Dewatering
For temporary ground and surface water control (dewatering) diversions in excess of 100,000* gallons of water per day, the project owner must obtain a Dewatering Allocation Permit, or Dewatering Permit-by-Rule or Short Term Permit-by-Rule depending on the duration of the diversion and the method employed.
* At the 100,000 gallons per day threshold additional approvals for water diversion may be required by the Delaware River Basin Commission and the New Jersey Pinelands Commission.
Dewatering
The Temporary Dewatering Permit Application (BWA-002) has been updated. Effective June 1, 2017, any application not submitted on the new form will be returned.
Permit Application Progress/Status
Diversion Monitoring and Reporting
Guidance and Information
USGS Resources You May Need |
|