Notice is hereby given that the Delaware River Basin Commission ("Commission") received a request for extension of the below-listed docket approval and accepted written comment on this request through the date set forth below.
- Docket No.: D-2017-009-2
- Issued on: June 12, 2019
- Issued to: Delaware River Partners LLC
- Issued for: Gibbstown Logistics Center Dock 2, Greenwich Township, Gloucester County, N.J.
- Previously Extended through: June 12, 2025
- Issued on: June 12, 2019
- Comment Deadline: 5 p.m., Thursday, April 24
Instructions to Submit Written Comment
- Written comments were submitted via our web-based collection system, Smart Comment.
- Written comments on this extension request were accepted through 5 p.m. on Thursday, April 24, 2025.
- Use of the web-based system ensured that all submissions were captured in a single location and their receipt was acknowledged. Exceptions to the use of this system were available based on need, by writing to the attention of the Commission Secretary, DRBC, P.O. Box 7360, 25 Cosey Road, West Trenton, NJ 08628-0360.
- For assistance, please email contact@drbc.gov
Related Documents (all pdfs, except where noted)
- Letter from Docket Holder Requesting Extension (March 14, 2025)
- DRBC Resolution for the Minutes of Sept. 8, 2022 (extending docket through June 12, 2025)
- DRBC Resolution for the Minutes and Opinion of Dec. 9, 2020 (affirming June 12, 2019, docket approval)
- DRBC Docket D-2017-009-2 (issued June 12, 2019)
- Supplemental Materials from Docket Holder
- Docket Holder Request for Extension of USACE Section 404/Section 10 Permit (September 19, 2024)
- New Jersey DEP Letter Extending Waterfront Development In-Water Permit (May 23, 2024)
- USACE Section 404/Section 10 Permit (issued January 25, 2020)
- New Jersey DEP Waterfront Development In-Water Permit (issued May 20, 2019)
- Docket Holder Ledger Entries (xlsx)
- Docket Holder Request for Extension of USACE Section 404/Section 10 Permit (September 19, 2024)
Background
The Commission approved the GLC Dock 2 project under Section 3.8 of the Compact after a public hearing and an additional, months-long, evidentiary hearing, based on the Commission's determination that the project, as limited by the conditions in the Docket, did not impair or conflict with the Comprehensive Plan. In accordance with the regulation governing requests for extension, no additional public hearing will be provided unless three or more Commission members ask the Executive Director in writing to schedule one or vote during a public meeting of the Commission to provide one. See Rules of Practice and Procedure, 18 C.F.R. 401.41(a)(4).