| June 23 to July 30, 2006 - Completed |
| Work: |
Remove the center median barrier, sign structure and its associated support (west of bridge), install temporary drainage and pave inside shoulder areas for temporary traffic. |
| |
| Traffic shift: |
Two eastbound lanes and two westbound lanes will be maintained throughout the project limits. The eastbound and westbound lanes will be shifted to the outermost lanes to provide a work area in the median of the Stickel Bridge and portions of I-280. |
| |
| July 2006 to January 2007 - Completed |
| Work: |
Northern part of bridge |
| |
| Traffic shift: |
Two eastbound lanes and two westbound lanes will be maintained throughout the project limits. The westbound lanes will be shifted to the south adjacent to the eastbound lanes. |
| |
| January 2007 to August 2007 - Completed |
| Work: |
Southern part of bridge |
| |
| Traffic shift: |
Two eastbound lanes and two westbound lanes will be maintained throughout the project limits. The eastbound and westbound lanes will be shifted to the north. |
| |
| August 2007 to November 2007 - Completed |
| Work: |
Median of bridge |
| |
| Traffic shift: |
Two eastbound lanes and two westbound lanes will be maintained throughout the project limits. The eastbound and westbound lanes will be shifted to the outermost lanes. |
| |
| November 2007
- April 2009 - Completed |
| Work: |
Mechanical work |
| |
| Traffic shift: |
Two eastbound lanes and two westbound lanes will be maintained during periodic single daytime lane closures. One lane in each direction will be maintained during periodic double nighttime lane closures. |
| |