Creek Road (County Route 753) over Route 42

October 2013 photo
October 2013
This view is looking west at Creek Road over Route 42.

July 2014 photo
July 2014
This view is looking west at Creek Road over Route 42. The
new pedestrian bridge is in operation to the right of Creek Road.

February 2015 photo
February 2015
This view is looking west on
Creek Road over Route 42. The two lane bridge is in
operation on the southern half of the bridge while the northern half
of the bridge was demolished and the new half of the bridge is under construction.

May 2015 photo
May 2015
This view is looking west on Creek Road over Route 42.
The two lane bridge is in operation on the southern half of the
bridge. The northern half of the bridge is under construction
with the new bridge reinforcement in place and awaiting the concrete pour.

August 2015 photo
August 2015
This view is looking west on Creek Road over Route 42.
The northern half of the new bridge is in operation (two lanes).
The southern half of the old bridge is removed and the bridge
abutments are being demolished in anticipation of construction
of the new southern half of the bridge.

November 2015 photo
November 2015
This view is looking west on Creek Road over Route 42.
The northern half of the new bridge is in operation (two lanes).
Construction of the new southern half of the bridge is in progress.
The new abutments and the center pier are in
place awaiting structural steel installation.


Last updated date: November 13, 2020 8:37 AM