
| No. 1 | 7 | 7 |
| No. 2 | 8 | 9 |
| No. 3 | 10 | 10 |
| No. 5 | 11 | 10 |
| No. 7 | 12 | 14 |
| No. 10 | 15 | 15 |
| No. 15 | 17 | 15 |
| Table 917.10-6 Required Ball Depths | |||
| Diameter of ball1, inches | Up to 20 | Over 20 to 30 | Over 30 to 48 |
| Minimum depth of ball1, percentage of diameter | 75 | 67 | 60 |
| 1 | Dimensions may vary according to site and type of plant material as provided in the American Standard for Nursery Stock. |
Use methyl alcohol at 70 percent (denatured wood alcohol diluted appropriately with water) or commercial bleach.
Use a polyvinyl antidesiccant.
Use a glyphosate based herbicide. Apply herbicides according to N.J.A.C 7:301 et seq.
Ensure that exposed conduit and fittings on sign structures are aluminum conforming to UL standards for rigid metallic conduit. Use fittings and accessories for aluminum conduit that are made of aluminum or stainless steel.
Ensure that conduit and fittings used as a raceway for the installation of wires and cables conform to the following:
For colored conduits (other than black and natural) ensure the “X” designation as part of the Cell Classification under Section 6.2 of ASTM D 3350 is “E”.
For ITS Conduit Type __, one of the conduits that is designated for electrical use is to be extruded integrally colored red to indicate its use for Electrical wiring.
Submit a certificate of compliance, as specified in 106.07, for all materials, components, and assemblies.
The manufacturer shall provide to the RE and the Contractor all splicing and terminating information necessary for proper installation of the cables and wires.
Ensure that conductors are made of stranded copper and conform to the standard rules of the American Institute of Electrical Engineers and of the National Board of Fire Underwriters. Do not use conductors that are smaller than No. 14 AWG or Brown and Sharp Gage. Ensure that conductors are soft annealed copper wire according to ASTM B 3, Class B for tin-coated conductors or are bare copper conductors according to ASTM B 8, Class B. Submit a certificate of compliance, as specified in 106.07, for all materials, components, and assemblies.
Use only one type of loop detector lead on the Project.
Ensure that the loop wire is thermoplastic single conductor wire with a 1/4-inch PVC tube or 1/4-inch, HDPE tube extruded over the loop detector wire, is manufactured in conformance with ICEA Publication No. S-61-402/ NEMA Publication No. WC5, and conforms to the following:
Use wire conforming to current ICEA-NEMA Standards Publication for Cross-linked-thermosetting-polyethylene-insulated Wire and Cable for the Transmission and Distribution of Electrical Energy, ICEA Publication No. S-66-524/ NEMA Publication No. WC 7 and UL Type RHW-USE.
Ensure that the insulation is a heat-resistant, moisture-resistant submarine compound conforming to ICEA Publication No. S-66-524/ NEMA Publication No. WC 7, except for the thickness of insulation. For all conductors, use insulation that is required for 600-volt rated circuit voltage according to Table 3-1 for cross-linked-thermosetting-polyethylene-insulated power cables, Column A of ICEA Publication No. S-66-524/NEMA Publication No. WC 7.
Use only one type of traffic signal cable on the Project.
For rigid metallic conduit with a diameter of 1 inch or more, use bushings that are hot-dip galvanized or electro-galvanized malleable iron, with a bakelite, nylon, or some other type of heat-resistant plastic molded and locked into the bushing. Use an aluminum, bronze, copper, or other corrosion-resistant metal lug. Ensure that the set screws, lug mounting, and binding screws are stainless steel. The Contractor may use threadless bushings at specific locations where the conduit is not threaded.
Fabricate insulating bushings for rigid metallic conduit with a diameter of less than 1 inch of molded high-impact thermoset plastic with a high dielectric and mechanical strength. Bond the conduit with bonding lock nuts. Do not use bushings made of materials that support combustion.
Use ground wire that is bare or insulated with a conductor that is 7-strand, soft-drawn copper conforming to ASTM B 8, Class B. Ensure that bare conductors are tinned. For insulated conductors, cover the conductor with an insulation that meets or exceeds the requirements of UL Type THW.
Use ground rods that are 5/8 inch in diameter and 12 feet long, composed of a steel core with copper covering. Thoroughly weld the 2 metals so that an interlocking crystalline union is secured between the 2 metals. Ensure that the minimum thickness of the copper on the cylindrical portion of the rod averages at least 0.010 inch.
Submit a certificate of compliance, as specified in 106.07, for all materials, components, and assemblies.
Use cable connectors that are fused for on line wires and nonfused on neutral wires. Ensure that the connectors are a waterproof inline type connector and are composed of a line side and a load side housing, each made of water-resistant synthetic rubber. In each housing, include a section to form a watertight seal around the cable, an interior arrangement to receive and retain the copper fuse contacts, and a watertight seal section at the point of disconnection.
Use contacts that are spring loaded, designed for a maximum current of 30 amperes at 600 volts and have a 90 percent minimum conductivity. Ensure that the contacts are suitable for gripping a cartridge-type midget fuse. Ensure that the fuse is 13/32 inch in diameter and 1-1/2 inches in length and is rated at 5 amperes and that the contacts are fully annealed and compressed onto the cable. Determine the size of each housing based on the cable diameter. Permanently mark each side of the housing as either load side or line side.
Submit manufacturer’s certification for all materials, components, and assemblies as specified in 106.07.
Use cable racks that are molded polycarbonate and have a dielectric strength of less than 2 microamps at 100,000 volts. Ensure that the polycarbonate used in the construction of the rack is fire retardant with an SE-1 rating. Use a cable rack that is 3 inches wide and 3 feet long in ground-installed junction boxes or that is 3 inches wide and 1 foot long in structures. Ensure that the cable rack contains 3 saddle arms with a capacity of 2 inches.
As an alternative, the Contractor may use steel cable racks that consist of a steel channel, welded steel supports, a clip, and porcelain insulators for each support. Hot-dip galvanize all steel components. Use a cable rack that is approximately 2 feet long with 3 supports in ground installed boxes and 7 inches long with 1 support in junction boxes located on structures. Space support holes on the channel approximately 1-1/2 inches on center. Ensure that the cable supports are designed with an interlocking feature at the rear of the support to prevent tilting and that the installed cable supports extend approximately 4 inches from the rack. Construct the porcelain insulator required on each support with a hook bottom groove to prevent slipping.
Submit a certificate of compliance, as specified in 106.07, for all materials, components, and assemblies.
Use cast boxes with suitable covers of like material held in place with stainless steel fasteners and sealed with a weatherproof neoprene gasket.
Provide mounting lugs with cast boxes. Ensure that all mounting hardware is stainless steel. For cast iron boxes, conform to the requirements specified in 909.03. Hot-dip galvanize cast iron boxes and covers.
Use aluminum boxes and covers that are either sand cast conforming to ASTM B 26, Alloy 356.0-F or 356.0-T6, or die cast conforming to ASTM B 108, Alloy 356.0-T6.
Use junction boxes for underdeck lighting that are cast iron of approved design, suited and adapted to the specific location and the number of conduit, nipples, and other required details. Use flush-type boxes for installation in a structure and surface-mounted-type boxes in all surface applications. Ensure that the cover has a neoprene gasket and is secured with stainless steel screws. If required, equip the box with busses to provide at least 5 full threads or a UL-approved watertight rigid conduit hub at each entry point of the conduit.
Use cast aluminum for pull boxes and pull fittings exposed on sign structures. Use boxes that are of approved design, suited and adapted to the specific location and the number and arrangement of conduit, and other details for the installation. Ensure that boxes have external lugs for mounting and internal mounting buttons for mounting equipment.
Submit a certificate of compliance, as specified in 106.07, for all materials, components, and assemblies.
For cabinets, use aluminum alloy conforming to ASTM B209, Alloy 6061-T6.
Label the door of all meter and control equipment cabinets, other than traffic signal cabinets, with a permanent reflective metallic sign indicating the voltage and the word DANGER. Apply the sign on a 0.040-inch minimum thickness aluminum alloy sheet. Use lettering that is approximately 1-1/2 inches high and is red on a white background. Install the sign with 4 stainless steel vandal proof screws.
Seal a print of the system field wiring in plastic and attach it to the inside of the door of each meter cabinet, control equipment, and controller cabinet.
Submit a certificate of compliance, as specified in 106.07, for all materials, components, and assemblies.
Use photoelectric controls that are rated for the control or lighting circuit voltage indicated. Provide mounting hardware to allow the unit to be installed in whatever type of location is shown. Ensure that the mounting conforms to the EEI-NEMA Standards for physical and electrical interchangeability of light sensitive control devices.
Submit a certificate of compliance, as specified in 106.07, for all materials, components, and assemblies.
Fabricate pedestals, poles, transformer bases, and mast bracket arms for traffic signal, highway lighting, and camera standards with materials according to the appropriate ASTM standard and the AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires and Traffic Signals. Weld and fabricate steel members according to AWS D1.1, Structural Welding code. For aluminum members, weld and fabricate according to ANSI/AWS D1.2 Structural Welding Code - Aluminum. Ensure that welding is performed by welders who are qualified according to ANSI/AWS D1.1 or ANSI/AWS D1.2, as appropriate. Submit copies of the welder qualifications upon request. Perform at least the minimum specified number of quality control inspections according to the applicable ANSI/ AASHTO/ AWS specification and any other tests and inspections necessary to control the quality of the work.
Ensure that aluminum poles, lighting, bracket arms, and traffic signal mast arms have a rotary, sand-polish finish giving a nonreflecting outer surface. Ensure that the external surfaces of transformer bases and shoe bases have a satin-type finish. Hot-dip galvanize steel poles and steel traffic signal arms according to ASTM A 123.
If wire or cable passes through a hole or runs along a surface at any point, through or on the complete assembly, ensure that the holes and surfaces are deburred and void of any sharp edges or protuberances that may damage the wire or cable. Install rubber grommets in the entrance hole to the shaft and mast arms where mid-mounted traffic signals are installed.
When installing aluminum traffic signal standards, use stainless steel hardware, bolts, nuts, and washers conforming to 908.04. For steel traffic signal standards, use galvanized hardware, bolts, nuts, and washers conforming to 908.01.
The manufacturer shall test standards and mast bracket arms to ensure compliance with specified material and strength requirements. Perform testing that also ensures that the items have been manufactured in conformance with the AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires and Traffic Signals.
Ensure aluminum poles and mast bracket arms are factory wrapped to protect them during shipment.
Submit a certificate of compliance, as specified in 106.07, for all materials, components, and assemblies. Submit 5 copies of the certification stipulating that the items conform to the strength and material requirements.
Fabricate according to AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signals.
Submit a certificate of compliance, as specified in 106.07, for all materials, components, and assemblies.
| Table 918.14-1 – Requirements for Traffic Signal Lamps | |||
| Indication Size | Wattage | Rated Initial Lumens | Center Length |
| 8 inch | 60 | 595 | 2-7/16 inches |
| 12 inch | 135 | 1750 | 3 inches |
| Pedestrian | 60 | 595 | 2-7/16 inches |
| Table 918.14-2 – Requirements for Highway Lighting Lamps | |||
| Wattage | Wattage Designation | Lumens | Voltage |
| 150 | SC-150 | 16,000 | 55 |
| 250 | VA-250 | 27,500 | 100 |
| 400 | WA-400 | 50,000 | 100 |
| Table 918.14-3 – Requirements for Highway Lighting Lamps | ||
| Designation | Wattage | Lumens |
| H 37-5KC/W | 250 | 11,400 |
| H 33-1GL/W | 400 | 22,000 |
Provide geotextile rolls with protective wrapping and, before placement, store rolls in a manner that protects against moisture and minimizes exposure to ultraviolet radiation. For applications that are above ground or exposed to ultraviolet radiation, provide geotextiles that are inert to commonly encountered chemicals and are stabilized against ultraviolet light degradation. Label each roll to provide product identification.
Use geotextiles conforming to the requirements in Table 919.01-1 for the intended use.
| Table 919.01-1 Requirements for Geotextiles | ||
| Category | Test Method | Class |
| Subsurface Drainage Geotextile | AASHTO M 288 | Class 2 |
| Stabilization Geotextile | AASHTO M 288 | Class 1 |
| Temporary Silt Fence1 | AASHTO M 288 | – |
| Erosion Control Geotextile2, 3 | AASHTO M 288 | Class 1 or 22 |
| Paving Fabric | AASHTO M 288 | – |
| 1 | Use the same geotextile requirements for both silt fence and heavy-duty silt fence. Reinforce heavy-duty silt fence with wire mesh as shown on the Plans. |
| 2 | For inlet filters, use Class 2 for woven monofilament geotextiles or Class 1 for all other types of geotextiles. |
| 3 | For inlet filter, Type 2, in addition to the AASHTO M 288 requirements, ensure that the geotextile’s burst strength is at least 650 pounds per square inch when tested according to ASTM D 3786. |
For geotextiles that are being permanently incorporated into the Contract, submit a certification of compliance as specified in 106.07.
Manufacture sediment control bags using polypropylene non-woven geotextiles conforming to the requirements in Table 919.02-1. Manufacture sediment control bag with a fill spout large enough to accommodate a 4-inch discharge hose and with straps to secure the hose and prevent pumped water from escaping without being filtered.
| Table 919.02-1 Requirements for Sediment Control Bag Geotextile | ||
| Property | Test Method | Requirements |
| Weight, oz/yd2, minimum | ASTM D 3776 | 10 |
| Grab Tensile Strength, lbs, minimum | ASTM D 4632 | 250 |
| Puncture Strength, lbs, minimum | ASTM D 4833 | 150 |
| Flow Rate, gal/min/ft2, minimum | ASTM D 4491 | 85 |
| Permittivity, sec−1, minimum | ASTM D 4491 | 1.2 |
| Mullen Burst Strength, psi, minimum | ASTM D 3786 | 460 |
| UV Stability, % , minimum | ASTM D 4355 | 70 |
| Apparent Opening Size, mm, maximum | ASTM D 4751 | 0.150 |
Use stalks of oats, wheat, rye, or barley that is relatively free from seeds, noxious weeds, and other foreign matter as straw. Ensure that the stalks are free from decayed matter and from organic matter soluble in water.
Use timothy, redtop, or native grasses for hay. Bind haybales with wire or baling twine. Use an ultraviolet light stabilized polypropylene twine that has a knot strength of 170 pounds and straight break strength of 300 pounds.
Provide gabion wire baskets that conform to the dimensions shown on the Plans within a tolerance of 5 percent. Use wire mesh that is galvanized steel wire having a minimum size of No. 12 gauge and a tensile strength between 60,000 and 80,000 pounds per square inch. Ensure that the zinc coating is 0.4 pounds per square yard when tested according to ASTM A 90.
Fabricate mesh openings to be hexagonal in shape and uniform in size. For baskets less than 24 inches in height, use openings measuring approximately 2-1/2 × 3-1/4 inches. For baskets greater than or equal to 24 inches in height, use openings measuring approximately 3-1/4 × 4-1/2 inches. Fabricate the wire mesh to be nonravelling when a single strand is cut.
Submit a certification of compliance as specified in 106.07.
For geomembrane liner systems, use HDPE sheeting with a nominal thickness of 30 mils. Manufacture the geomembrane of new, first quality resin formulated specifically for the intended purpose. Use resin as specified in Table 919.05-1.
| Table 919.05-1 Requirements for HDPE Resin | ||
| Property | Test Method | Requirements |
| Specific Gravity | ASTM D 792 | > 0.940 |
| Melt Index | ASTM D 1238 | < 0.4 g/10 min |
| Carbon Black Content | ASTM D 1603 | 2 - 3% |
Ensure that the surface of the geomembrane does not have striations, roughness, pinholes or bubbles and is free of holes, blisters and any foreign matter, such as soil or oil accumulation.
Submit a certification of compliance as specified in 106.07. If requested by the RE, attach a certification from the resin manufacturer certifying that the resin meets the requirements of Table 919.05-1.
For metallic waterstops, use sheet copper conforming to ASTM B 152, UNS No. C11000, with a weight of 16 ounces per square foot.
Use synthetic rubber or PVC nonmetallic waterstops conforming to Section 8 of AASHTO LRFD Bridge Construction Specifications.
Submit certifications of compliance for waterstops as specified in 106.07.
For epoxy bonding, use a 2-component, epoxy-resin, bonding system for application to concrete. Ensure that the epoxy bonding compound conforms to ASTM C 881, Type 2, Grade 1 or 2, Class B or C and is listed on the QPL.
Submit certifications of compliance for epoxy bonding compound as specified in 106.07.
Use water in mixing or curing of concrete that is free of oil, salt, acid, alkali, sugar, vegetable, or other substances injurious to the finished product. Ensure that water conforms to AASHTO T 26. The Contractor may use water known to be of potable quality without testing. If the source of water is shallow, enclose the intake to exclude silt, mud, grass, or other foreign materials.
If requested by the ME or RE, submit copies of test results for water.
Use sodium chloride conforming to ASTM D 632, Type I, Grade 1, with the following exceptions:
Use Schedule 40 PVC drainage pipe according to ASTM D 2729.
Provide epoxy injection material listed on the QPL that meets the requirements of ASTM C 881, Type I or IV, Grade 1, Class B or C. Submit certifications of compliance for epoxy injection material as specified in 106.07.
Provide polyethylene sheeting that is at least 10 mil in thickness. For concrete curing process, use white polyethylene sheeting as specified in 903.10.03.
Provide commercially made yellow or “international” orange floating turbidity barriers made of reinforced PVC sheeting as follows:
| Table 919.13-1 Requirements for Floating Turbidity Barrier1 | |||
| Type 1 | Type 2 | Type 3 | |
| Fabric Type | Polyester or Nylon reinforced PVC | Polyester or Nylon reinforced PVC | Nylon reinforced PVC with polypropylene filtration panel6 |
| Thickness, mils, minimum | 45 | 45 | 45 for PVC and filtration panel |
| Weight, oz./yd2., minimum | 18 | 22 | 22 |
| Grab tensile strength, lbs, minimum | 300 | 397 | 500 |
| UV Inhibited | Yes | Yes | Yes |
| Seams | Heat Welded | Heat Welded | Heat Welded |
| Stress Plates | Aluminum | ||
| Connecting Hardware | Galvanized | Galvanized | Galvanized |
| Floatation, lbs/ft, minimum2 | 13 | 22 | 29 |
| Bottom load chain or bottom weights3 |
1/4 in. Galvanized, 0.63 lbs/ft. minimum |
5/16 in. Galvanized, 0.95 lbs/ft. minimum |
5/16 in. Galvanized, 0.95lbs/ft min |
| Standard Depth4 | 5 ft. | 5 ft. | 5 ft. |
| Standard Length5 | 50 & 100 ft. | 50 & 100 ft. | 50 & 100 ft. |
| 1 | Submit manufacture specification to the Department for approval. Specifications vary slightly by manufacturer. |
| 2 | Floatation for barriers of depths greater than 10 feet is to be minimum 60 pounds per foot. Floatation must be sufficient to maintain the top of the barrier at an elevation 3 inches above the water. |
| 3 | Load chains or bottom weights shall be heavy enough to keep the floating turbidity relatively vertical in all flows. |
| 4 | The depth of the barrier may be greater than or lesser than 5 feet and shall be designed for the site. |
| 5 | The maximum length for barriers of depth greater than 10 feet is 50 feet. |
| 6 | The polypropylene filtration panel shall be no more than approximately 20 percent of the surface area. |
For detectable warning surfaces, use a surface or a coating material that is safety red in color according to FED-STD-595B color chip No. 31350 and has a 35 BPN minimum slip resistance when tested according to ASTM E 303. Ensure that the finished product is stabilized against UV degradation and adheres to the substrate without peeling or blistering.
Provide polyester matting of commercial quality that is a composite of polyester base fiber and vinyl chloride resin and is permeable to air and water, but shall prevent sunlight from reaching the soil. Ensure that the matting resists ultraviolet light, mildew and algae. Ensure that the matting is self-extinguishing when removed from flame. Ensure that the matting has a minimum thickness of 1/4 inch.