Governor Phil Murphy • Lt. Governor Tahesha Way
  Search
new jersey department of environmental protection
NJ Home Page Services A to Z NJ FAQs NJ Departments/Agencies departments
site remediation program

SRP Home | DEP Home

Community Relations Community Relations Site List NJNG Long Branch Site October 2005 Update

 

New Jersey Natural Gas (NJNG) Long Branch Plant Site Update

Long Branch, Monmouth County
October 2005

This report is provided in response to a request by the Concerned Citizens Coalition of Long Branch (CCC) for monthly updates on work conducted and planned at four areas associated with the former Long Branch Manufactured Gas Plant (MGP).* These areas are:

  • the former MGP (including the former Conrail properties, the eastern off-site property, and the former Jerry Morgan Park)
  • the off-site portion of Troutmans Creek that flows north of the MGP
  • residential areas where the community has expressed concern about potential soil contamination (Long Branch Avenue, Seaview Avenue, Grant Court and Ellis Avenue)
  • the former Seaview Manor housing complex

All work is consistent with NJDEP's Technical Requirements for Site Remediation, which were developed to ensure remedial actions protect human health and the environment.

* For historical information about activities that NJDEP and NJNG have conducted at these areas, please refer to the monthly updates NJDEP has provided to CCC since January 2005.

1) Long Branch Plant

Red Brick Building
In October 2005 NJNG began field activities to delineate the extent of trichloroethene (TCE) and perchloroethylene (PCE) contamination in the soil beneath the concrete pad where the red brick building was located, and ground water sampling to evaluate potential ground water impacts. NJNG is currently under schedule to submit a Remedial Action Work Plan (RAWP) to address the subsurface soils in November 2005. However, NJNG did not begin the field activities for this area of the site until October, therefore NJDEP anticipates that NJNG will request an extension for submission of the RAWP. The remedy would essentially consist of removing the remaining concrete slabs, any underground storage tanks (if they exist), and contaminated soil, followed by capping the area consistent with the rest of the site. If ground water impacts are found, they will be addressed as part of the site-wide ground water remedial action.

Soil Gas Investigation
In August 2005 NJNG submitted a Sub-Slab Sampling Remedial Investigation Work Plan (RIWP), which detailed proposals to investigate potential vapor intrusion at the Talco and Atlantic Plumbing Supply Company (APSC) buildings. NJDEP issued a letter conditionally approving the RIWP on September 20, 2005. Due to problems getting access to the APSC property, as October 2005, NJNG had not started field activities for this phase of the site investigation. NJDEP has received verbal notice that NJNG recently reached a settlement agreement with APSC. NJNG plans to begin the soil gas investigation in November. The Talco building will be addressed at a minimum and the APSC building may also be included given the recent settlement. NJDEP expects to receive a Remedial Investigation Report (RIR) summarizing the findings of the soil gas investigation in early 2006.

Ground Water Investigation
In September 2005 NJDEP conditionally approved NJNG’s Remedial Investigation Work Plan/Ground Water Pilot Test Work Plan, which contained proposals to delineate the dense non-aqueous phase liquid (DNAPL) and conduct ground water treatment studies. NJDEP issued a letter on October 27, 2005 informing NJNG that they were not in compliance with the Administrative Consent Order when field activities did not proceed in accordance with the approved schedule. However, NJNG has informed NJDEP they will begin field activities in November and still expect to meet their deadline of March 6, 2005 for submission of a combined Remedial Investigation Report/Remedial Action Work Plan to address site-wide ground water issues.

On-Site Portion of Troutmans Creek
Remediation of the southern on-site portion of the Troutmans Creek is pending, as this work could not be implemented until NJNG obtained access from the owner of Atlantic Plumbing Supply Company property. NJDEP received verbal notice from NJNG that a settlement was recently reached so the scheduling of the start of this work may now be pursued.

2) Troutmans Creek

On August 8, 2005 NJNG submitted an RIR summarizing the results of the creek sampling it conducted since March 2004. NJDEP is reviewing the report and expects to issue comments in late December 2005.

3) Off-Site Residential Areas

NJDEP collected soil samples from the right-of-ways along Long Branch Avenue, Seaview Avenue and Ellis Avenue and from Grant Court in May 2005. These samples were analyzed for volatile organic compounds, semi-volatile organic compounds, total petroleum hydrocarbons and metals. NJDEP expects to issue an RIR detailing its findings in late December 2005.

4) Seaview Manor

NJNG finished removing the contaminated soil from areas where buildings are to be re-built, and a minimum of two feet of contaminated soil from the other areas. These areas were re-graded and re-seeded in late August/early September. NJNG submitted the Remedial Action Report (RAR) for Block 400, Lot 7 in September 2005. The RAR describes the restricted and unrestricted use remedial actions that were completed at this parcel. NJDEP expects to finish reviewing this RAR in late December 2005. A separate RAR for the remainder of the parcels will be submitted in January 2006, with the exception of the culvert (see below).

Culvert Status
NJNG removed two feet of soil from the culvert area and capped it during the remedial action for Block 400, Lots 6 and 7. The removal of the culvert and any underlying contamination will occur in the spring and summer of 2006.