CPSBIDFM-1 DEPARTMENT OF TRANSPORTATION PAGE 1 CONSTRUCTION SERVICES/PROCUREMENT DIVISION TRENTON, NEW JERSEY TABULATION OF BIDS AND UNIT PRICES CUMBERLAND POND SPILLWAY CCONTRACT NO. 041950392 GRADING, PAVING & STRUCTURE MAURICE RIVER TOWNSHIP, CUMBERLAND COUNTY FEDERAL PROJECT NO. STP-0008 (122) D.P. NO. 03119 BIDS RECEIVED JUNE 26, 2003 CONTRACT AWARD DATE JULY 24, 2003 BIDDERS TOTAL PRICE BID 1 . LOFTUS CONSTRUCTION INC $ 750,450.00 1903 TAYLOR'S LANE CINNAMINSON NJ08077 2 . AGATE CONSTR CO INC $ 987,172.00 PO#107 KINGS HWY & RT#83 OCEAN VIEW NJ08230 3 . IEW CONSTR GP $ 1,038,452.50 PO#8008 TRENTON NJ08650 4 . RICHARD E PIERSON CONSTR CO INC $ 1,123,474.50 P O BOX 430 WOODSTOWN NJ08098 5 . CRUZ CONSTRUCTION CORP $ 1,643,723.50 952 HOLMDEL ROAD HOLMDEL NJ07733 ITEM DESCRIPTION UNIT CONTRACT LOW BIDDER 2ND LOW BIDDER NO. QUANTITY UNIT PRICE DOLLAR AMT. UNIT PRICE DOLLAR AMT. 1 PERFORMANCE BOND AND PAYMENT BOND LS 1 12,300.00 12,300.00 6,000.00 6,000.00 2 FINAL CLEANUP LS 1 1,000.00 1,000.00 1,000.00 1,000.00 3 CONSTRUCTION LAYOUT LS 1 5,000.00 5,000.00 10,000.00 10,000.00 4 FIELD OFFICE TYPE B SET-UP U 1 15,000.00 15,000.00 20,000.00 20,000.00 5 FIELD OFFICE TYPE B MAINTENANCE MO 7 1,000.00 7,000.00 1,500.00 10,500.00 6 TELEPHONE SERVICE LS 1 1,750.00 1,750.00 1,750.00 1,750.00 7 MATERIALS FIELD LABORATORY SET-UP U 1 5,000.00 5,000.00 2,000.00 2,000.00 8 MATERIALS FIELD LABORATORY MAINTENANCE MO 6 500.00 3,000.00 800.00 4,800.00 9 TRAINEES HRS 1,000 1.00 1,000.00 .01 10.00 10 OWNER'S AND CONTRACTOR'S PROTECTIVE LS 1 5,000.00 5,000.00 3,000.00 3,000.00 LIABILITY INSURANCE 11 PROGRESS SCHEDULE LS 1 1,000.00 1,000.00 1,000.00 1,000.00 12 MOBILIZATION LS 1 40,000.00 40,000.00 98,000.00 98,000.00 13 CLEARING SITE LS 1 5,000.00 5,000.00 5,000.00 5,000.00 14 ROADWAY EXCAVATION, TEMPORARY EROSION CONTROL CM 80 20.00 1,600.00 1.00 80.00 15 CONSTRUCTION DRIVEWAY MGR 1 500.00 500.00 200.00 200.00 16 HEAVY DUTY SILT FENCE LM 585 15.00 8,775.00 10.00 5,850.00 17 FLOATING TURBIDITY BARRIER LM 17 50.00 850.00 150.00 2,550.00 18 NO ITEM U 0 .00 0.00 .00 0.00 19 NO ITEM U 0 .00 0.00 .00 0.00 20 CONCRETE SIDEWALK, REINFORCED, 150 MM THICK SM 9 20.00 180.00 80.00 720.00 21 BEAM GUIDE RAIL LM 314 35.00 10,990.00 35.00 10,990.00 22 SLOTTED GUIDE RAIL TERMINALS U 2 2,000.00 4,000.00 1,900.00 3,800.00 23 REMOVAL OF GUIDE RAIL LM 284 10.00 2,840.00 5.00 1,420.00 24 BEAM GUIDE RAIL ANCHORAGES U 2 600.00 1,200.00 500.00 1,000.00 25 MISCELLANEOUS CONCRETE CM 2 5,000.00 10,000.00 5,000.00 10,000.00 26 SNOW FENCE, PLASTIC LM 452 8.00 3,616.00 10.00 4,520.00 27 RIPRAP STONE CHANNEL PROTECTION, 450 MM THICK SM 115 40.00 4,600.00 125.00 14,375.00 (D50=225 MM) 28 PRECAST CONCRETE CURB, CONSTRUCTION BARRIER, LM 251 120.00 30,120.00 125.00 31,375.00 TYPE 4 29 DRUMS U 15 50.00 750.00 100.00 1,500.00 30 TEMPORARY CRASH CUSHIONS, QUADGUARD, U 1 20,000.00 20,000.00 15,000.00 15,000.00 6 BAYS, 610 MM WIDE 31 VARIABLE MESSAGE SIGNS U 1 12,000.00 12,000.00 3,000.00 3,000.00 32 CONSTRUCTION SIGNS SM 27 100.00 2,700.00 110.00 2,970.00 33 TEMPORARY CRASH CUSHIONS, INERTIAL BARRIER U 1 15,000.00 15,000.00 5,000.00 5,000.00 SYSTEM, 14 MODULES 34 REMOVABLE WET WEATHER PAVEMENT MARKING TAPE LM 1,350 6.00 8,100.00 3.50 4,725.00 35 TRAFFIC DIRECTORS, FLAGGERS HRS 300 60.00 18,000.00 1.00 300.00 36 TRAFFIC MARKINGS, LINES, LONG LIFE, LM 1,360 2.00 2,720.00 1.40 1,904.00 THERMOPLASTIC 37 REMOVAL OF TRAFFIC STRIPES AND MARKINGS LM 1,360 1.00 1,360.00 1.30 1,768.00 38 FLEXIBLE DELINEATORS, GUIDE RAIL MOUNTED U 43 10.00 430.00 20.00 860.00 39 REMOVAL AND REPLACEMENT OF PAVEMENT U 30 20.00 600.00 10.00 300.00 REFLECTOR LENSES 40 CELLULAR CONCRETE BLOCK REVETMENT SYSTEM SM 414 120.00 49,680.00 150.00 62,100.00 41 SLOPE REPAIR AREA SM 1,700 10.00 17,000.00 50.00 85,000.00 42 NONVEGETATIVE SURFACE, HOT MIX ASPHALT SM 605 20.00 12,100.00 20.00 12,100.00 43 TWO-WAY PLOWABLE BI-DIRECTIONAL U 10 100.00 1,000.00 30.00 300.00 AMBER PAVEMENT REFLECTORS AND CASTINGS 44 FERTILIZING AND SEEDING, TYPE F SM 170 2.00 340.00 10.00 1,700.00 45 NO ITEM U 0 .00 0.00 .00 0.00 46 NO ITEM U 0 .00 0.00 .00 0.00 47 NO ITEM U 0 .00 0.00 .00 0.00 48 NO ITEM U 0 .00 0.00 .00 0.00 49 NO ITEM U 0 .00 0.00 .00 0.00 BRIDGE 50 CLEARING SITE STRUCTURE (SPILLWAY) LS 1 4,000.00 4,000.00 4,000.00 4,000.00 51 FOUNDATION EXCAVATION CM 87 125.00 10,875.00 65.00 5,655.00 52 COFFERDAMS LS 1 75,284.00 75,284.00 123,000.00 123,000.00 53 STAGED STREAM DIVERSION SYSTEM LS 1 50,000.00 50,000.00 100,000.00 100,000.00 54 CONCRETE IN STRUCTURES, FOOTINGS CM 53 400.00 21,200.00 500.00 26,500.00 55 CONCRETE IN STRUCTURES, SPILLWAY CM 44 2,000.00 88,000.00 1,500.00 66,000.00 56 CONCRETE WALL REPAIR LS 1 2,000.00 2,000.00 5,000.00 5,000.00 57 REINFORCEMENT STEEL IN STRUCTURES, EPOXY KG 4,750 3.00 14,250.00 2.50 11,875.00 COATED 58 PRESSURE INJECTION, CONCRETE CRACKS LM 2 800.00 1,600.00 500.00 1,000.00 59 UNDERWATER CONCRETE PARGING SM 34 300.00 10,200.00 400.00 13,600.00 60 TEST PILES, DRIVEN LM 17 500.00 8,500.00 700.00 11,900.00 61 TEST PILES, FURNISHED LM 23 30.00 690.00 75.00 1,725.00 62 STEEL H-PILES, DRIVEN, HP 250 MM BY 62 KG/M LM 326 50.00 16,300.00 100.00 32,600.00 63 STEEL H-PILES, FURNISHED, HP 250 MM LM 390 30.00 11,700.00 75.00 29,250.00 BY 62 KG/M 64 FURNISHING EQUIPMENT FOR DRIVING PILES LS 1 25,000.00 25,000.00 50,000.00 50,000.00 65 SLUICE GATE U 1 15,000.00 15,000.00 10,000.00 10,000.00 66 FISH LADDER LM 9 2,500.00 22,500.00 3,000.00 27,000.00 67 ALUMINUM GRATING SM 5 500.00 2,500.00 400.00 2,000.00 68 GROUND VIBRATION MONITORING LS 1 12,000.00 12,000.00 5,000.00 5,000.00 69 METAL RAILING LM 63 250.00 15,750.00 200.00 12,600.00 SUMMARY OF AMOUNTS ROAD ITEMS $ 343,101.00 $ 448,467.00 BRIDGE ITEMS $ 407,349.00 $ 538,705.00 SUB-TOTAL AMOUNTS FOR BRIDGE WORK BRIDGE $ 407,349.00 $ 538,705.00 AGREE AGREE (HEADER) LOW BID =$ 750,450.00 (HEADER) 2ND LOW BID =$ 987,172.00 COMPUTED LOW BID =$ 750,450.00 COMPUTED 2ND LOW BID =$ 987,172.00 COMPUTED LOW BID =$ 750,450.00 COMPUTED 2ND LOW BID =$ 987,172.00