CPSBIDFM-1 DEPARTMENT OF TRANSPORTATION PAGE 1 CONSTRUCTION SERVICES/PROCUREMENT DIVISION TRENTON, NEW JERSEY TABULATION OF BIDS AND UNIT PRICES ROUTE 1 & 9 SOUTHBOUND EXPRESS TO AIRPORT CONNECTOR RAMP AND LOCAL TO EXPRESS CONNECTOR LANE CONTRACT NO. 047001300 GRADING AND PAVING CITY OF NEWARK, COUNTY OF ESSEX D.P. NO. 02104 BIDS RECEIVED APRIL 11, 2002 CONTRACT AWARD DATE APRIL 29, 2002 BIDDERS TOTAL PRICE BID 1 . TILCON OF NEW YORK INC $ 1,888,365.70 625 MT HOPE ROAD WHARTON NJ07885 2 . ROMAN ASPHALT CORP $ 1,967,193.46 14 OGDEN STREET NEWARK NJ07104 3 . TARHEEL ENTERPRISES INC $ 2,130,543.32 2000 HIGHWAY 35 MORGAN NJ08879 4 . INTERCOUNTY PAVING ASSOC LLC REJECTED 859 WILLOW GROVE STREET HACKETTSTOWN NJ07840 ITEM DESCRIPTION UNIT CONTRACT LOW BIDDER 2ND LOW BIDDER NO. QUANTITY UNIT PRICE DOLLAR AMT. UNIT PRICE DOLLAR AMT. 1 PERFORMANCE BOND AND PAYMENT BOND LS 1 8,000.00 8,000.00 21,210.00 21,210.00 2 FINAL CLEANUP LS 1 5,000.00 5,000.00 5,000.00 5,000.00 3 CONSTRUCTION LAYOUT LS 1 75,000.00 75,000.00 33,000.00 33,000.00 4 FIELD OFFICE TYPE A SET-UP U 1 25,000.00 25,000.00 35,000.00 35,000.00 5 FIELD OFFICE TYPE A MAINTENANCE MO 6 1,000.00 6,000.00 2,000.00 12,000.00 6 NO ITEM U 0 .00 0.00 .00 0.00 7 FUEL PRICE ADJUSTMENT LS 1 500.00 500.00 500.00 500.00 8 NO ITEM U 0 .00 0.00 .00 0.00 9 OWNER'S AND CONTRACTOR'S PROTECTIVE LS 1 200.00 200.00 4,000.00 4,000.00 LIABILITY INSURANCE 10 TRAINING REIMBURSEMENT LS 1 7,700.00 7,700.00 7,700.00 7,700.00 11 MOBILIZATION LS 1 200,000.00 200,000.00 196,000.00 196,000.00 12 TELEPHONE SERVICE LS 1 1,500.00 1,500.00 1,500.00 1,500.00 13 NO ITEM U 0 .00 0.00 .00 0.00 14 NO ITEM U 0 .00 0.00 .00 0.00 15 NO ITEM U 0 .00 0.00 .00 0.00 16 NO ITEM U 0 .00 0.00 .00 0.00 17 CLEARING SITE LS 1 20,000.00 20,000.00 16,000.00 16,000.00 18 STRIPPING HA 1 8,500.00 8,500.00 1.00 1.00 19 REMOVAL OF CONCRETE BASE COURSE AND SM 375 50.00 18,750.00 195.00 73,125.00 CONCRETE SURFACE COURSES 20 ROADWAY EXCAVATION, UNCLASSIFIED CM 2,063 30.00 61,890.00 49.00 101,087.00 21 MILLING, 50 MM DEPTH SM 14,068 5.75 80,891.00 6.00 84,408.00 22 MILLING, 75 MM VARIABLE DEPTH SM 1,244 6.45 8,023.80 7.00 8,708.00 23 SAWCUTTING LM 1,843 5.95 10,965.85 20.00 36,860.00 24 SUBBASE CM 498 45.00 22,410.00 70.00 34,860.00 25 UNDERLAYER PREPARATION SM 796 6.00 4,776.00 7.00 5,572.00 26 HAYBALES U 20 5.00 100.00 25.00 500.00 27 SILT FENCE LM 224 15.00 3,360.00 20.00 4,480.00 28 INLET FILTERS U 11 50.00 550.00 100.00 1,100.00 29 GEOTEXTILE SM 2,467 3.00 7,401.00 3.00 7,401.00 30 HOT MIX ASPHALT PAVEMENT REPAIR, SM 187 84.00 15,708.00 75.00 14,025.00 PARTIAL DEPTH 31 REMOVAL OF PAVEMENT REFLECTORS AND CASTINGS U 250 7.50 1,875.00 20.00 5,000.00 32 NO ITEM U 0 .00 0.00 .00 0.00 33 NO ITEM U 0 .00 0.00 .00 0.00 34 DENSE GRADED AGGREGATE BASE COURSE, SM 2,381 9.80 23,333.80 12.00 28,572.00 200 MM THICK 35 COARSE AGGREGATE, SIZE NO. 8 CM 2 35.00 70.00 30.00 60.00 36 COARSE AGGREGATE, SIZE NO. 57 CM 50 30.00 1,500.00 30.00 1,500.00 37 CONCRETE BASE COURSE, VES, 250 MM THICK SM 796 125.00 99,500.00 140.00 111,440.00 38 SUPERPAVE HOT MIX ASPHALT 25M64 BASE COURSE MGR 1,052 46.00 48,392.00 60.00 63,120.00 39 NO ITEM U 0 .00 0.00 .00 0.00 40 NO ITEM U 0 .00 0.00 .00 0.00 41 NO ITEM U 0 .00 0.00 .00 0.00 42 NO ITEM U 0 .00 0.00 .00 0.00 43 NO ITEM U 0 .00 0.00 .00 0.00 44 SUPERPAVE HOT MIX ASPHALT 12.5H76 SURFACE MGR 2,584 65.00 167,960.00 64.00 165,376.00 COURSE 45 ASPHALT PRICE ADJUSTMENT LS 1 1,200.00 1,200.00 1,200.00 1,200.00 46 SUPERPAVE HOT MIX ASPHALT 19H64 INTERMEDIATE MGR 475 65.00 30,875.00 61.00 28,975.00 COURSE 47 TACK COAT L 8,513 .25 2,128.25 1.00 8,513.00 48 PRIME COAT L 2,619 .25 654.75 1.30 3,404.70 49 LONGITUDINAL JOINT TIES U 1,462 12.75 18,640.50 11.00 16,082.00 50 NO ITEM U 0 .00 0.00 .00 0.00 51 SUBBASE OUTLET DRAIN LM 14 150.00 2,100.00 75.00 1,050.00 52 150 MM CORRUGATED STEEL UNDERDRAIN PIPE LM 3 200.00 600.00 70.00 210.00 53 UNDERDRAIN, TYPE F LM 40 150.00 6,000.00 100.00 4,000.00 54 375 MM REINFORCED CONCRETE CULVERT PIPE LM 93 200.00 18,600.00 155.00 14,415.00 55 450 MM REINFORCED CONCRETE CULVERT PIPE LM 3 210.00 630.00 160.00 480.00 56 600 MM REINFORCED CONCRETE CULVERT PIPE LM 2 225.00 450.00 170.00 340.00 57 INLETS CONVERTED TO MANHOLES U 4 2,100.00 8,400.00 1,500.00 6,000.00 58 INLETS, TYPE B U 4 3,225.00 12,900.00 3,500.00 14,000.00 59 INLETS, TYPE E U 6 3,250.00 19,500.00 3,800.00 22,800.00 60 225 BY 400 MM CONCRETE VERTICAL CURB LM 827 65.00 53,755.00 65.00 53,755.00 61 600MM X 175MM DUAL FACE CONCRETE LM 641 90.00 57,690.00 86.00 55,126.00 VERTICAL CURB, DOWELLED 62 CONCRETE SIDEWALK, 100 MM THICK SM 1 95.00 95.00 65.00 65.00 63 CONCRETE ISLAND, 100 MM THICK SM 12 75.00 900.00 65.00 780.00 64 RUB RAIL LM 317 25.00 7,925.00 22.50 7,132.50 65 SLOTTED GUIDE RAIL TERMINALS U 2 2,275.00 4,550.00 2,175.00 4,350.00 66 REMOVAL OF GUIDE RAIL LM 206 7.50 1,545.00 7.25 1,493.50 67 BEAM GUIDE RAIL LM 317 165.00 52,305.00 93.00 29,481.00 68 RESET BEAM GUIDE RAIL WITH EXISTING POSTS LM 61 25.00 1,525.00 23.00 1,403.00 69 BEAM GUIDE RAIL ANCHORAGES U 3 750.00 2,250.00 700.00 2,100.00 70 NO ITEM U 0 .00 0.00 .00 0.00 71 NO ITEM U 0 .00 0.00 .00 0.00 72 BREAKAWAY BARRICADES U 40 80.00 3,200.00 100.00 4,000.00 73 DRUMS U 150 60.00 9,000.00 70.00 10,500.00 74 TRAFFIC CONES U 100 20.00 2,000.00 15.00 1,500.00 75 CONSTRUCTION IDENTIFICATION SIGNS, U 2 2,000.00 4,000.00 2,000.00 4,000.00 1 200 BY 2 400 MM 76 VARIABLE MESSAGE SIGNS U 4 4,000.00 16,000.00 3,500.00 14,000.00 77 CONSTRUCTION SIGNS SM 100 96.00 9,600.00 200.00 20,000.00 78 ILLUMINATED FLASHING ARROWS, 600 BY 1 200 MM U 2 1,500.00 3,000.00 1,500.00 3,000.00 79 TRAFFIC CONTROL TRUCKS WITH MOUNTED U 2 6,000.00 12,000.00 2,500.00 5,000.00 CRASH CUSHIONS 80 REMOVABLE PAVEMENT MARKING TAPE LM 200 4.10 820.00 4.10 820.00 81 TRAFFIC STRIPES LM 200 20.00 4,000.00 12.00 2,400.00 82 NO ITEM U 0 .00 0.00 .00 0.00 83 NO ITEM U 0 .00 0.00 .00 0.00 84 TRAFFIC STRIPES, LONG LIFE, EPOXY RESIN LM 6,610 1.00 6,610.00 .98 6,477.80 85 TRAFFIC MARKINGS, LINES, LONG LIFE, LM 530 3.25 1,722.50 3.25 1,722.50 THERMOPLASTIC 86 REMOVAL OF TRAFFIC STRIPES AND MARKINGS LM 1,000 1.65 1,650.00 1.50 1,500.00 87 TWO-WAY PLOWABLE MONO-DIRECTIONAL U 205 28.50 5,842.50 28.50 5,842.50 WHITE PAVEMENT REFLECTORS AND CASTINGS 88 TWO-WAY PLOWABLE MONO-DIRECTIONAL U 56 28.50 1,596.00 28.50 1,596.00 AMBER PAVEMENT REFLECTORS AND CASTINGS 89 NO ITEM U 0 .00 0.00 .00 0.00 90 SIGNS SM 6 600.00 3,600.00 600.00 3,600.00 91 GUIDE SIGNS, TYPE GA, NON-BREAKAWAY SUPPORTS SM 18 1,170.00 21,060.00 1,170.00 21,060.00 92 GUIDE SIGN PANELS, TYPE GO SM 290 480.00 139,200.00 480.00 139,200.00 93 FLEXIBLE DELINEATORS, GUIDE RAIL MOUNTED U 24 22.50 540.00 21.00 504.00 94 NO ITEM U 0 .00 0.00 .00 0.00 95 NO ITEM U 0 .00 0.00 .00 0.00 96 NO ITEM U 0 .00 0.00 .00 0.00 97 NO ITEM U 0 .00 0.00 .00 0.00 98 JUNCTION BOX FOUNDATIONS U 7 1,350.00 9,450.00 1,240.00 8,680.00 99 LIGHTING STANDARD ASSEMBLIES, TYPE L-4.6-V-X U 9 2,900.00 26,100.00 2,150.00 19,350.00 100 78 MM RIGID METALLIC CONDUIT, TYPE CUG LM 396 60.00 23,760.00 61.99 24,548.04 101 MULTIPLE LIGHTING WIRE, NO. 2 AWG LM 776 6.50 5,044.00 8.53 6,619.28 102 UNDERDECK LIGHTING ASSEMBLIES, TYPE W U 3 1,750.00 5,250.00 1,600.00 4,800.00 103 41MM RIGID METALLIC CONDUIT, LM 17 125.00 2,125.00 62.32 1,059.44 TYPE EXPOSED 104 450 BY 900 MM JUNCTION BOXES U 4 1,250.00 5,000.00 1,100.00 4,400.00 105 MULTIPLE LIGHTING WIRE, NO. 10 AWG LM 80 5.00 400.00 3.28 262.40 106 78 MM RIGID METALLIC CONDUIT, TYPE CUR LM 62 165.00 10,230.00 141.04 8,744.48 107 246MM BY 468MM BY 156MM CAST U 1 950.00 950.00 1,100.00 1,100.00 IRON JUNCTION BOXES 108 LIGHTING STANDARD ASSEMBLIES, TYPE L-2.4-V-X U 1 2,850.00 2,850.00 2,460.00 2,460.00 109 NO ITEM U 0 .00 0.00 .00 0.00 110 NO ITEM U 0 .00 0.00 .00 0.00 111 NO ITEM U 0 .00 0.00 .00 0.00 112 NO ITEM U 0 .00 0.00 .00 0.00 113 NO ITEM U 0 .00 0.00 .00 0.00 114 NO ITEM U 0 .00 0.00 .00 0.00 115 NO ITEM U 0 .00 0.00 .00 0.00 116 NO ITEM U 0 .00 0.00 .00 0.00 117 NO ITEM U 0 .00 0.00 .00 0.00 118 NO ITEM U 0 .00 0.00 .00 0.00 119 NO ITEM U 0 .00 0.00 .00 0.00 120 41 MM RIGID METALLIC CONDUIT, TYPE CUG LM 40 52.50 2,100.00 51.17 2,046.80 121 SERVICE WIRE, NO. 6 AWG LM 195 5.75 1,121.25 6.56 1,279.20 122 TELEPHONE WIRE 6/C #22 AWG SHIELDED LM 60 15.00 900.00 9.84 590.40 123 FOUNDATIONS, TYPE P U 2 1,800.00 3,600.00 800.00 1,600.00 124 NO ITEM U 0 .00 0.00 .00 0.00 125 250 BY 900 MM JUNCTION BOXES U 4 500.00 2,000.00 890.00 3,560.00 126 METER CABINET, TYPE P-WIM U 2 8,500.00 17,000.00 9,450.00 18,900.00 127 METER CABINET, TYPE MC U 1 1,350.00 1,350.00 1,600.00 1,600.00 128 GROUND WIRE, NO. 8 AWG LM 80 3.30 264.00 3.44 275.20 129 AVC/WIM SITE, 2 LANES U 3 42,000.00 126,000.00 41,200.00 123,600.00 130 AVC/WIM SITE, 3 LANES U 1 64,000.00 64,000.00 61,400.00 61,400.00 131 NO ITEM U 0 .00 0.00 .00 0.00 132 LOOP DETECTOR LEAD LM 390 8.00 3,120.00 5.25 2,047.50 133 FOUNDATIONS, TYPE MCF U 1 850.00 850.00 750.00 750.00 134 NO ITEM U 0 .00 0.00 .00 0.00 135 NO ITEM U 0 .00 0.00 .00 0.00 136 NO ITEM U 0 .00 0.00 .00 0.00 137 NO ITEM U 0 .00 0.00 .00 0.00 138 NO ITEM U 0 .00 0.00 .00 0.00 139 NO ITEM U 0 .00 0.00 .00 0.00 140 NO ITEM U 0 .00 0.00 .00 0.00 141 NO ITEM U 0 .00 0.00 .00 0.00 142 TOPSOILING, 100 MM THICK SM 1,810 4.00 7,240.00 5.00 9,050.00 143 FERTILIZING AND SEEDING, TYPE A-3 SM 1,810 .50 905.00 1.00 1,810.00 144 FERTILIZING AND SEEDING, TYPE F SM 181 .50 90.50 1.00 181.00 145 TOPSOIL STABILIZATION MATTING SM 80 5.00 400.00 6.00 480.00 146 STRAW MULCHING SM 1,991 .50 995.50 1.00 1,991.00 147 NONVEGETATIVE SURFACE, HOT MIX ASPHALT SM 227 32.00 7,264.00 32.50 7,377.50 148 NO ITEM U 0 .00 0.00 .00 0.00 149 NO ITEM U 0 .00 0.00 .00 0.00 150 NO ITEM U 0 .00 0.00 .00 0.00 151 NO ITEM U 0 .00 0.00 .00 0.00 152 NO ITEM U 0 .00 0.00 .00 0.00 153 LIGHT POLE-SINGLE U 3 4,300.00 12,900.00 3,890.00 11,670.00 154 LIGHT POLE-DOUBLE U 1 6,000.00 6,000.00 4,980.00 4,980.00 155 HAND HOLE U 3 5,500.00 16,500.00 985.00 2,955.00 156 DUCT BANK, 4-3" LM 138 150.00 20,700.00 95.12 13,126.56 157 #2 AWG TYPE USE WIRE LM 610 10.00 6,100.00 8.53 5,203.30 158 #6 AWG TYPE USE WIRE LM 158 7.50 1,185.00 6.40 1,011.20 159 2" PVC CONDUIT LM 22 60.00 1,320.00 27.89 613.58 160 REMOVE LIGHT POLE-SINGLE U 2 1,250.00 2,500.00 675.00 1,350.00 161 REMOVE HAND HOLE U 1 1,125.00 1,125.00 850.00 850.00 162 REMOVE 2" PVC CONDUIT LM 10 18.50 185.00 22.96 229.60 163 REMOVE 4 #2 WIRE LM 83 18.50 1,535.50 6.56 544.48 164 PLUG CONDUIT ENDS U 16 15.00 240.00 14.00 224.00 165 RELOCATE LIGHT POLE-SINGLE U 1 2,200.00 2,200.00 890.00 890.00 SUMMARY OF AMOUNTS ROAD ITEMS $ 1,888,365.70 $ 1,967,193.46 BRIDGE ITEMS 0.00 0.00 SUB-TOTAL AMOUNTS FOR BRIDGE WORK AGREE AGREE (HEADER) LOW BID =$ 1,888,365.70 (HEADER) 2ND LOW BID =$ 1,967,193.46 COMPUTED LOW BID =$ 1,888,365.70 COMPUTED 2ND LOW BID =$ 1,967,193.46 COMPUTED LOW BID =$ 1,888,365.70 COMPUTED 2ND LOW BID =$ 1,967,193.46