This is I-295 Northbound before Route 561. All lanes have been reopened in this section of the project. The contractor is scheduled to pave the final course of asphalt in Summer 2004.
|
 |
Getting ready for a concrete pour, this is the form work and reinforcing steel of the center pier on I-295 Southbound over Route 70 (Eastbound on left, Westbound on right).
|
 |
The bridge demolition at I-295 Northbound over Route 70 is in the final stage of construction. The right lane and outside shoulder of this structure will be reconstructed in Spring 2004.
|
 |
The excavator is removing the existing left lane of I-295 Northbound in the vicinity of Route 73. The existing roadway will be completely removed and reconstructed in this section of the project.
|
 |
Construction in this section of the project, I-295 Southbound between Route 73 and 38, entails building a new inside shoulder and overlaying the existing road with asphalt.
|