NJDEP UST Fund Cost Guide
Effective January 1, 2010
Updated 23 June 2010
Cover Letter
Januaury 1, 2010
Dear UST Fund Applicant or Consultant:
Enclosed you will find an updated version of the Department of Environmental Protection (NJDEP) Petroleum Underground Storage Tank Remediation, Upgrade & Closure Fund (UST Fund) Cost Guide. The latest version of the UST Fund Cost Guide is now utilized by the NJDEP and the NJEDA in accordance with N.J.S.A. 58:10A-37.5b. The UST Fund Cost Guide will be used for the reimbursement of costs associated with regulated and unregulated leaking tanks as well as non-leaking residential heating oil tanks. Versions of this Cost Guide may now be found on the web at www.nj.gov/dep/srp/finance/ustfund.
This Cost Guide will become effective with the following conditions:
- All new applications that have been submitted to the NJDEP prior to and after January 1, 2010, and have not yet been forwarded to the New Jersey Economic Development Authority (NJEDA) for approval will be reviewed utilizing the 2010 Cost Guide.
- All previously approved applications (applications where the NJEDA has approved funding) will have costs submitted and reviewed (e.g. invoices and subcontractor invoices) utilizing the Cost Guide in effect at that time of their approval. All applications that have already been submitted to the NJDEP may not be withdrawn for the purpose of revising the cost proposals.
- The cost proposals submitted with applications to the UST Fund are estimates. Disbursements will be made after the work is performed and sufficient documentation of actual costs incurred is submitted to the NJDEP or NJEDA. This would include, but is not limited to, direct subcontractor invoices and receipts representing actual service, material and equipment costs, and proof of payment such as cancelled checks or invoices marked “paid”. It is important that applicants advise their consultants/contractors that this documentation is necessary for the applicant to receive the maximum reimbursement possible from the UST Fund. It is recommended that the applicant make this a requirement in the contract with their consultant/contractor.
- If proposed rates and/or costs related to UST Fund Applications for leaking tanks exceed the UST Fund Cost Guide they must be justified to the satisfaction of the NJDEP. Such justification may include an explanation of specific site conditions that warrant additional effort, specific specialized site needs, etc. It is the responsibility of the applicant to provide such justification. Any costs in excess of those found in the UST Fund Cost Guide that can not be adequately justified may be capped at the UST Fund Cost Guide rates/costs or denied.
- All services, and/or materials that are subcontracted, rented or purchased by the applicant’s prime consultant/contractor will be reimbursed at actual cost plus a prime consultant/contractor mark-up not to exceed 15%. The exception to this is if the subcontracted, rented or purchased items are substantiated by quantity documentation only, with no specific unit cost documentation being provided. In these instances the NJDEP will review and consider the appropriate reimbursement on a case by case basis. All such costs must be verified, as discussed above, by the direct subcontractor invoices or material receipts. For example, for soil disposal or waste oil/ wastewater disposal, costs must be verified by receipt of the disposal facility invoice indicating cost per unit and amount (weight or volume) disposed of. For materials that are purchased in bulk by consultants/contractors for use at various sites, a copy of a recent invoice indicating the bulk purchase price would satisfy the documentation requirement.
- The NJDEP will review the proposed scope of work and costs to determine if the level of effort is appropriate for the work proposed. This level of effort review evaluates the amount of time it takes to perform the tasks proposed, as well as the level of personnel necessary to perform these tasks. Any questions about the proposed level of effort will be directed to the applicant and their consultant/contractor. Any level of effort that is found to be in excess of what the NJDEP deems necessary to perform the work proposed will not be approved for funding.
- For regulated UST applications and regulated UST supplemental funding requests, please note that the NJDEP instructs the NJEDA to make a 50% disbursement upon approval of the application, and subsequent to the closing of the grant, and/or loan.
- The UST Fund Cost Guide was developed by evaluating current construction, and/or remediation cost references, other State of New Jersey contracts for similar services or items, the solicitation of quotes from rental companies, and the general experience of NJDEP staff. The UST Fund Cost Guide was not intended to be all-inclusive; encompassing every possible cost associated with underground storage tank closure, replacement and/ or remediation. Any rates/costs proposed that do not appear in the UST Fund Cost Guide will be evaluated on a case-by-case basis using a similar process.
- Any costs not approved by the NJDEP or the NJEDA are the sole responsibility of the applicant.
- Applicants should note the ineligible costs listed on Page 5 of the UST Fund Cost Guide.
- Any questions regarding the attached UST Fund Cost Guide can be directed to the Bureau of Contract & Fund Management, NJDEP @ (609) 777-0101.
IMPORTANT NOTE: In compliance with N.J.S.A. 58:10A-37.5b, the Department of Environmental Protection (Department) has developed and published a cost guidance document that establishes the maximum cost to be paid for the eligible project costs of the closure or replacement of a petroleum underground storage tank used to store heating oil for onsite consumption in a residential building or a petroleum underground storage tank with a capacity of 2,000 gallons or less used to store heating oil for onsite consumption in a nonresidential building. The Department and the New Jersey Economic Development Authority (NJEDA) will use the following Cost Guide to determine costs that are eligible under the UST Fund. A copy of the Cost Guide and other UST Fund information is available on the Department’s web site at www.nj.gov/dep/srp/finance/ustfund. Be advised that as of October 3, 2006, due to the enactment of P.L. 2006, c.58, all contractors performing work on non-regulated underground storage tanks, including homeowner heating oil tanks, where work is being funded by the Petroleum Underground Storage Tank Remediation, Upgrade & Closure Fund, must be certified in accordance with N.J.A.C. 7:14B-13.
The stated notice was to satisfy the requirements of N.J.S.A. 58:10A-37.5b, as it pertains to unregulated underground heating oil storage tanks. Please note, the following NJDEP cost guidance document was developed for both Unregulated Petroleum Underground Storage Tanks and Regulated Petroleum Underground Storage Tanks.
Respectfully,
Frank Pinto, Chief
Bureau of Contract & Fund Management
NJDEP
P.O. Box 413
401 East State Street
Trenton, NJ 0/8625 |
Alternate Format:
Adobe Acrobat [pdf 72 Kb]
Sections
|
Attachment G — UST Fund Cost Guide
Underground Storage Tank Removal/ Closure
(Unregulated & Regulated)
(All prices include excavation, cutting, cleaning, removal, & disposal) |
Flat Rate |
550 gallons or less |
$1,500 |
1000 gallons |
$2,100 |
1500 gallons |
$2,500 |
2000 gallons |
$2,600 |
3000 gallons |
$3,500 |
|
|
Above Ground Storage Tank (AST) Installation
(Unregulated Tanks, includes tank & labor) |
Flat Rate |
120 gallons |
$1,700 |
165 gallons |
$1,800 |
240 gallons |
$1,950 |
275 gallons |
$2,000 |
330 gallons |
$2,400 |
400 gallons |
$2,600 |
|
|
Underground Storage Tank Installation
(Unregulated only)
(Will only be reimbursed when AST Installations are not feasible.) |
Flat Rate |
290 - 550 gallons |
$3,000 |
1000 gallons |
$4,200 |
|
|
Municipal Services (Not subject to a subcontractor markup) |
Daily Rate |
Permits |
At Cost |
Police oversight |
At Cost |
|
|
Heavy Equipment |
Daily Rate |
Mobilization/demobilization - one time allowable per site per machine |
$500 |
Loader/backhoe w/operator (Mobilization/Demobilization applies) |
$950 |
Sm Trackhoe w/operator (J Deere 200LC or equivalent) (Mobilization/Demobilization applies) |
$1,400 |
Lg Trackhoe w/operator (Cat 325 or equivalent) (Mobilization/Demobilization applies) |
$1,700 |
Skid Steer Loader w/operator (Mobilization/Demobilization applies) |
$700 |
Field Vehicle with reusable tools |
$110 |
Dump Truck w/operator (approx. 12 yd3) |
$400 |
Dump Truck, Tandem - Triaxle w/operator (25 yd3) |
$900 |
Rolloff Box (20 yd3) |
$600 |
Vacuum Truck w/operator |
$800/day or $100/hr |
Geoprobe w/ Operator |
$1,800/ day or $1,000/half day |
GPR/Electrometer Survey |
$1,200 |
|
|
Labor/Personnel |
Hourly Rate |
Laborer |
$50 |
Equipment Operator |
$60 |
CADD Operator |
$60 |
Foreman |
$65 |
Environmental Technician |
$70 |
Staff Engineer / Scientist
/Subsurface Evaluator |
$80 |
Geologist/Hydrogeologist |
$85 |
Sr. Hydrogeologist/Professional Engineer |
$105 |
Project Manager (*) |
$110 |
Senior Project Manager (*) |
$125 |
Associate (*) |
$150 |
Principal (*) |
$175 |
* Total project management labor will be
capped at the following percentages based on the total project cost: |
|
20% allowable for jobs up to $10,000. |
|
15% allowable for jobs between $10,001 - $25,000 |
|
10% allowable for jobs $25,001 and higher. |
|
|
|
Material Disposal (Does not include transportation)
(Tasks in this section can be subject to subcontractor markup) |
Per Unit |
Non-Hazardous Petroleum Contaminated Soil |
$50/ton |
Disposal of Petroleum/Oil Contaminated Water |
$0.85/gallon |
Disposal of Gasoline Contaminated Water |
$1.00/gallon |
Backfill
(Tasks in this section can be subject to subcontractor markup) |
Per Unit |
Recycled Concrete Aggregate |
$15/ton |
Fill Material |
$20/ton |
Top Soil |
$25/cy |
|
|
Reports
Regulated Applications/ Licensed Site Remediation Program |
Flat Rate |
Closure Report without contamination |
$2,000 |
Closure Report with contamination |
$4,000 |
Preliminary Assessment Report |
$1,500 |
Site Investigation |
$2,000 |
Receptor Evaluation Report - Unregulated (Non-UHOT Cases) / Regulated / LSRP |
$1,200 |
IEC Response Action Report (Potable Well/Vapor Intrusion) |
$2,000 |
Remedial Investigation Report |
$3,000 |
Remedial Action Workplan |
$2,000 |
Remedial Action Report / Response Action Outcome |
$3,000 |
Structural Support Certification and plan (for cases that require structural support) |
$1,500 |
Facility Questionnaire and UST Registration |
$200 |
Groundwater Sampling Data Management |
$500/event |
Baseline Ecological Evaluation |
$1,200 |
Site Access Letters |
$250/event |
Open Public Records Request (File review) (not subject to markup) |
Actual invoice cost by OPRA |
|
|
Note: Report costs include all work associated with report, including, but not limited to, the preparation of all maps, tables, drawings, photocopies, postage, and all clerical and administrative support |
|
|
|
Reports
Unregulated Applications / Unregulated Heating Oil Tank Program |
Flat Rate |
Site Investigation/Remedial Investigation Report - (Non-UHOT Cases) |
$2,000 |
Receptor Evaluation Report - (Non-UHOT Cases) |
$1,200 |
Baseline Ecological Evaluation |
$1,200 |
Remedial Action Workplan - (Non-UHOT Cases) |
$2,000 |
Remedial Action Report |
$2,000 |
UHOT List Preparation (Not applicable for case that require direct NJDEP oversight) |
$500 |
Structural Support Certification and plan (for cases that require structural support) |
$1,500 |
Groundwater Sampling Data Management |
$500/event |
Potable Well Report |
$100/event |
Site Access Letters |
$250/event |
Open Public Records Request (File review) (not subject to markup) |
Actual invoice cost by OPRA |
|
|
Note: Report costs include all work associated with report, including, but not limited to, the preparation of all maps, tables, drawings, photocopies, postage, and all clerical and administrative support. |
|
|
|
Vapor Intrusion (Includes labor, equipment, sampling and reporting)
(Rates have been estimated for a total of four sites per task) |
Flat Rate |
Vapor Intrusion Remedial Investigation Workplan |
$2,000 |
Vapor Intrusion Indoor Air Building Survey |
$670 |
Vapor Intrusion Indoor Air Building Survey Update |
$250 |
Sub-slab Sampling |
$1,160 |
Indoor Air Sampling |
$1,900 |
Vapor Intrusion Report |
$2,000 |
|
|
Public Notification
Regulated / Licensed Site Remediation Program Cases only |
Flat Rate |
Signage or letters |
$100 |
Fact sheet preparation |
$360 |
Newspaper Publishing |
As invoiced
(No markup will be allowed) |
|
|
Health and Safety |
|
Health and Safety Plan |
$250.00 |
|
|
Equipment/Instrumentation
(Tasks in this section can be subject to subcontractor markup) |
Per Day/ Per Week |
PID |
$75/day or $200/week |
FID |
$85/day or $250/week |
Four Gas Meter |
$100/day or $300/week |
Remediation Product Skimming Pump |
$75/day or $225/week |
Pump-Bladder QED SampPro 1.75, Controller QED MP10, & Compressor 3020 12V DC |
$150/day or $450/week |
Grundfos Pump w/controller |
$95/day or $290/week |
Generator |
$45/day or $135/week |
Oil/Water Probe |
$45/day or $140/week |
Data Logger (Hermit 3000 or equivalent) |
$125/day or $375/week |
Transducer |
$35/day or $105/week |
Water Quality Meter |
$100/day or $300/week |
Air Temp/Barometric Pressure Meter |
$75.00/day or $200/week |
Jack Hammer w/compressor |
$150/day or $400/week |
Welding Equipment |
$75/day or $200/week |
Concrete Mixer |
$50/day or $150/week |
Mechanical Auger |
400/day |
Bailer 1' or 3' |
$5/each |
Plastic Sheeting |
$75/roll |
Low Density Polyethylene Tubing .17x1/4" (used with QED Bladder Pump) |
$.60/foot |
Vibratory Plate Compactor / Tamper |
$55/day or $200/week |
Poly Bladder Kit Includes: poly bladder, set of o-rings, & SS Grab Plate used with QED Bladder Pump |
$22/ each |
3/8" Polyvinyl or Polyurethane Tubing 100' |
$25/roll |
3/8" Polyvinyl or Polyurethane Tubing 500' |
$125/roll |
Single Whale Pump for 3/8" tubing |
$10/day |
Double Whale Pump for 3/8" tubing |
$15/day |
Car battery for whale pump |
$5/day |
Hand Auger w/12' extension |
$12/day |
55-Gallon Drums |
$45/each |
|
|
Well Survey (This task can be subject to subcontractor markup) |
$1,500/day |
|
|
Well Installation (Includes labor)
(Tasks in this section can be subject to subcontractor markup) |
Flat Rate |
Shallow Unconsolidated (approx. 20ft. deep) |
$2,500 |
Shallow Bedrock (approx. 20ft. deep) |
$4,000 |
Deep Wells |
Site Specific |
Temporary Geoprobe Well Point |
$600 |
|
|
Well Abandonment / Sealing
(This task can be subject to subcontractor markup) |
$600 |
|
|
Laboratory Analytical Fee Schedule
(Tasks in this section can be subject to subcontractor markup) |
Per Sample |
Diesel Range Organics (DRO) |
$120 |
VOCs+10 |
$140 |
BN+15 |
$170 |
PAH |
$125 |
PP Metals |
$125 |
Lead |
$30 |
Electronic Data Deliverables (Only if required by the NJDEP) |
$20/diskette |
Methanol or Encore sampler |
$10/each |
Scale for methanol only |
$10/day |
|
|
Waste Classification
(Tasks in this section can be subject to subcontractor markup) |
Per Sample |
Full TCLP & ID27 |
$800 |
ID27(Full TCLP+RCRA+others) |
$1,100 |
|
|
Site Restoration |
Site Restoration costs are limited to damage caused by the remediation of leaking USTs. No restoration costs due contractor negligence will be considered. Eligible costs for certain site restoration categories are capped at $5,000 each. These categories include landscaping, hardscaping, costs associated with deck removal and or replacement, and costs associated with swimming pool removal or replacement. These categories are described further as follows:
- Landscaping - This category includes lawn restoration, bushes, shrubs, trees, flower beds, edging, mulch, etc. Note that replacement of plantings will not necessarily be with mature plants.
- Hardscaping - This category includes paver, brick or cement walkways, patios, and decorative walls of any construction, and loose stone used for decorative purposes.
- Decking costs - This category includes the need to dismantle, remove, and replace a portion or the entirety of a wooden or composite deck in order to effectuate a remediation.
- Pool costs - This category includes the need to dismantle, remove and replace a portion or the entirety of a swimming pool in order to effectuate remediation.
The UST Fund also has the right to cap other categories of restoration costs that are not directly related to the structural integrity of the home in question. In addition, for restoration costs that are eligible, the UST Fund will only reimburse for replacement of what existed prior to the remediation up to the cap amount. Applicant is responsible for obtaining a minimum of three (3) price quotes for any restoration work. Before and after photos are strongly recommended.
|
Ineligible UST Fund Costs |
- NJDEP Oversight Costs/ Fixed Fees
- Performance Guarantees
- Preparation of UST Fund application
- Administration and management of funds.
- Repair of damages caused by subcontractor/consultant due to negligence.
- Costs associated with ASTs (ie. AST tubs, roofs or housing) (except replacement for leaking UST).
- Items not totally expended at one site (i.e., hand tools, temporary fencing, rain gear, etc.).
- Rush turnaround times for sampling (unless required by the NJDEP)
- Temporary relocation of residency (Displacement due to Remediation)
- Meals and lodging.
- Tank tightness/leak detection testing.
- Subcontractor cost markup exceeding 15%.
- Legal fees, except as determined necessary for remediation by NJDEP (i.e., offsite access).
- State NJDEP permit fees (local permit fees are reimbursable).
- Costs for preparation of appeal letters for denied costs.
- Office administration costs including but not limited to faxes, copying, postage/FedEx, etc.
- Fuel surcharge & More than one field vehicle
- Work completed by uncertified firm
|
|
 |