Question 1: Can the schedule, org chart and 2 “EXTRA 8 ½”x 11” PAGES” be fold out 11x17 pages?
Answer 1: Yes.
Question 2: Can the pavement design requirement be removed from the Geotechnical Engineer team leader since it’s a requirement of the Pavement Engineer team leader?
Answer 2: Yes.
Question 3: Can a Bachelor of Technology in Transportation with a NJ PE License fulfill the BS Engineering requirement for Utility Task Leader?
Answer 3: Yes.
Question 4: Should the Technical Write-up be between 4 and 7 pages or should it be 7 pages exactly?
Answer 4: The Key Issues write up can be a minimum of 4 pages and a maximum of 7 pages.
Question 5: Do you need to meet all listed experience requirements on all projects to receive full points for PM and Team Leader positions?
Answer 5: No, the requirements can be met cumulatively across more than one project.
Question 6:
Is it possible to download copies of the following documents which were referenced within the Final CD Report but were not provided as part of that Report:
- 2006-2013 Mine Reports for Bull Frog Mine (Avalon Bay Development), various authors
- January 2006 Geotechnical Assessment of Route 80 Exit 34, French Parrello
Answer 6: Discs with the Avalon Bay Bull Frog Mine Report, Mine Subsidence Report, Appendix B - As Builts, Photos, Assist Me Analysis & Memo, and US Army Sewer Plans & Photos will be available for pick up from the Main Office Building Security Desk. An email requesting the disc must be sent to PSPD.PSPD@dot.nj.gov 1 business day prior to pick up. The closing Date will also be extended to 7/21/15.
Question 7: Can the asbuilts for the following structures be made available? 1412-177, 1412-178, 1403-152, 1404-156
The asbuilts are stated to be in Appendix B, but it only lists the bridges and states that the plans are on the CD submitted with the report
Answer 7: Discs with the Avalon Bay Bull Frog Mine Report, Mine Subsidence Report, Appendix B - As Builts, Photos, Assist Me Analysis & Memo, and US Army Sewer Plans & Photos will be available for pick up from the Main Office Building Security Desk. An email requesting the disc must be sent to PSPD.PSPD@dot.nj.gov 1 business day prior to pick up. The closing Date will also be extended to 7/21/15.
Question 8: Can someone with a degree in geological engineering (BS, MS, PhD) and NJ Professional Engineer, practicing geotechnical/pavement disciplines for more than 30 years meet all the qualifications requirements (Section 9) for the pavement design task leader?
Answer 8: Yes.
|