Department of Transportation

Retaining Wall 19 along
Route 42 southbound ramp to I-295 southbound
(near Bellmawr Little League®)

2012
This view is looking north along Route 42 (northbound
traffic on right) with the Route 42 southbound ramp to
I-295 southbound near the baseball fields. The future
retaining wall will be located along the right side of the ramp

July 2013
This view is looking south at the Route 42 southbound
ramp to I-295 southbound. Clearing is underway
and the temporary noise barrier is in place.

October 2013
This view is looking south at the Route 42 southbound ramp to
I-295 southbound. Temporary sheeting is in place for the new
pipe crossing under Route 42 before Retaining Wall 19 is built.

July 2014
This view is looking south at the Route 42
southbound ramp to I-295 southbound.
Th new pipe crossing under Route 42 is completed.
October 2014
This view is looking east along Route 42 (southbound traffic in foreground) with the new retaining wall
in place and the new noise barrier being set on top of the new wall along Route 42 northbound.
February 2015
This view is looking west at the Route 42 southbound ramp to
I-295 southbound with Retaining Wall 19 construction underway.
November 2015
This view is looking west at the Route 42 southbound ramp to
I-295 southbound with Retaining Wall 19 construction
proceeding and nearing completioin.


Last updated date: November 13, 2020 10:24 AM