General Permit 17 – Stabilization of eroded shorelines

Introduction on the need and origin of the LS rule

Coastal Management Rules
N.J.A.C. 7:7-6.17 General Permit 17 –stabilization of eroded shorelines

(a) This general permit authorizes the stabilization of eroded shorelines along tidal
waterways, excluding the Atlantic Ocean, provided that the proposed method complies with all of the following:

1. The stabilization materials are limited to live branch cuttings, live facings, live stakes, vegetative cuttings, vegetated earth buttresses, choir fiber products, fiber plugs, plants and clusters, selected plant materials, fiber pallets, fiber carpet, and wood stake anchor systems.
Materials shall be installed in accordance with the construction guidelines of Chapter 16--
"Streambank and Shoreline Stabilization Protection," of the National Engineering Handbook (NEH), Part 650, 1996, published by the United States Department of Agriculture, incorporated herein by reference, as amended and supplemented. This coastal general permit does not authorize the use of geotubes, stone, concrete, gabions, wood sheathing, pvc pipe, used tires, discarded Christmas trees, or other material not specifically stated in this paragraph;

2. The stabilization of the eroded shoreline shall have no adverse impact on special areas defined at N.J.A.C. 7:7-9;

3. No disturbance to wetlands shall occur;

4. Where shoreline stabilization will occur outshore of a wetland, the construction shall result in minimum feasible alteration or impairment of natural tidal circulation;

5. Where shoreline stabilization will occur outshore of a wetlands, the construction shall result in minimum feasible alteration or impairment of the natural contour or the natural vegetation of the wetlands;

6. For sites where grading is required, no grading shall occur below the spring high water line, and all soil or other graded materials shall be pulled back away from the water. Grading by pushing soil or other material below the spring high water line is prohibited;

7. The placement of bioengineering materials, with the exception of plantings, shall be limited to that necessary to protect the shoreline;

8. Plant material shall be chosen and installed in accordance with "Vegetation For Tidal Shoreline Stabilization In the Mid-Atlantic States" in Chapter 16--"Streambank and Shoreline Stabilization Protection," of the National Engineering Handbook (NEH), Part 650, 1996, published by the United States Department of Agriculture, incorporated herein by reference, as
amended and supplemented.

9. For projects on public lands, public access to the waterfront shall be provided and maintained during construction, and thereafter; and

10. If the Department determines that construction has resulted in adverse shoreline sand movement, including erosion or shoaling, the Department may require the permittee to remove the shoreline stabilization materials.

 

Department: NJDEP Home | About DEP | Index by Topic | Programs/Units | DEP Online
Statewide: NJ Home | Services A to Z | Departments/Agencies | FAQs

Copyright © State of New Jersey, 1996-2016

Last Updated: July 9, 2018